| Modelo (WBS) |
Presupuesto Base |
Ajustes | PSP Ajustado |
Anticipos | Costo Real |
Costo Ajustado |
% Part | % Part A | % Av Fin |
% Av Fis |
Variación % |
Valor Ganado |
Ejecutado | Variación Q |
CPI | % CPI | EAC | VAC | % VAC | Ingreso | Margen Bruto |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ordenado por 80/20 (Peor CPI primero) | |||||||||||||||||||||
|
BOCONIA RESIDENCIALES
|
- | - | - | - | - | - | 100.00% | 100.00% | 89.36% | 80.78% | -8.58% | - | - | - | 0.90 | 9.61% | - | - | -10.63% | - | 0.00% |
|
SALON SOCIAL
|
- | - | - | - | - | - | 2.14% | 2.13% | 97.56% | 44.51% | -53.05% | - | - | - | 0.46 | 54.38% | - | - | -119.18% | - | 0.00% |
|
CASA CLUB
|
- | - | - | - | - | - | 2.14% | 2.13% | 97.56% | 44.51% | -53.05% | - | - | - | 0.46 | 54.38% | - | - | -119.18% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.29% | 0.28% | 62.83% | 1.00% | -61.83% | - | - | - | 0.02 | 98.41% | - | - | -6183.49% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.14% | 0.13% | 111.70% | 1.00% | -110.70% | - | - | - | 0.01 | 99.10% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.14% | 0.13% | 111.70% | 1.00% | -110.70% | - | - | - | 0.01 | 99.10% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.12% | 0.12% | 122.58% | 1.00% | -121.58% | - | - | - | 0.01 | 99.18% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 1.00% | 1.00% | - | - | - | 36.54 | -3554.49% | - | - | 97.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.16% | 0.15% | 20.42% | 1.00% | -19.42% | - | - | - | 0.05 | 95.10% | - | - | -1941.76% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 596.00% | 1.00% | -595.00% | - | - | - | 0.00 | 99.83% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.52 | 47.99% | - | - | -92.27% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 2275.19% | 1.00% | -2274.19% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 71.13% | 1.00% | -70.13% | - | - | - | 0.01 | 98.59% | - | - | -7013.19% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 10.30% | 1.00% | -9.30% | - | - | - | 0.10 | 90.29% | - | - | -930.15% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 879.01% | 1.00% | -878.01% | - | - | - | 0.00 | 99.89% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 43.69% | 1.00% | -42.69% | - | - | - | 0.02 | 97.71% | - | - | -4269.09% | - | 0.00% |
|
BROCAS PARA MADERA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 1.00% | 1.00% | - | - | - | 23.70 | -2270.38% | - | - | 95.78% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 13.08% | 1.00% | -12.08% | - | - | - | 0.08 | 92.35% | - | - | -1207.80% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 15.07% | 1.00% | -14.07% | - | - | - | 0.07 | 93.37% | - | - | -1407.35% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 1.00% | 1.00% | - | - | - | 47.53 | -4652.75% | - | - | 97.90% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.27 | 73.32% | - | - | -274.81% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.27 | 73.32% | - | - | -274.81% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 14.86 | -1386.14% | - | - | 93.27% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 14.86 | -1386.14% | - | - | 93.27% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 1.00% | 1.00% | - | - | - | 16.12 | -1512.37% | - | - | 93.80% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 1.00% | 1.00% | - | - | - | 16.12 | -1512.37% | - | - | 93.80% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 1.00% | 1.00% | - | - | - | 104.81 | -10381.28% | - | - | 99.05% | - | 0.00% |
|
IMPERMEABILIZANTE
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 1.00% | 1.00% | - | - | - | 104.81 | -10381.28% | - | - | 99.05% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 1.00% | 1.00% | - | - | - | 225.10 | -22409.70% | - | - | 99.56% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 1.00% | 1.00% | - | - | - | 225.10 | -22409.70% | - | - | 99.56% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 1" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 1.55 | -55.26% | - | - | 35.59% | - | 0.00% |
|
('EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 1.55 | -55.26% | - | - | 35.59% | - | 0.00% |
|
ANDAMIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 1.00% | 1.00% | - | - | - | 1.55 | -55.26% | - | - | 35.59% | - | 0.00% |
|
PRELIMINARES
|
- | - | - | - | - | - | 0.03% | 0.02% | 891.52% | 100.00% | -791.52% | - | - | - | 0.11 | 88.78% | - | - | -791.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 101148.17% | 100.00% | -101048.17% | - | - | - | 0.00 | 99.90% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 15555.19% | 100.00% | -15455.19% | - | - | - | 0.01 | 99.36% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 15555.19% | 100.00% | -15455.19% | - | - | - | 0.01 | 99.36% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO - MAT + MO / ELECTRICIDAD ESPECIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SUMINISTRO E INSTALACION HIDRAULICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.67% | 100.00% | -69.67% | - | - | - | 0.59 | 41.06% | - | - | -69.67% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.67% | 100.00% | -69.67% | - | - | - | 0.59 | 41.06% | - | - | -69.67% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1944.94 | -194394.00% | - | - | 99.95% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 65.61% | 100.00% | 34.39% | - | - | - | 1.52 | -52.42% | - | - | 34.39% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 13.01 | -1201.00% | - | - | 92.31% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 13.01 | -1201.00% | - | - | 92.31% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 66.38 | -6538.00% | - | - | 98.49% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 66.38 | -6538.00% | - | - | 98.49% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON TRANSPARENTTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMENTO PVC GALON
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5591.47 | -559047.00% | - | - | 99.98% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5591.47 | -559047.00% | - | - | 99.98% | - | 0.00% |
|
CIMENTACION
|
- | - | - | - | - | - | 0.19% | 0.18% | 167.48% | 100.00% | -67.48% | - | - | - | 0.60 | 40.29% | - | - | -67.48% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 259.09% | 100.00% | -159.09% | - | - | - | 0.39 | 61.40% | - | - | -159.09% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 259.09% | 100.00% | -159.09% | - | - | - | 0.39 | 61.40% | - | - | -159.09% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.05% | 0.05% | 188.16% | 100.00% | -88.16% | - | - | - | 0.53 | 46.85% | - | - | -88.16% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3922.16 | -392116.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 114.28% | 100.00% | -14.28% | - | - | - | 0.88 | 12.50% | - | - | -14.28% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1144.34% | 100.00% | -1044.34% | - | - | - | 0.09 | 91.26% | - | - | -1044.34% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.95 | -50595.00% | - | - | 99.80% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.03% | 100.00% | -74.03% | - | - | - | 0.57 | 42.54% | - | - | -74.03% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 686.10 | -68510.00% | - | - | 99.85% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 155.03% | 100.00% | -55.03% | - | - | - | 0.65 | 35.50% | - | - | -55.03% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 155.03% | 100.00% | -55.03% | - | - | - | 0.65 | 35.50% | - | - | -55.03% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 135.87% | 100.00% | -35.87% | - | - | - | 0.74 | 26.40% | - | - | -35.87% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5400.08 | -539908.00% | - | - | 99.98% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 19050.46 | -1904946.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 5.74% | 100.00% | 94.26% | - | - | - | 17.41 | -1641.24% | - | - | 94.26% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.91% | 100.00% | 29.09% | - | - | - | 1.41 | -41.02% | - | - | 29.09% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 583.75 | -58275.00% | - | - | 99.83% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5872.13 | -587113.00% | - | - | 99.98% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1205.18 | -120418.00% | - | - | 99.92% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.89% | 100.00% | 19.11% | - | - | - | 1.24 | -23.63% | - | - | 19.11% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.62 | -2662.00% | - | - | 96.38% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.62 | -2662.00% | - | - | 96.38% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 122.46 | -12146.00% | - | - | 99.18% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 122.46 | -12146.00% | - | - | 99.18% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 537.16 | -53616.00% | - | - | 99.81% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 396.44 | -39544.00% | - | - | 99.75% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 140.72 | -13972.00% | - | - | 99.29% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1470.58 | -146958.00% | - | - | 99.93% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1208.69 | -120769.00% | - | - | 99.92% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 261.89 | -26089.00% | - | - | 99.62% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LOSAS
|
- | - | - | - | - | - | 0.47% | 0.46% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.27% | 0.26% | 126.09% | 100.00% | -26.09% | - | - | - | 0.79 | 20.69% | - | - | -26.09% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9096.08% | 100.00% | -8996.08% | - | - | - | 0.01 | 98.90% | - | - | -8996.08% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.96 | -2496.00% | - | - | 96.15% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 18221.26% | 100.00% | -18121.26% | - | - | - | 0.01 | 99.45% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1300.89% | 100.00% | -1200.89% | - | - | - | 0.08 | 92.31% | - | - | -1200.89% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1300.89% | 100.00% | -1200.89% | - | - | - | 0.08 | 92.31% | - | - | -1200.89% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 540.67% | 100.00% | -440.67% | - | - | - | 0.18 | 81.50% | - | - | -440.67% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 329.51 | -32851.00% | - | - | 99.70% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1247.16 | -124616.00% | - | - | 99.92% | - | 0.00% |
|
FORMALETA DE MADERA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 402.84 | -40184.00% | - | - | 99.75% | - | 0.00% |
|
PARALES DE 3" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.01% | 0.01% | 479.60% | 100.00% | -379.60% | - | - | - | 0.21 | 79.15% | - | - | -379.60% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 177.17% | 100.00% | -77.17% | - | - | - | 0.56 | 43.56% | - | - | -77.17% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11715.63 | -1171463.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.05% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 13791.51 | -1379051.00% | - | - | 99.99% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 101.57% | 100.00% | -1.57% | - | - | - | 0.98 | 1.54% | - | - | -1.57% | - | 0.00% |
|
BLOCK DE 19X19X19.5 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 126.66 | -12566.00% | - | - | 99.21% | - | 0.00% |
|
BLOCK POMEZ DE 20X20X40CM
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.17% | 100.00% | -6.17% | - | - | - | 0.94 | 5.81% | - | - | -6.17% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 54.32% | 100.00% | 45.68% | - | - | - | 1.84 | -84.11% | - | - | 45.68% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9068.79 | -906779.00% | - | - | 99.99% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.01% | 0.01% | 69.15% | 100.00% | 30.85% | - | - | - | 1.45 | -44.61% | - | - | 30.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.01% | 79.01% | 100.00% | 20.99% | - | - | - | 1.27 | -26.56% | - | - | 20.99% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.78% | 100.00% | 18.22% | - | - | - | 1.22 | -22.27% | - | - | 18.22% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 27.91% | 100.00% | 72.09% | - | - | - | 3.58 | -258.34% | - | - | 72.09% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.05% | 0.05% | 87.02% | 100.00% | 12.98% | - | - | - | 1.15 | -14.92% | - | - | 12.98% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3424.84 | -342384.00% | - | - | 99.97% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1342.43 | -134143.00% | - | - | 99.93% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 13.32 | -1232.00% | - | - | 92.49% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 13.32 | -1232.00% | - | - | 92.49% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 312.87 | -31187.00% | - | - | 99.68% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 312.87 | -31187.00% | - | - | 99.68% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3311.65 | -331065.00% | - | - | 99.97% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2522.53 | -252153.00% | - | - | 99.96% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 789.12 | -78812.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.20% | 0.20% | 112.04% | 100.00% | -12.04% | - | - | - | 0.89 | 10.74% | - | - | -12.04% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.20% | 0.20% | 112.04% | 100.00% | -12.04% | - | - | - | 0.89 | 10.74% | - | - | -12.04% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.19% | 0.18% | 110.72% | 100.00% | -10.72% | - | - | - | 0.90 | 9.68% | - | - | -10.72% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 4091.18 | -409018.00% | - | - | 99.98% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 102.70% | 100.00% | -2.70% | - | - | - | 0.97 | 2.63% | - | - | -2.70% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 102.70% | 100.00% | -2.70% | - | - | - | 0.97 | 2.63% | - | - | -2.70% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.01% | 0.01% | 102.70% | 100.00% | -2.70% | - | - | - | 0.97 | 2.63% | - | - | -2.70% | - | 0.00% |
|
MUROS
|
- | - | - | - | - | - | 0.29% | 0.28% | 108.17% | 100.00% | -8.17% | - | - | - | 0.92 | 7.56% | - | - | -8.17% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 135.38% | 100.00% | -35.38% | - | - | - | 0.74 | 26.13% | - | - | -35.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 135.38% | 100.00% | -35.38% | - | - | - | 0.74 | 26.13% | - | - | -35.38% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.14% | 0.14% | 136.56% | 100.00% | -36.56% | - | - | - | 0.73 | 26.77% | - | - | -36.56% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 382.29 | -38129.00% | - | - | 99.74% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.15% | 0.14% | 81.57% | 100.00% | 18.43% | - | - | - | 1.23 | -22.59% | - | - | 18.43% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.02% | 0.01% | 189.41% | 100.00% | -89.41% | - | - | - | 0.53 | 47.20% | - | - | -89.41% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 64.92 | -6392.00% | - | - | 98.46% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1312.93 | -131193.00% | - | - | 99.92% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.01% | 0.01% | 270.55% | 100.00% | -170.55% | - | - | - | 0.37 | 63.04% | - | - | -170.55% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.03% | 0.02% | 125.91% | 100.00% | -25.91% | - | - | - | 0.79 | 20.58% | - | - | -25.91% | - | 0.00% |
|
BLOCK DE 14X19X39 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 14X19X39 - 100 KGS/CM2
|
- | - | - | - | - | - | 0.03% | 0.02% | 91.22% | 100.00% | 8.78% | - | - | - | 1.10 | -9.63% | - | - | 8.78% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.06% | 0.05% | 73.04% | 100.00% | 26.96% | - | - | - | 1.37 | -36.91% | - | - | 26.96% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.33% | 100.00% | 28.67% | - | - | - | 1.40 | -40.19% | - | - | 28.67% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 113.58 | -11258.00% | - | - | 99.12% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 113.48% | 100.00% | -13.48% | - | - | - | 0.88 | 11.88% | - | - | -13.48% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 99.48% | 100.00% | 0.52% | - | - | - | 1.01 | -0.52% | - | - | 0.52% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 97.58% | 100.00% | 2.42% | - | - | - | 1.02 | -2.48% | - | - | 2.42% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.01% | 0.01% | 19.13% | 100.00% | 80.87% | - | - | - | 5.23 | -422.87% | - | - | 80.87% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.02% | 49.57% | 100.00% | 50.43% | - | - | - | 2.02 | -101.72% | - | - | 50.43% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 69.50% | 100.00% | 30.50% | - | - | - | 1.44 | -43.88% | - | - | 30.50% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 112.39% | 100.00% | -12.39% | - | - | - | 0.89 | 11.03% | - | - | -12.39% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.02% | 0.02% | 53.95% | 100.00% | 46.05% | - | - | - | 1.85 | -85.37% | - | - | 46.05% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 232.02 | -23102.00% | - | - | 99.57% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 232.02 | -23102.00% | - | - | 99.57% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 739.54 | -73854.00% | - | - | 99.86% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 739.54 | -73854.00% | - | - | 99.86% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1953.85 | -195285.00% | - | - | 99.95% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1441.99 | -144099.00% | - | - | 99.93% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 511.86 | -51086.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2123.87 | -212287.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1301.19 | -130019.00% | - | - | 99.92% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 822.68 | -82168.00% | - | - | 99.88% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2354.73 | -235373.00% | - | - | 99.96% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2354.73 | -235373.00% | - | - | 99.96% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 192.00 | -19100.00% | - | - | 99.48% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 192.00 | -19100.00% | - | - | 99.48% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 192.00 | -19100.00% | - | - | 99.48% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.87% | 0.90% | 58.31% | 0.00% | -58.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ANDAMIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.19% | 0.23% | 35.28% | 0.00% | -35.28% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 103.55% | 0.00% | -103.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 CORRUGADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 109.54% | 0.00% | -109.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 394.27% | 0.00% | -394.27% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 494.31% | 0.00% | -494.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.01% | 0.00% | -79.01% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 11.72% | 0.00% | -11.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.43% | 0.00% | -110.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 246.75% | 0.00% | -246.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 25.87% | 0.00% | -25.87% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.01% | 0.01% | 69.40% | 0.00% | -69.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 277.94% | 0.00% | -277.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 995.31% | 0.00% | -995.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 131.35% | 0.00% | -131.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 121.88% | 0.00% | -121.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 342.64% | 0.00% | -342.64% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.13% | 0.00% | -88.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 1" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 30.68% | 0.00% | -30.68% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.06% | 0.00% | -26.06% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.29% | 0.00% | -2.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAFLEX 1A GRIS 300 ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BANDEJA PARA PINTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANERAL PARA PINTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.24% | 0.00% | -12.24% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGLA DE 3"X2"X8'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FORMALETA DE MADERA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA SIN RODILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA MUROS MO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 166.41% | 0.00% | -166.41% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO BRASILIA DE 43 X 43
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1116.19% | 0.00% | -1116.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 28.87% | 0.00% | -28.87% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 23.59% | 0.00% | -23.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO CERAMICO 20X30
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA AVELLANA MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 5057.85% | 0.00% | -5057.85% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 796.55% | 0.00% | -796.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE ARENA CON ARENA COLOR CHOCOLATE
|
- | - | - | - | - | - | 0.00% | 0.00% | 91.43% | 0.00% | -91.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO REDONDO ECOLINE - AMERICAN STANDARD
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINGITORIO ARTICO 307-R LLAVE PUSH BI INCESA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LLAVE P/LAVAMANOS SENCILLA FOSET
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE CON REJILLA CUADRADA P/DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE ABASTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHAPETA CROMADA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/2 A LA PARED
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO 8'X4'X1/2" ULTRALIGHT
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO 8'X4'X1/2" ANTI-MOHO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANALETA CARGA 1-5/8" X 12' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL LISTON CARGA 1 1/2"X12' CAL 26 LMS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REBORDE TIPO "J" 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 12
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ANGULAR 1"X10' CAL 26
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIN CLIP DE 1 1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO CINTA DE PAPEL JUNTAS 2 (76.2M)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO FULMINANTE CAL 27
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO LIJA PARA AGUA NO. 150
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO LIJA PARA AGUA NO. 220
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO MASILLA CUBETA 28 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO TACHUELON 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO TORNILLO PUNTA BROCA 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO TORNILLO R-FINA NO. 6 X 1 PUNTA NORMAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.68% | 0.67% | 66.54% | 0.00% | -66.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE CARPINTERIA',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION DE PUERTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO SUMINISTRO DE PUERTAS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO - MAT + MO / ELECTRICIDAD ESPECIALES
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE VENTANERIA',)
|
- | - | - | - | - | - | 0.25% | 0.24% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO INSTALACION DE VENTANERIA
|
- | - | - | - | - | - | 0.25% | 0.24% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 345.54% | 0.00% | -345.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.01% | 0.01% | 345.54% | 0.00% | -345.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SUMINISTRO E INSTALACION HIDRAULICAS
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO INSTALACION DE ARTEFACTOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 322.64% | 0.00% | -322.64% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 48103.79% | 0.00% | -48103.79% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO PULIDO DE CONCRETO
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.13% | 0.13% | 64.59% | 0.00% | -64.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO INSTALACION DE BARANDA
|
- | - | - | - | - | - | 0.13% | 0.13% | 64.59% | 0.00% | -64.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INDIRECTOS DE OBRA
|
- | - | - | - | - | - | 10.56% | 10.21% | 149.53% | 77.90% | -71.63% | - | - | - | 0.52 | 47.90% | - | - | -91.96% | - | 0.00% |
|
INDIRECTOS
|
- | - | - | - | - | - | 10.56% | 10.21% | 149.53% | 77.90% | -71.63% | - | - | - | 0.52 | 47.90% | - | - | -91.96% | - | 0.00% |
|
SERVICIOS
|
- | - | - | - | - | - | 0.26% | 0.25% | 224.54% | 75.00% | -149.54% | - | - | - | 0.33 | 66.60% | - | - | -199.38% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.26% | 0.25% | 5.16% | 75.00% | 69.84% | - | - | - | 14.55 | -1354.85% | - | - | 93.13% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.26% | 0.25% | 3.61% | 75.00% | 71.39% | - | - | - | 20.78 | -1978.36% | - | - | 95.19% | - | 0.00% |
|
INSTALACIONES PROVISIONALES
|
- | - | - | - | - | - | 0.26% | 0.25% | 0.00% | 75.00% | 75.00% | - | - | - | 58194.00 | -5819300.00% | - | - | 100.00% | - | 0.00% |
|
CISTERNA DE AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RIPIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INTERNET OFICINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ENERGIA ELECTRICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIOS CONTRATADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUBLICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HERRAMIENTO Y EQUIPO
|
- | - | - | - | - | - | 2.42% | 2.34% | 192.44% | 80.00% | -112.44% | - | - | - | 0.42 | 58.43% | - | - | -140.55% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 8481.95% | 80.00% | -8401.95% | - | - | - | 0.01 | 99.06% | - | - | 0.00% | - | 0.00% |
|
('SEGURIDAD INDUSTRIAL',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 484.28% | 80.00% | -404.28% | - | - | - | 0.17 | 83.48% | - | - | -505.35% | - | 0.00% |
|
TAPON DE OIDOS CON CAJA BULLHE HP 22DB
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAMISA T-SHIRT, CINTA REFLECTIVA. 50 MEDIUM Y 50 LARGE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ROTULOS DE SE?ALIZAICON
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 80.00% | 80.00% | - | - | - | 1876.84 | -187584.00% | - | - | 99.95% | - | 0.00% |
|
CINTA REFLECTIVA 3M ROJO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CERCA PLASTICA LIMITACION NARANJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 762.40% | 80.00% | -682.40% | - | - | - | 0.10 | 89.51% | - | - | -853.00% | - | 0.00% |
|
CINTA DE PELIGRO COLOR ROJO
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.33% | 80.00% | 54.67% | - | - | - | 3.16 | -215.79% | - | - | 68.33% | - | 0.00% |
|
CINTA DE PRECAUCION COLOR AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 50.67% | 80.00% | 29.33% | - | - | - | 1.58 | -57.89% | - | - | 36.67% | - | 0.00% |
|
('ACABADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA PARA LLAVES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACEITE DW 40 11 ONZ AFLOJALO TODO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPUMA LIMPIADORA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICON PARA TABLEROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TAPAGOTERA DE ALUMINIO 01*10M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAMENT-1 ADITIVO ACELERANTE P/CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR COMBIFLEX
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ANTISOL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('BOTIQUIN',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLAS HÚMEDAS O PAÑUELOS DESECHABLES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CARPINTERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BISAGRA 4 X 4 DORADAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DIESEL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP SUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP DIESEL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPIGAS DE HULE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOMACORRIENTE DOBLE POLARIZADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOMACORRIENTE DE SOBRE PONER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA CONDUIT DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABLE TSJ 3' X 12'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABLE THHN # 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGLETA RADIANT RDZBK 15AMP 125V 2USB+RECEPTACULO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FOCO LED 13W PAR30IP65
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTENSION ELECTRICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLEXITUBO 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO REDONDO HIERRO NEGRO 1" CHAPA 16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GUIA P/ELECTRICISTA METALICA P/ CABLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOMBILLA NORMAL 100W
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABLE PARALELO #12
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABLE TSJ 2X12
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLAFONERA LED DE 18W
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMPARA LED 2L 20W 3K
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPAMENTO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLA PLEGABLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICON BLANCO 10.1Z ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO DE 1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COSTALES VACIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMINA GAL. DE 12 PIES 28MM ACANALADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIERRA SANDFLEX
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANGUERA P/PASAR NIVELES 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TELA DE REFUERZO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BARRA ROSCADA 9.5 MM ( 3 / 8 ) X UN METRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 36 BASE DE AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LLAVERO CON ETIQUETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACEITE DE RICINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 7 X 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 240 P/AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 400 P/AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1/2 (ESTACONES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COSTANERA LEGITIMA DE 5"X6MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCA DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACIDO MURIATICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 1''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE ALUMINIO DE 1 3/4" X 3" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO CIRCULAR CORTE DE MADERA 7 1/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO DE ALAMBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 220 BASE DE AGUA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEDAZO METALICO 3/16"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANDADO YALE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 5/8 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMINA GAL. DE 10 PIES 28MM ACANALADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AMBIENTAL GLADE 400 ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIQUIDO ATRAPA POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MICROFIBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ATOMIZADOR GUATEPLAST 32 ONZ
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SQUEEGEE LIMPIADOR DE VIDRIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MICROFIBRA 20U SURTIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JABON EN GEL ANTIBACTERIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALCOHOL EN GEL ANTIBACTERIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MANOS UNIVERSAL TK BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAPEL TOALLA PARA MANOS BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOLSAS GRANDES PARA BASURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIADOR DE EFLORESCENCIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAPEL HIGIENICO 8 ROLLOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLON DE 2" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 4" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TARIMA DE MADERA DE POLIN C/CABOTE 40''X48''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARCADOR DE ESQUINA TRUPER 15121
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR ACRILICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 1 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR MULTIFUNCIONAL 6000 MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REDUCIDOR DE 3/4" X 1 1/2" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEE DE 1 1/4" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO DE 1 1/2" X 45 PVC AP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TAPON HEMBRA DE 1" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEFLON DE 3/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIPLE DE 1" X 3" HG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
UNION DE 1" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LLAVE STILSON
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTROS PARA HERRAMIENTAS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO P/CORTE D/CONCRETO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABO PARA PALA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABO PARA PIOCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CABO PARA AZADON
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPONJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASILLA PARA GRIETAS EXT/INT. MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 12*1" PUNTA DE BROCA CON ARANDELA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.24% | 0.23% | 478.33% | 80.00% | -398.33% | - | - | - | 0.17 | 83.28% | - | - | -497.91% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.24% | 0.23% | 460.50% | 80.00% | -380.50% | - | - | - | 0.17 | 82.63% | - | - | -475.63% | - | 0.00% |
|
VIAJES DE RIPIO Y VARIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLETES
|
- | - | - | - | - | - | 0.24% | 0.23% | 206.68% | 80.00% | -126.68% | - | - | - | 0.39 | 61.29% | - | - | -158.35% | - | 0.00% |
|
FLETES DE CAMION 5 TONELADAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLETES DE CAMION DOBLE EJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FILTRO PARA AGUA PACIFIC FILTERS DE 3 ETAPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER DE SANITARIOS PORTATILES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 414.37% | 80.00% | -334.37% | - | - | - | 0.19 | 80.69% | - | - | -417.96% | - | 0.00% |
|
('SEGURIDAD INDUSTRIAL',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 125.20% | 80.00% | -45.20% | - | - | - | 0.64 | 36.10% | - | - | -56.50% | - | 0.00% |
|
GUANTE DE PROTECCION
|
- | - | - | - | - | - | 0.01% | 0.01% | 575.30% | 80.00% | -495.30% | - | - | - | 0.14 | 86.09% | - | - | -619.12% | - | 0.00% |
|
LENTES PROTECTORES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 573.44 | -57244.00% | - | - | 99.83% | - | 0.00% |
|
LINEA DE VIDA CON GANCHO GRANDE
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 80.00% | 80.00% | - | - | - | 3918.77 | -391776.80% | - | - | 99.97% | - | 0.00% |
|
ARNES
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 80.00% | 80.00% | - | - | - | 3023.10 | -302210.40% | - | - | 99.97% | - | 0.00% |
|
ALCOHOLIMETRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUBRENUCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTINTOR 10 LBS
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.57% | 80.00% | 65.43% | - | - | - | 5.49 | -449.09% | - | - | 81.79% | - | 0.00% |
|
LENTES DE PROTECCION CLAROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LENTES DE PROTECCION OSCUROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECIBELIMETRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOTAS INDUSTRIALES
|
- | - | - | - | - | - | 0.05% | 0.05% | 108.80% | 80.00% | -28.80% | - | - | - | 0.74 | 26.47% | - | - | -36.00% | - | 0.00% |
|
CASCO DE PROTECCION
|
- | - | - | - | - | - | 0.01% | 0.01% | 71.36% | 80.00% | 8.64% | - | - | - | 1.12 | -12.10% | - | - | 10.80% | - | 0.00% |
|
TAPON DE OIDOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 63.96% | 80.00% | 16.04% | - | - | - | 1.25 | -25.08% | - | - | 20.05% | - | 0.00% |
|
MASCARILLA C/VALVULA DE CARBON
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 80.00% | 80.00% | - | - | - | 2401.28 | -240028.00% | - | - | 99.96% | - | 0.00% |
|
CHALECO REFLECTIVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 308.13% | 80.00% | -228.13% | - | - | - | 0.26 | 74.04% | - | - | -285.16% | - | 0.00% |
|
BOTAS DE HULE PUNTA DE ACERO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARCO DE ANDAMIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA ELECTRICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ATORNILLADOR 18V. MILWAUKEE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PULIDORA TIPO ESMERILADORA 4 1/2" PULG. 1100W
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISTOLA DE CALOR TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIERRA ELECTRICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RENTA DE COMPRESOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ROTOMARTILLO INDUSTRIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BARRENO ROTOMARTILLO ELEC. TRUPER 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIERRA CIRCULAR INDUSTRIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIVEL LASER AUTONIVELANTE 2 LÍNEAS VERTICAL Y HORIZONTAL MARCA DEWALT
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUBETAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TIJERA PARA CORTAR LAMINA 10" (524101)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERRUCHO PARA TABLAYESO 12" TOTAL (3006)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TIRALINEAS DE PLASTICO 30M TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA 4" INOXIDABLE MANGO DE PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANGUERA P/AGUA DE 1/2" COLOR VERDE 30 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MACHETE TIPO VIZCANIO DE 14"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAIMAN 24"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PALA CON CABO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HACHA C/ CABO 3.5 LBS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIOCHA C/CABO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PALAS METALICAS PARA RECOGER BASURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCUADRILON DE 16' X 24'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RADIO COMUNICADOR PORTATIL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DEPOSITO ROTOPLAS DE 1,100 LITROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIVEL 3 BURBUJAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TENAZA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BARRETAS LARGAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA METALICA DE 2" MANGO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JUEGO SIERRA BANDA M-18 FUEL CORTE 5" MILWAUKEE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISTOLA PARA CALAFATEO SENCILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RADIO COMUNICADOR PORTATIL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOMBA MANUAL PARA BARRIL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DEPOSITO ROTOPLAS DE 2,500 LITROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUNTERO CON EMPUÑADURA 3/4X12
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CARRETA DE MANO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COBA DE 8" CON CABO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZADON C/CABO DE 3 LIBRAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIVEL DE 100' C/YESO AZUL IRWIN
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALMADANA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOMBA PARA FUMIGAR (MATABI)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISTOLA PLASTICA TRUPER DE 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SACATIERRAS CLASSIC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCALERA DE ALUMINIO 2 BANDAS 5 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTENSION 6 PIES X 1 3/4 P/PLANCHON DE MAGNESIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUCHILLA PRECORTADA 18MM CON ESTUCHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 5 TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 10' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HILO NYLON P/ALBAÑIL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARTILLO C/SACA CLAVOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SEGUETA PARA SIERRA BANDA PORTÁTIL M-18 MILWAUKEE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINCEL PARA ROTOMARTILLO BOSCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUNTA PARA ROTOMARTILLO BOCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINCEL CON PUNTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUNTA PARA CONCRETO SDS MAX
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 2.05% | 1.98% | 88.27% | 80.00% | -8.27% | - | - | - | 0.91 | 9.37% | - | - | -10.34% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 2.05% | 1.98% | 85.59% | 80.00% | -5.59% | - | - | - | 0.93 | 6.54% | - | - | -6.99% | - | 0.00% |
|
ALQUILER DE MAQUINARIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HERRAMIENTAS Y EQUIPO
|
- | - | - | - | - | - | 2.05% | 1.98% | 40.47% | 80.00% | 39.53% | - | - | - | 1.98 | -97.70% | - | - | 49.42% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VIBRO COMPACTADORA BAILARINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER VIBRO COMPACTADORA BAILARINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER TORNILLOS NIVELADORES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RENTA DE COMPACTADORA BAILARINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RENTA DE MINICARGADOR CON BRAZO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RENTA DE RODO VIBRADOR NO TRIPULADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIO Y MANTENIMIENTO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS Y MANTENIMIENTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO DE COMPUTO E IMPRESORAS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AIRE COMPRIMIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEGAFONO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS ADMINISTRATIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ATENCION AL PERSONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS INDIRECTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARQUEOS Y PEAJES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PAPELERIA Y UTILES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAPEL P/ FOTOCOPIADORA CARTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARCADOR PERMANENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TIJERA MULTIUSOS SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BATERIAS DOBLE A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BATERIA AAA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAPELERIA Y UTILES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TELEFONO E INTERNET
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE VENTANERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPARACION Y MANTENIMIENTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 80.00% | 80.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA ADMINISTRATIVO
|
- | - | - | - | - | - | 1.15% | 1.11% | 177.19% | 75.00% | -102.19% | - | - | - | 0.42 | 57.67% | - | - | -136.26% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 1.15% | 1.11% | 61.70% | 75.00% | 13.30% | - | - | - | 1.22 | -21.56% | - | - | 17.74% | - | 0.00% |
|
('SERVICIOS CONTRATADOS',)
|
- | - | - | - | - | - | 0.85% | 0.83% | 66.25% | 75.00% | 8.75% | - | - | - | 1.13 | -13.21% | - | - | 11.67% | - | 0.00% |
|
HONORARIOS PROFESIONALES
|
- | - | - | - | - | - | 0.85% | 0.83% | 66.25% | 75.00% | 8.75% | - | - | - | 1.13 | -13.21% | - | - | 11.67% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE SEGURIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS ADMINISTRATIVOS',)
|
- | - | - | - | - | - | 0.29% | 0.28% | 0.00% | 75.00% | 75.00% | - | - | - | 66150.00 | -6614900.00% | - | - | 100.00% | - | 0.00% |
|
SUPERVISOR SEGURIDAD INDUSTRIAL
|
- | - | - | - | - | - | 0.29% | 0.28% | 0.00% | 75.00% | 75.00% | - | - | - | 66150.00 | -6614900.00% | - | - | 100.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IGSS PATRONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONIF. DECRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IRTRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INTECAP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONO 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AGUINALDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INDEMNIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA AYUDANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA SEGURIDAD INDUSTRIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA BODEGUERO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VACACIONES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA ALBAÑIL / MAESTRO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA OPERATIVO
|
- | - | - | - | - | - | 2.52% | 2.43% | 152.12% | 75.00% | -77.12% | - | - | - | 0.49 | 50.70% | - | - | -102.83% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 1.73% | 1.67% | 151.03% | 75.00% | -76.03% | - | - | - | 0.50 | 50.34% | - | - | -101.37% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 1.73% | 1.67% | 151.03% | 75.00% | -76.03% | - | - | - | 0.50 | 50.34% | - | - | -101.37% | - | 0.00% |
|
IGSS PATRONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONIF. DECRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IRTRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INTECAP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONO 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AGUINALDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INDEMNIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA AYUDANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA SEGURIDAD INDUSTRIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 1.73% | 1.67% | 52.60% | 75.00% | 22.40% | - | - | - | 1.43 | -42.59% | - | - | 29.87% | - | 0.00% |
|
PROVISION PRESTACIONES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA BODEGUERO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VACACIONES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA ALBAÑIL / MAESTRO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 0.79% | 0.76% | 65.27% | 75.00% | 9.73% | - | - | - | 1.15 | -14.90% | - | - | 12.97% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 0.21% | 0.20% | 232.77% | 75.00% | -157.77% | - | - | - | 0.32 | 67.78% | - | - | -210.36% | - | 0.00% |
|
SERVICIO DE SEGURIDAD
|
- | - | - | - | - | - | 0.21% | 0.20% | 232.77% | 75.00% | -157.77% | - | - | - | 0.32 | 67.78% | - | - | -210.36% | - | 0.00% |
|
('GASTOS ADMINISTRATIVOS',)
|
- | - | - | - | - | - | 0.58% | 0.56% | 0.28% | 75.00% | 74.72% | - | - | - | 266.28 | -26528.42% | - | - | 99.62% | - | 0.00% |
|
ATENCION AL PERSONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MAESTRO DE OBRA
|
- | - | - | - | - | - | 0.35% | 0.33% | 0.00% | 75.00% | 75.00% | - | - | - | 78750.00 | -7874900.00% | - | - | 100.00% | - | 0.00% |
|
BODEGUERO
|
- | - | - | - | - | - | 0.24% | 0.23% | 0.00% | 75.00% | 75.00% | - | - | - | 54032.62 | -5403162.50% | - | - | 100.00% | - | 0.00% |
|
('SERVICIOS CONTRATADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HONORARIOS PROFESIONALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 75.00% | 75.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES PROVISIONALES
|
- | - | - | - | - | - | 0.73% | 0.70% | 189.67% | 100.00% | -89.67% | - | - | - | 0.53 | 47.28% | - | - | -89.67% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.73% | 0.70% | 35.43% | 100.00% | 64.57% | - | - | - | 2.82 | -182.27% | - | - | 64.57% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.73% | 0.70% | 34.70% | 100.00% | 65.30% | - | - | - | 2.88 | -188.17% | - | - | 65.30% | - | 0.00% |
|
INSTALACIONES PROVISIONALES
|
- | - | - | - | - | - | 0.64% | 0.62% | 0.00% | 100.00% | 100.00% | - | - | - | 192850.00 | -19284900.00% | - | - | 100.00% | - | 0.00% |
|
CISTERNA DE AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER DE SANITARIOS PORTATILES
|
- | - | - | - | - | - | 0.09% | 0.09% | 275.54% | 100.00% | -175.54% | - | - | - | 0.36 | 63.71% | - | - | -175.54% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLETES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUBETAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CARRETA DE MANO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SEGURIDAD INDUSTRIAL',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASCARILLAS DESECHABLES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TERMINAL BIOMETRICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONSUMIBLES CAFETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOLSA PLASTICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO DE COMPUTO E IMPRESORAS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPUTADORAS DE ESCRITORIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS INDIRECTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARQUEOS Y PEAJES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PAPELERIA Y UTILES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARCADOR RESALTADOR FABER CASTELL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MARCADOR PERMANENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TIJERA MULTIUSOS SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ENGRAPADORA FAST
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CARGADOR PARA BATERIAS AA / AAA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAPICEROS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAPELERIA Y UTILES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIOS CONTRATADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LONA VINILICA 3.3X0.80
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LONA VINILICA 2X2 MTS FULL COLOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ANTISOL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CARPINTERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BISAGRA 4 X 4 DORADAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BISAGRA 3 X 3 GRIS NIQUEL MATE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP SUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPIGAS DE HULE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOMACORRIENTE DOBLE POLARIZADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMINA GAL. DE 12 PIES 28MM ACANALADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIERRA SANDFLEX
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMINA 12' ACANALADA COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LONA VINILICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO + BANDEJA + MANERAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 1''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO CIRCULAR CORTE DE MADERA 7 1/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANDADO YALE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAMINA GAL. DE 10 PIES 28MM ACANALADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JABON EN GEL ANTIBACTERIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 2" X 2" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLON DE 2" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 4" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 8´
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4'X8'X1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLONCILLO DE 11/2" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TARIMA DE MADERA DE POLIN C/CABOTE 40''X48''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA DE ACEITE EN COLORES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR ACRILICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR MULTIFUNCIONAL 6000 MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADAPTADOR MACHO DE 1/2" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (160 PSI) PVC AGUA POTABLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEE DE 1 1/4" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO PVC DE 1" X 45 A/P
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REDUCIDOR DE 2" X 1 1/2" PVC AP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADAPTADOR MACHO DE 2" PVC AP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMENTO PVC 1/4
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REDUCIDOR DE 2" X 1 1/2" PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEE DE 1/2" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 4" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLOTE PARA TANQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA EMPOTRADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC DE 1" X 250 PSI A/P
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO PVC DE 1" X 90 A/P
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REDUCIDOR PVC DE 3/4" A 1" A/P
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADAPTADOR HEMBRA DE 1/2" PVC CON ROSCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO DE 1 1/2" X 90 PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO DE 1/2" X 45 PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO DE 2" X 90 PVC AGUA POTABLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CODO DE 2" X 90 PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEE DE 1" PVC AP.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TEE DE 2" PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADAPTADOR HEMBRA DE 3/4" PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REDUCIDOR PVC DE 1/2" A 1" A/P
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MANTENIMIENTO Y LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO SERVICIO DE FUMIGACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LABORATORIOS
|
- | - | - | - | - | - | 0.14% | 0.14% | 143.52% | 95.00% | -48.52% | - | - | - | 0.66 | 33.81% | - | - | -51.07% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 143.52% | 95.00% | -48.52% | - | - | - | 0.66 | 33.81% | - | - | -51.07% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 143.52% | 95.00% | -48.52% | - | - | - | 0.66 | 33.81% | - | - | -51.07% | - | 0.00% |
|
SERVICIO DE LABORATORIO
|
- | - | - | - | - | - | 0.14% | 0.14% | 143.52% | 95.00% | -48.52% | - | - | - | 0.66 | 33.81% | - | - | -51.07% | - | 0.00% |
|
TOPOGRAFIA
|
- | - | - | - | - | - | 0.71% | 0.69% | 105.24% | 78.00% | -27.24% | - | - | - | 0.74 | 25.88% | - | - | -34.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.71% | 0.69% | 105.03% | 78.00% | -27.03% | - | - | - | 0.74 | 25.73% | - | - | -34.65% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB CONTRATO MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.71% | 0.69% | 0.00% | 78.00% | 78.00% | - | - | - | 168570.87 | -16856987.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO SERVICIOS DE TOPOGRAFIA
|
- | - | - | - | - | - | 0.71% | 0.69% | 0.00% | 78.00% | 78.00% | - | - | - | 168570.87 | -16856987.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IDP REGULAR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 78.00% | 78.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PRESTACIONES PERSONAL DE OBRA
|
- | - | - | - | - | - | 1.43% | 1.38% | 122.00% | 92.00% | -30.00% | - | - | - | 0.75 | 24.59% | - | - | -32.61% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 1.43% | 1.38% | 121.98% | 92.00% | -29.98% | - | - | - | 0.75 | 24.58% | - | - | -32.59% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 1.43% | 1.38% | 121.98% | 92.00% | -29.98% | - | - | - | 0.75 | 24.58% | - | - | -32.59% | - | 0.00% |
|
IGSS PATRONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONIF. DECRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IRTRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INTECAP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BONO 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AGUINALDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INDEMNIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA AYUDANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA SEGURIDAD INDUSTRIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PROVISION PRESTACIONES
|
- | - | - | - | - | - | 1.43% | 1.38% | 112.73% | 92.00% | -20.73% | - | - | - | 0.82 | 18.39% | - | - | -22.53% | - | 0.00% |
|
MANO DE OBRA BODEGUERO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUELDOS ADMON
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VACACIONES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MANO DE OBRA ALBAÑIL / MAESTRO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 92.00% | 92.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FIANZAS, SEGUROS Y CONTRATOS
|
- | - | - | - | - | - | 1.21% | 1.17% | 51.33% | 51.00% | -0.33% | - | - | - | 0.99 | 0.64% | - | - | -0.64% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 1.21% | 1.17% | 51.33% | 51.00% | -0.33% | - | - | - | 0.99 | 0.64% | - | - | -0.64% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 1.21% | 1.17% | 51.33% | 51.00% | -0.33% | - | - | - | 0.99 | 0.64% | - | - | -0.64% | - | 0.00% |
|
FIANZAS DE ANTICIPO
|
- | - | - | - | - | - | 0.26% | 0.25% | 37.48% | 51.00% | 13.52% | - | - | - | 1.36 | -36.06% | - | - | 26.50% | - | 0.00% |
|
FIANZA DE CONSERVACION DE OBRA
|
- | - | - | - | - | - | 0.36% | 0.34% | 0.00% | 51.00% | 51.00% | - | - | - | 54855.83 | -5485482.95% | - | - | 100.00% | - | 0.00% |
|
FIANZA DE CUMPLIMIENTO DE CONTRATO
|
- | - | - | - | - | - | 0.38% | 0.37% | 47.77% | 51.00% | 3.23% | - | - | - | 1.07 | -6.77% | - | - | 6.34% | - | 0.00% |
|
SEGURO DE RESPONSABILIDAD CIVIL
|
- | - | - | - | - | - | 0.21% | 0.20% | 0.00% | 51.00% | 51.00% | - | - | - | 32046.81 | -3204580.88% | - | - | 100.00% | - | 0.00% |
|
FIANZAS, SEGUROS Y CONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 51.00% | 51.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 19
|
- | - | - | - | - | - | 1.30% | 1.25% | 74.84% | 42.53% | -32.31% | - | - | - | 0.57 | 43.17% | - | - | -75.97% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 84.95% | 63.07% | -21.88% | - | - | - | 0.74 | 25.75% | - | - | -34.69% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 116.53% | 100.00% | -16.53% | - | - | - | 0.86 | 14.19% | - | - | -16.53% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 156.21% | 100.00% | -56.21% | - | - | - | 0.64 | 35.98% | - | - | -56.21% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 323.95% | 100.00% | -223.95% | - | - | - | 0.31 | 69.13% | - | - | -223.95% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.28% | 100.00% | 37.72% | - | - | - | 1.61 | -60.57% | - | - | 37.72% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 11.33% | 100.00% | 88.67% | - | - | - | 8.82 | -782.40% | - | - | 88.67% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.03% | 100.00% | 31.97% | - | - | - | 1.47 | -47.00% | - | - | 31.97% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 12.45% | 100.00% | 87.55% | - | - | - | 8.03 | -703.50% | - | - | 87.55% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 82.58% | 100.00% | 17.42% | - | - | - | 1.21 | -21.10% | - | - | 17.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 82.58% | 100.00% | 17.42% | - | - | - | 1.21 | -21.10% | - | - | 17.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 113.39% | 100.00% | -13.39% | - | - | - | 0.88 | 11.81% | - | - | -13.39% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 164.78% | 100.00% | -64.78% | - | - | - | 0.61 | 39.31% | - | - | -64.78% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 10891.79% | 100.00% | -10791.79% | - | - | - | 0.01 | 99.08% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 603.17% | 100.00% | -503.17% | - | - | - | 0.17 | 83.42% | - | - | -503.17% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 166.31% | 100.00% | -66.31% | - | - | - | 0.60 | 39.87% | - | - | -66.31% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 186.19% | 100.00% | -86.19% | - | - | - | 0.54 | 46.29% | - | - | -86.19% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 83.76% | 100.00% | 16.24% | - | - | - | 1.19 | -19.39% | - | - | 16.24% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 276.65% | 100.00% | -176.65% | - | - | - | 0.36 | 63.85% | - | - | -176.65% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 174.74% | 100.00% | -74.74% | - | - | - | 0.57 | 42.77% | - | - | -74.74% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.93% | 100.00% | -74.93% | - | - | - | 0.57 | 42.83% | - | - | -74.93% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 57.34% | 100.00% | 42.66% | - | - | - | 1.74 | -74.40% | - | - | 42.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 57.34% | 100.00% | 42.66% | - | - | - | 1.74 | -74.40% | - | - | 42.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 75.65% | 67.00% | -8.65% | - | - | - | 0.89 | 11.43% | - | - | -12.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 109.42% | 67.00% | -42.42% | - | - | - | 0.61 | 38.77% | - | - | -63.32% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 295360.00% | 67.00% | -295293.00% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14780.46% | 67.00% | -14713.46% | - | - | - | 0.00 | 99.55% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 62720.00% | 67.00% | -62653.00% | - | - | - | 0.00 | 99.89% | - | - | 0.00% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 3082.34% | 67.00% | -3015.34% | - | - | - | 0.02 | 97.83% | - | - | -4500.50% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 344.62% | 67.00% | -277.62% | - | - | - | 0.19 | 80.56% | - | - | -414.36% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 110.02% | 67.00% | -43.02% | - | - | - | 0.61 | 39.10% | - | - | -64.21% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.08% | 67.00% | -15.08% | - | - | - | 0.82 | 18.38% | - | - | -22.51% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 44.80% | 67.00% | 22.20% | - | - | - | 1.50 | -49.54% | - | - | 33.13% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 18.45% | 67.00% | 48.55% | - | - | - | 3.63 | -263.15% | - | - | 72.46% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 204.29% | 67.00% | -137.29% | - | - | - | 0.33 | 67.20% | - | - | -204.91% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.97% | 67.00% | -166.97% | - | - | - | 0.29 | 71.36% | - | - | -249.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 107.33% | 67.00% | -40.33% | - | - | - | 0.62 | 37.58% | - | - | -60.19% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1297.90% | 67.00% | -1230.90% | - | - | - | 0.05 | 94.84% | - | - | -1837.16% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 452.79 | -45179.27% | - | - | 99.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 121.24 | -12024.32% | - | - | 99.18% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 51.58% | 0.00% | -51.58% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 4.23% | 0.00% | -4.23% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 10.15% | 0.00% | -10.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.22% | 0.00% | -64.22% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 433.72% | 0.00% | -433.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 12.52% | 0.00% | -12.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 518.09% | 0.00% | -518.09% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.56% | 0.00% | -80.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.56% | 0.00% | -80.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 52.95% | 69.88% | 16.93% | - | - | - | 1.32 | -31.98% | - | - | 24.23% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 99.79% | 68.00% | -31.79% | - | - | - | 0.68 | 31.86% | - | - | -46.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.18% | 72.00% | 71.82% | - | - | - | 402.75 | -40174.82% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.14% | 72.00% | 65.86% | - | - | - | 11.73 | -1073.05% | - | - | 91.48% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.10% | 0.00% | -72.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 18
|
- | - | - | - | - | - | 1.30% | 1.25% | 74.20% | 42.53% | -31.67% | - | - | - | 0.57 | 42.68% | - | - | -74.47% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 83.57% | 63.07% | -20.50% | - | - | - | 0.75 | 24.53% | - | - | -32.51% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 122.86% | 100.00% | -22.86% | - | - | - | 0.81 | 18.61% | - | - | -22.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 173.99% | 100.00% | -73.99% | - | - | - | 0.57 | 42.53% | - | - | -73.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 74322.47% | 100.00% | -74222.47% | - | - | - | 0.00 | 99.87% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 121739.13% | 100.00% | -121639.13% | - | - | - | 0.00 | 99.92% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1005.17% | 100.00% | -905.17% | - | - | - | 0.10 | 90.05% | - | - | -905.17% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 30.09% | 100.00% | 69.91% | - | - | - | 3.32 | -232.39% | - | - | 69.91% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 61049.00% | 100.00% | -60949.00% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 321.37% | 100.00% | -221.37% | - | - | - | 0.31 | 68.88% | - | - | -221.37% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 81.61% | 100.00% | 18.39% | - | - | - | 1.23 | -22.53% | - | - | 18.39% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.22% | 100.00% | 93.78% | - | - | - | 16.09 | -1508.50% | - | - | 93.78% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.03% | 100.00% | 31.97% | - | - | - | 1.47 | -47.00% | - | - | 31.97% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 76.18% | 100.00% | 23.82% | - | - | - | 1.31 | -31.26% | - | - | 23.82% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 76.18% | 100.00% | 23.82% | - | - | - | 1.31 | -31.26% | - | - | 23.82% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 78.52% | 67.00% | -11.52% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 114.82% | 67.00% | -47.82% | - | - | - | 0.58 | 41.65% | - | - | -71.38% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 213274.55% | 67.00% | -213207.55% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7597.21% | 67.00% | -7530.21% | - | - | - | 0.01 | 99.12% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1883.32% | 67.00% | -1816.32% | - | - | - | 0.04 | 96.44% | - | - | -2710.92% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.14% | 67.00% | -65.14% | - | - | - | 0.51 | 49.30% | - | - | -97.23% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 123.68% | 67.00% | -56.68% | - | - | - | 0.54 | 45.83% | - | - | -84.60% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 44.80% | 67.00% | 22.20% | - | - | - | 1.50 | -49.54% | - | - | 33.13% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.77% | 67.00% | 12.23% | - | - | - | 1.22 | -22.33% | - | - | 18.25% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 487.36% | 67.00% | -420.36% | - | - | - | 0.14 | 86.25% | - | - | -627.40% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.97% | 67.00% | -166.97% | - | - | - | 0.29 | 71.36% | - | - | -249.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 170.97% | 67.00% | -103.97% | - | - | - | 0.39 | 60.81% | - | - | -155.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1916.61% | 67.00% | -1849.61% | - | - | - | 0.03 | 96.50% | - | - | -2760.62% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.97% | 67.00% | -41.97% | - | - | - | 0.61 | 38.51% | - | - | -62.64% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 452.79 | -45179.27% | - | - | 99.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 121.24 | -12024.32% | - | - | 99.18% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 111.06% | 100.00% | -11.06% | - | - | - | 0.90 | 9.96% | - | - | -11.06% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 159.36% | 100.00% | -59.36% | - | - | - | 0.63 | 37.25% | - | - | -59.36% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 15806.01% | 100.00% | -15706.01% | - | - | - | 0.01 | 99.37% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 245.83% | 100.00% | -145.83% | - | - | - | 0.41 | 59.32% | - | - | -145.83% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 165.92% | 100.00% | -65.92% | - | - | - | 0.60 | 39.73% | - | - | -65.92% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 186.19% | 100.00% | -86.19% | - | - | - | 0.54 | 46.29% | - | - | -86.19% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.54% | 100.00% | 19.46% | - | - | - | 1.24 | -24.17% | - | - | 19.46% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 276.65% | 100.00% | -176.65% | - | - | - | 0.36 | 63.85% | - | - | -176.65% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 174.74% | 100.00% | -74.74% | - | - | - | 0.57 | 42.77% | - | - | -74.74% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.77% | 100.00% | -45.77% | - | - | - | 0.69 | 31.40% | - | - | -45.77% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 165.44% | 100.00% | -65.44% | - | - | - | 0.60 | 39.55% | - | - | -65.44% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 58.58% | 100.00% | 41.42% | - | - | - | 1.71 | -70.70% | - | - | 41.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 58.58% | 100.00% | 41.42% | - | - | - | 1.71 | -70.70% | - | - | 41.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 41.97% | 0.00% | -41.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 8.97% | 0.00% | -8.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 8.77% | 0.00% | -8.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 0.00% | -71.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 0.00% | -2272.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 0.00% | -2272.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 15.02% | 0.00% | -15.02% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 621.70% | 0.00% | -621.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 0.00% | -92.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 0.00% | -92.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 62.20% | 0.00% | -62.20% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 62.20% | 0.00% | -62.20% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 53.05% | 69.88% | 16.83% | - | - | - | 1.32 | -31.73% | - | - | 24.09% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 99.79% | 68.00% | -31.79% | - | - | - | 0.68 | 31.86% | - | - | -46.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.39% | 72.00% | 71.61% | - | - | - | 183.61 | -18260.81% | - | - | 99.46% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.46% | 72.00% | 58.54% | - | - | - | 5.35 | -434.78% | - | - | 81.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.10% | 0.00% | -72.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 3
|
- | - | - | - | - | - | 1.30% | 1.25% | 89.44% | 56.95% | -32.49% | - | - | - | 0.64 | 36.32% | - | - | -57.05% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 98.43% | 87.23% | -11.20% | - | - | - | 0.89 | 11.38% | - | - | -12.84% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 134.53% | 50.00% | -84.53% | - | - | - | 0.37 | 62.83% | - | - | -169.07% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 181.54% | 50.00% | -131.54% | - | - | - | 0.28 | 72.46% | - | - | -263.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 181.54% | 50.00% | -131.54% | - | - | - | 0.28 | 72.46% | - | - | -263.08% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 1827.38 | -182638.50% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 753.09 | -75209.00% | - | - | 99.87% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 50.00% | 50.00% | - | - | - | 12310.10 | -1230910.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 58.17% | 50.00% | -8.17% | - | - | - | 0.86 | 14.04% | - | - | -16.34% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 50.00% | -2222.46% | - | - | - | 0.02 | 97.80% | - | - | -4444.93% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 50.00% | -2222.46% | - | - | - | 0.02 | 97.80% | - | - | -4444.93% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 329.43% | 50.00% | -279.43% | - | - | - | 0.15 | 84.82% | - | - | -558.86% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 431.43 | -43043.00% | - | - | 99.77% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 3.29 | -229.00% | - | - | 69.60% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 238.80% | 50.00% | -188.80% | - | - | - | 0.21 | 79.06% | - | - | -377.61% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 41.80 | -4079.50% | - | - | 97.61% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 212.35% | 50.00% | -162.35% | - | - | - | 0.24 | 76.45% | - | - | -324.71% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1554.26% | 50.00% | -1504.26% | - | - | - | 0.03 | 96.78% | - | - | -3008.51% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 4.92 | -391.50% | - | - | 79.65% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 4.92 | -391.50% | - | - | 79.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 12.96 | -1196.50% | - | - | 92.29% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 9.59 | -859.00% | - | - | 89.57% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 3.38 | -237.50% | - | - | 70.37% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 249.20 | -24820.50% | - | - | 99.60% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 249.20 | -24820.50% | - | - | 99.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 340.40 | -33939.50% | - | - | 99.71% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 340.40 | -33939.50% | - | - | 99.71% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 832.99 | -83199.00% | - | - | 99.88% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 832.99 | -83199.00% | - | - | 99.88% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 1012.75 | -101175.00% | - | - | 99.90% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 124.46 | -12345.50% | - | - | 99.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 5.62 | -462.00% | - | - | 82.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 8.69 | -769.00% | - | - | 88.49% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 1.74 | -73.50% | - | - | 42.36% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 7.20 | -620.50% | - | - | 86.12% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 865.04 | -86404.50% | - | - | 99.88% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 50.00% | 50.00% | - | - | - | 4640.83 | -463983.00% | - | - | 99.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 40.34 | -3933.50% | - | - | 97.52% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 50.00% | 50.00% | - | - | - | 4600.50 | -459949.50% | - | - | 99.98% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 110.70% | 100.00% | -10.70% | - | - | - | 0.90 | 9.67% | - | - | -10.70% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 123.60% | 100.00% | -23.60% | - | - | - | 0.81 | 19.09% | - | - | -23.60% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 316.08% | 100.00% | -216.08% | - | - | - | 0.32 | 68.36% | - | - | -216.08% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 177.36% | 100.00% | -77.36% | - | - | - | 0.56 | 43.62% | - | - | -77.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 50.35% | 100.00% | 49.65% | - | - | - | 1.99 | -98.61% | - | - | 49.65% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.33% | 100.00% | 12.67% | - | - | - | 1.15 | -14.51% | - | - | 12.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.11% | 100.00% | 83.89% | - | - | - | 6.21 | -520.85% | - | - | 83.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1825.21 | -182421.00% | - | - | 99.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.22% | 100.00% | -0.22% | - | - | - | 1.00 | 0.22% | - | - | -0.22% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.22% | 100.00% | -0.22% | - | - | - | 1.00 | 0.22% | - | - | -0.22% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 99.67% | 100.00% | 0.33% | - | - | - | 1.00 | -0.33% | - | - | 0.33% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 132.86% | 100.00% | -32.86% | - | - | - | 0.75 | 24.73% | - | - | -32.86% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 272.11% | 100.00% | -172.11% | - | - | - | 0.37 | 63.25% | - | - | -172.11% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.73% | 100.00% | -23.73% | - | - | - | 0.81 | 19.18% | - | - | -23.73% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.95% | 100.00% | 73.05% | - | - | - | 3.71 | -271.00% | - | - | 73.05% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.39% | 100.00% | 72.61% | - | - | - | 3.65 | -265.07% | - | - | 72.61% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 4807.82 | -480682.00% | - | - | 99.98% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 326.34 | -32534.00% | - | - | 99.69% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 71.50% | 100.00% | 28.50% | - | - | - | 1.40 | -39.86% | - | - | 28.50% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 71.50% | 100.00% | 28.50% | - | - | - | 1.40 | -39.86% | - | - | 28.50% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 61.23% | 100.00% | 38.77% | - | - | - | 1.63 | -63.31% | - | - | 38.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 82.33% | 100.00% | 17.67% | - | - | - | 1.21 | -21.46% | - | - | 17.67% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1231.53% | 100.00% | -1131.53% | - | - | - | 0.08 | 91.88% | - | - | -1131.53% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 441.43% | 100.00% | -341.43% | - | - | - | 0.23 | 77.35% | - | - | -341.43% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 110.02% | 100.00% | -10.02% | - | - | - | 0.91 | 9.11% | - | - | -10.02% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 40.92% | 100.00% | 59.08% | - | - | - | 2.44 | -144.36% | - | - | 59.08% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.18% | 100.00% | 86.82% | - | - | - | 7.59 | -658.81% | - | - | 86.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 825.52 | -82452.00% | - | - | 99.88% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 163.42 | -16242.00% | - | - | 99.39% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.66% | 100.00% | -17.66% | - | - | - | 0.85 | 15.01% | - | - | -17.66% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 124.59 | -12359.00% | - | - | 99.20% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 96.45% | 86.12% | -10.33% | - | - | - | 0.89 | 10.71% | - | - | -11.99% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 106.96% | 88.00% | -18.96% | - | - | - | 0.82 | 17.72% | - | - | -21.54% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 110.17% | 88.00% | -22.17% | - | - | - | 0.80 | 20.12% | - | - | -25.19% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 84.61% | 84.00% | -0.61% | - | - | - | 0.99 | 0.72% | - | - | -0.73% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 86.40% | 84.00% | -2.40% | - | - | - | 0.97 | 2.77% | - | - | -2.85% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.10% | 84.00% | 58.90% | - | - | - | 3.35 | -234.71% | - | - | 70.12% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 73.38% | 0.00% | -73.38% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.23% | 0.00% | -98.23% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 97.36% | 0.00% | -97.36% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 97.36% | 0.00% | -97.36% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 97.36% | 0.00% | -97.36% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.72% | 0.00% | -101.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.72% | 0.00% | -101.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.72% | 0.00% | -101.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 100.03% | 0.00% | -100.03% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.17% | 0.00% | -153.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.17% | 0.00% | -153.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 20.40% | 0.00% | -20.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 58.78% | 0.00% | -58.78% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 54.68% | 0.00% | -54.68% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.77% | 0.00% | -81.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 4
|
- | - | - | - | - | - | 1.30% | 1.25% | 88.66% | 56.95% | -31.71% | - | - | - | 0.64 | 35.76% | - | - | -55.68% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 99.21% | 87.23% | -11.98% | - | - | - | 0.88 | 12.08% | - | - | -13.74% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 130.42% | 50.00% | -80.42% | - | - | - | 0.38 | 61.66% | - | - | -160.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 182.67% | 50.00% | -132.67% | - | - | - | 0.27 | 72.63% | - | - | -265.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 182.67% | 50.00% | -132.67% | - | - | - | 0.27 | 72.63% | - | - | -265.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 1827.38 | -182638.50% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 753.09 | -75209.00% | - | - | 99.87% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 50.00% | 50.00% | - | - | - | 12310.10 | -1230910.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.38% | 50.00% | 4.62% | - | - | - | 1.10 | -10.17% | - | - | 9.23% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 3017.22% | 50.00% | -2967.22% | - | - | - | 0.02 | 98.34% | - | - | -5934.44% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 11.73 | -1073.00% | - | - | 91.47% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 233.23% | 50.00% | -183.23% | - | - | - | 0.21 | 78.56% | - | - | -366.46% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 41.80 | -4079.50% | - | - | 97.61% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 166.85% | 50.00% | -116.85% | - | - | - | 0.30 | 70.03% | - | - | -233.71% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3108.51% | 50.00% | -3058.51% | - | - | - | 0.02 | 98.39% | - | - | -6117.03% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 50.00% | 9.85% | - | - | - | 1.25 | -24.54% | - | - | 19.70% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 431.43 | -43043.00% | - | - | 99.77% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 3.29 | -229.00% | - | - | 69.60% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 4.92 | -391.50% | - | - | 79.65% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 4.92 | -391.50% | - | - | 79.65% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 9.78% | 50.00% | 40.22% | - | - | - | 5.11 | -411.15% | - | - | 80.44% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 124.46 | -12345.50% | - | - | 99.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 5.62 | -462.00% | - | - | 82.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 8.69 | -769.00% | - | - | 88.49% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 1.74 | -73.50% | - | - | 42.36% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1374.95% | 50.00% | -1324.95% | - | - | - | 0.04 | 96.36% | - | - | -2649.90% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 865.04 | -86404.50% | - | - | 99.88% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 12.96 | -1196.50% | - | - | 92.29% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 9.59 | -859.00% | - | - | 89.57% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 3.38 | -237.50% | - | - | 70.37% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 249.20 | -24820.50% | - | - | 99.60% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 249.20 | -24820.50% | - | - | 99.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 340.40 | -33939.50% | - | - | 99.71% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 340.40 | -33939.50% | - | - | 99.71% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 832.99 | -83199.00% | - | - | 99.88% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 50.00% | 50.00% | - | - | - | 832.99 | -83199.00% | - | - | 99.88% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 50.00% | 50.00% | - | - | - | 4640.83 | -463983.00% | - | - | 99.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 40.34 | -3933.50% | - | - | 97.52% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 50.00% | 50.00% | - | - | - | 4600.50 | -459949.50% | - | - | 99.98% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 50.00% | 50.00% | - | - | - | 77.99 | -7699.00% | - | - | 98.72% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 104.64% | 100.00% | -4.64% | - | - | - | 0.96 | 4.43% | - | - | -4.64% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 128.67% | 100.00% | -28.67% | - | - | - | 0.78 | 22.28% | - | - | -28.67% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 272.11% | 100.00% | -172.11% | - | - | - | 0.37 | 63.25% | - | - | -172.11% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.87% | 100.00% | 38.13% | - | - | - | 1.62 | -61.64% | - | - | 38.13% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 1.85% | 100.00% | 98.15% | - | - | - | 54.14 | -5314.21% | - | - | 98.15% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.21% | 100.00% | 72.79% | - | - | - | 3.68 | -267.50% | - | - | 72.79% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 87.72% | 100.00% | 12.28% | - | - | - | 1.14 | -14.00% | - | - | 12.28% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 87.72% | 100.00% | 12.28% | - | - | - | 1.14 | -14.00% | - | - | 12.28% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 101.06% | 100.00% | -1.06% | - | - | - | 0.99 | 1.05% | - | - | -1.06% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 111.75% | 100.00% | -11.75% | - | - | - | 0.89 | 10.52% | - | - | -11.75% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 246.38% | 100.00% | -146.38% | - | - | - | 0.41 | 59.41% | - | - | -146.38% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 187.32% | 100.00% | -87.32% | - | - | - | 0.53 | 46.61% | - | - | -87.32% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9457.29 | -945629.00% | - | - | 99.99% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5325.36 | -532436.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1825.21 | -182421.00% | - | - | 99.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 92.79% | 100.00% | 7.21% | - | - | - | 1.08 | -7.78% | - | - | 7.21% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 92.79% | 100.00% | 7.21% | - | - | - | 1.08 | -7.78% | - | - | 7.21% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 72.75% | 100.00% | 27.25% | - | - | - | 1.37 | -37.46% | - | - | 27.25% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 103.97% | 100.00% | -3.97% | - | - | - | 0.96 | 3.82% | - | - | -3.97% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 286254.55% | 100.00% | -286154.55% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4377.01% | 100.00% | -4277.01% | - | - | - | 0.02 | 97.72% | - | - | -4277.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 62720.00% | 100.00% | -62620.00% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 223.74% | 100.00% | -123.74% | - | - | - | 0.45 | 55.30% | - | - | -123.74% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 136.70% | 100.00% | -36.70% | - | - | - | 0.73 | 26.84% | - | - | -36.70% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 49.34% | 100.00% | 50.66% | - | - | - | 2.03 | -102.68% | - | - | 50.66% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.64% | 100.00% | 97.36% | - | - | - | 37.94 | -3694.05% | - | - | 97.36% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 127.41% | 100.00% | -27.41% | - | - | - | 0.78 | 21.51% | - | - | -27.41% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 163.42 | -16242.00% | - | - | 99.39% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.66% | 100.00% | -17.66% | - | - | - | 0.85 | 15.01% | - | - | -17.66% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 39.75% | 100.00% | 60.25% | - | - | - | 2.52 | -151.54% | - | - | 60.25% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 93.68% | 86.12% | -7.56% | - | - | - | 0.92 | 8.07% | - | - | -8.78% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 102.71% | 88.00% | -14.71% | - | - | - | 0.86 | 14.32% | - | - | -16.72% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.79% | 88.00% | -17.79% | - | - | - | 0.83 | 16.82% | - | - | -20.22% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 83.50% | 84.00% | 0.50% | - | - | - | 1.01 | -0.60% | - | - | 0.59% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 71.46% | 0.00% | -71.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.60% | 0.00% | -94.60% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.93% | 0.00% | -27.93% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.93% | 0.00% | -27.93% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.93% | 0.00% | -27.93% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 100.02% | 0.00% | -100.02% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.15% | 0.00% | -153.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.15% | 0.00% | -153.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 20.40% | 0.00% | -20.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 58.78% | 0.00% | -58.78% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 54.68% | 0.00% | -54.68% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 20
|
- | - | - | - | - | - | 1.30% | 1.25% | 65.38% | 42.53% | -22.85% | - | - | - | 0.65 | 34.95% | - | - | -53.72% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 87.51% | 63.07% | -24.44% | - | - | - | 0.72 | 27.92% | - | - | -38.74% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 129.65% | 100.00% | -29.65% | - | - | - | 0.77 | 22.87% | - | - | -29.65% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 187.67% | 100.00% | -87.67% | - | - | - | 0.53 | 46.72% | - | - | -87.67% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 111483.15% | 100.00% | -111383.15% | - | - | - | 0.00 | 99.91% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182608.70% | 100.00% | -182508.70% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 437.04% | 100.00% | -337.04% | - | - | - | 0.23 | 77.12% | - | - | -337.04% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 27349.40% | 100.00% | -27249.40% | - | - | - | 0.00 | 99.63% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 323.95% | 100.00% | -223.95% | - | - | - | 0.31 | 69.13% | - | - | -223.95% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 61.53% | 100.00% | 38.47% | - | - | - | 1.63 | -62.53% | - | - | 38.47% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.03% | 100.00% | 31.97% | - | - | - | 1.47 | -47.00% | - | - | 31.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 75.63% | 100.00% | 24.37% | - | - | - | 1.32 | -32.22% | - | - | 24.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 75.63% | 100.00% | 24.37% | - | - | - | 1.32 | -32.22% | - | - | 24.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 76.47% | 67.00% | -9.47% | - | - | - | 0.88 | 12.39% | - | - | -14.14% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 110.97% | 67.00% | -43.97% | - | - | - | 0.60 | 39.62% | - | - | -65.63% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 329640.00% | 67.00% | -329573.00% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9228.24% | 67.00% | -9161.24% | - | - | - | 0.01 | 99.27% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1194.53% | 67.00% | -1127.53% | - | - | - | 0.06 | 94.39% | - | - | -1682.89% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 469.97% | 67.00% | -402.97% | - | - | - | 0.14 | 85.74% | - | - | -601.45% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 106.59% | 67.00% | -39.59% | - | - | - | 0.63 | 37.14% | - | - | -59.08% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 98.03% | 67.00% | -31.03% | - | - | - | 0.68 | 31.65% | - | - | -46.31% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 53.64% | 67.00% | 13.36% | - | - | - | 1.25 | -24.92% | - | - | 19.95% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 564.33 | -56332.76% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 330.14% | 67.00% | -263.14% | - | - | - | 0.20 | 79.71% | - | - | -392.75% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.97% | 67.00% | -166.97% | - | - | - | 0.29 | 71.36% | - | - | -249.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 142.97% | 67.00% | -75.97% | - | - | - | 0.47 | 53.14% | - | - | -113.39% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 988.23% | 67.00% | -921.23% | - | - | - | 0.07 | 93.22% | - | - | -1374.98% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 452.79 | -45179.27% | - | - | 99.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 121.24 | -12024.32% | - | - | 99.18% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 109.50% | 100.00% | -9.50% | - | - | - | 0.91 | 8.68% | - | - | -9.50% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 158.00% | 100.00% | -58.00% | - | - | - | 0.63 | 36.71% | - | - | -58.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 17871.97% | 100.00% | -17771.97% | - | - | - | 0.01 | 99.44% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.76% | 100.00% | -87.76% | - | - | - | 0.53 | 46.74% | - | - | -87.76% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 151.63% | 100.00% | -51.63% | - | - | - | 0.66 | 34.05% | - | - | -51.63% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 164.28% | 100.00% | -64.28% | - | - | - | 0.61 | 39.13% | - | - | -64.28% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 51.54% | 100.00% | 48.46% | - | - | - | 1.94 | -94.01% | - | - | 48.46% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 276.65% | 100.00% | -176.65% | - | - | - | 0.36 | 63.85% | - | - | -176.65% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 174.74% | 100.00% | -74.74% | - | - | - | 0.57 | 42.77% | - | - | -74.74% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.93% | 100.00% | -74.93% | - | - | - | 0.57 | 42.83% | - | - | -74.93% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.72% | 100.00% | 43.28% | - | - | - | 1.76 | -76.31% | - | - | 43.28% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.72% | 100.00% | 43.28% | - | - | - | 1.76 | -76.31% | - | - | 43.28% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 58.75% | 0.00% | -58.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 23.30% | 0.00% | -23.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 14.24% | 0.00% | -14.24% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 0.00% | -71.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1012.10% | 0.00% | -1012.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 109.37% | 0.00% | -109.37% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 44.49% | 0.00% | -44.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1036.17% | 0.00% | -1036.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.46% | 0.00% | -5.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 0.00% | -123.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 0.00% | -123.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.56% | 0.00% | -80.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.56% | 0.00% | -80.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 53.05% | 69.88% | 16.83% | - | - | - | 1.32 | -31.72% | - | - | 24.08% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7.01% | 68.00% | 60.99% | - | - | - | 9.70 | -870.27% | - | - | 89.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TAPADERA GALVANIZADA CUADRADA 4" CIEGA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.17% | 72.00% | 71.83% | - | - | - | 433.81 | -43281.42% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 72.00% | 66.30% | - | - | - | 12.64 | -1163.54% | - | - | 92.09% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 41.07% | 0.00% | -41.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.89% | 0.00% | -56.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.89% | 0.00% | -56.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.89% | 0.00% | -56.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.89% | 0.00% | -56.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 1
|
- | - | - | - | - | - | 1.30% | 1.25% | 96.78% | 63.05% | -33.73% | - | - | - | 0.65 | 34.86% | - | - | -53.50% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 115.73% | 100.00% | -15.73% | - | - | - | 0.86 | 13.59% | - | - | -15.73% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 146.52% | 100.00% | -46.52% | - | - | - | 0.68 | 31.75% | - | - | -46.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 196.86% | 100.00% | -96.86% | - | - | - | 0.51 | 49.20% | - | - | -96.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 196.86% | 100.00% | -96.86% | - | - | - | 0.51 | 49.20% | - | - | -96.86% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 64.75% | 100.00% | 35.25% | - | - | - | 1.54 | -54.43% | - | - | 35.25% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 485.93% | 100.00% | -385.93% | - | - | - | 0.21 | 79.42% | - | - | -385.93% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 350.51% | 100.00% | -250.51% | - | - | - | 0.29 | 71.47% | - | - | -250.51% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 279.20% | 100.00% | -179.20% | - | - | - | 0.36 | 64.18% | - | - | -179.20% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3555.90% | 100.00% | -3455.90% | - | - | - | 0.03 | 97.19% | - | - | -3455.90% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 124.74% | 100.00% | -24.74% | - | - | - | 0.80 | 19.84% | - | - | -24.74% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.63% | 100.00% | 97.37% | - | - | - | 38.01 | -3700.86% | - | - | 97.37% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 21.41% | 100.00% | 78.59% | - | - | - | 4.67 | -367.09% | - | - | 78.59% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 14.41 | -1341.00% | - | - | 93.06% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | -0.00% | -0.00% | 0.00% | 100.00% | 100.00% | - | - | - | -0.02 | 102.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 135.21% | 100.00% | -35.21% | - | - | - | 0.74 | 26.04% | - | - | -35.21% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 161.04% | 100.00% | -61.04% | - | - | - | 0.62 | 37.90% | - | - | -61.04% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 310.99% | 100.00% | -210.99% | - | - | - | 0.32 | 67.84% | - | - | -210.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 287.82% | 100.00% | -187.82% | - | - | - | 0.35 | 65.26% | - | - | -187.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 95.11% | 100.00% | 4.89% | - | - | - | 1.05 | -5.14% | - | - | 4.89% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 12154.62% | 100.00% | -12054.62% | - | - | - | 0.01 | 99.18% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.69% | 100.00% | 11.31% | - | - | - | 1.13 | -12.75% | - | - | 11.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 13.21% | 100.00% | 86.79% | - | - | - | 7.57 | -657.28% | - | - | 86.79% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 47.63% | 100.00% | 52.37% | - | - | - | 2.10 | -109.96% | - | - | 52.37% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 115.84% | 100.00% | -15.84% | - | - | - | 0.86 | 13.67% | - | - | -15.84% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RECARGO POR SUSPENSIÓN DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 107.06% | 100.00% | -7.06% | - | - | - | 0.93 | 6.59% | - | - | -7.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 107.06% | 100.00% | -7.06% | - | - | - | 0.93 | 6.59% | - | - | -7.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 132.76% | 100.00% | -32.76% | - | - | - | 0.75 | 24.67% | - | - | -32.76% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 186.78% | 100.00% | -86.78% | - | - | - | 0.54 | 46.46% | - | - | -86.78% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 12020.82% | 100.00% | -11920.82% | - | - | - | 0.01 | 99.17% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 316.53% | 100.00% | -216.53% | - | - | - | 0.32 | 68.41% | - | - | -216.53% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 265.53% | 100.00% | -165.53% | - | - | - | 0.38 | 62.34% | - | - | -165.53% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 70.91% | 100.00% | 29.09% | - | - | - | 1.41 | -41.02% | - | - | 29.09% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.33% | 100.00% | 12.67% | - | - | - | 1.15 | -14.51% | - | - | 12.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.11% | 100.00% | 83.89% | - | - | - | 6.21 | -520.85% | - | - | 83.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1825.21 | -182421.00% | - | - | 99.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AROMATIZANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 74.09% | 100.00% | 25.91% | - | - | - | 1.35 | -34.97% | - | - | 25.91% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 74.09% | 100.00% | 25.91% | - | - | - | 1.35 | -34.97% | - | - | 25.91% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUCHILLA PRECORTADA 18MM CON ESTUCHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 72.38% | 100.00% | 27.62% | - | - | - | 1.38 | -38.17% | - | - | 27.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 97.47% | 100.00% | 2.53% | - | - | - | 1.03 | -2.59% | - | - | 2.53% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 451330.91% | 100.00% | -451230.91% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2712.97% | 100.00% | -2612.97% | - | - | - | 0.04 | 96.31% | - | - | -2612.97% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 668.38% | 100.00% | -568.38% | - | - | - | 0.15 | 85.04% | - | - | -568.38% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.29% | 100.00% | -243.29% | - | - | - | 0.29 | 70.87% | - | - | -243.29% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4'X8'X1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 36.67% | 100.00% | 63.33% | - | - | - | 2.73 | -172.72% | - | - | 63.33% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.12% | 100.00% | 87.88% | - | - | - | 8.25 | -724.79% | - | - | 87.88% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 825.52 | -82452.00% | - | - | 99.88% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 419.78% | 100.00% | -319.78% | - | - | - | 0.24 | 76.18% | - | - | -319.78% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 89.56% | 100.00% | 10.44% | - | - | - | 1.12 | -11.66% | - | - | 10.44% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 129.32% | 100.00% | -29.32% | - | - | - | 0.77 | 22.67% | - | - | -29.32% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 166.98% | 100.00% | -66.98% | - | - | - | 0.60 | 40.11% | - | - | -66.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 93.81% | 86.12% | -7.69% | - | - | - | 0.92 | 8.20% | - | - | -8.93% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.44% | 88.00% | -13.44% | - | - | - | 0.87 | 13.25% | - | - | -15.27% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 104.47% | 88.00% | -16.47% | - | - | - | 0.84 | 15.76% | - | - | -18.71% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.55% | 88.00% | 87.45% | - | - | - | 159.47 | -15847.11% | - | - | 99.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.21% | 84.00% | -1.21% | - | - | - | 0.99 | 1.42% | - | - | -1.44% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 87.57% | 84.00% | -3.57% | - | - | - | 0.96 | 4.08% | - | - | -4.25% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.08% | 0.00% | -72.08% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.95% | 0.00% | -94.95% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 402.45% | 0.00% | -402.45% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 402.45% | 0.00% | -402.45% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 402.45% | 0.00% | -402.45% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 54.17% | 0.00% | -54.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.95% | 0.00% | -82.95% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.95% | 0.00% | -82.95% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 59.31% | 0.00% | -59.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 42.30% | 0.00% | -42.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 121.89% | 0.00% | -121.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 117.78% | 0.00% | -117.78% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 0.00% | -99.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 0.00% | -42.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.77% | 0.00% | -81.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.69% | 0.00% | -46.69% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 2
|
- | - | - | - | - | - | 1.30% | 1.25% | 94.88% | 63.05% | -31.83% | - | - | - | 0.66 | 33.55% | - | - | -50.49% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 95.38% | 86.12% | -9.26% | - | - | - | 0.90 | 9.71% | - | - | -10.75% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 104.00% | 88.00% | -16.00% | - | - | - | 0.85 | 15.39% | - | - | -18.19% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 107.12% | 88.00% | -19.12% | - | - | - | 0.82 | 17.85% | - | - | -21.73% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.66% | 84.00% | -1.66% | - | - | - | 0.98 | 1.94% | - | - | -1.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 88.03% | 84.00% | -4.03% | - | - | - | 0.95 | 4.58% | - | - | -4.80% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 84.00% | -1.81% | - | - | - | 0.98 | 2.11% | - | - | -2.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 99.31% | 100.00% | 0.69% | - | - | - | 1.01 | -0.69% | - | - | 0.69% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 127.15% | 100.00% | -27.15% | - | - | - | 0.79 | 21.35% | - | - | -27.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 175.78% | 100.00% | -75.78% | - | - | - | 0.57 | 43.11% | - | - | -75.78% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 175.78% | 100.00% | -75.78% | - | - | - | 0.57 | 43.11% | - | - | -75.78% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 48.03% | 100.00% | 51.97% | - | - | - | 2.08 | -108.21% | - | - | 51.97% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.55% | 100.00% | -120.55% | - | - | - | 0.45 | 54.66% | - | - | -120.55% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 68.97% | 100.00% | 31.03% | - | - | - | 1.45 | -45.00% | - | - | 31.03% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 6424.26% | 100.00% | -6324.26% | - | - | - | 0.02 | 98.44% | - | - | -6324.26% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 104.15% | 100.00% | -4.15% | - | - | - | 0.96 | 3.99% | - | - | -4.15% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.51% | 100.00% | 46.49% | - | - | - | 1.87 | -86.87% | - | - | 46.49% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1963.35% | 100.00% | -1863.35% | - | - | - | 0.05 | 94.91% | - | - | -1863.35% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 581.27% | 100.00% | -481.27% | - | - | - | 0.17 | 82.80% | - | - | -481.27% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 686.26% | 100.00% | -586.26% | - | - | - | 0.15 | 85.43% | - | - | -586.26% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 869.44 | -86844.00% | - | - | 99.88% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 122.79% | 100.00% | -22.79% | - | - | - | 0.81 | 18.56% | - | - | -22.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 152.63% | 100.00% | -52.63% | - | - | - | 0.66 | 34.48% | - | - | -52.63% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 336.90% | 100.00% | -236.90% | - | - | - | 0.30 | 70.32% | - | - | -236.90% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 4807.82 | -480682.00% | - | - | 99.98% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 326.34 | -32534.00% | - | - | 99.69% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 101.03% | 100.00% | -1.03% | - | - | - | 0.99 | 1.02% | - | - | -1.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 101.03% | 100.00% | -1.03% | - | - | - | 0.99 | 1.02% | - | - | -1.03% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 107.23% | 100.00% | -7.23% | - | - | - | 0.93 | 6.74% | - | - | -7.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 124.07% | 100.00% | -24.07% | - | - | - | 0.81 | 19.40% | - | - | -24.07% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7085.49% | 100.00% | -6985.49% | - | - | - | 0.01 | 98.59% | - | - | -6985.49% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 379.09% | 100.00% | -279.09% | - | - | - | 0.26 | 73.62% | - | - | -279.09% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 53.03% | 100.00% | 46.97% | - | - | - | 1.89 | -88.58% | - | - | 46.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.33% | 100.00% | 12.67% | - | - | - | 1.15 | -14.51% | - | - | 12.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.11% | 100.00% | 83.89% | - | - | - | 6.21 | -520.85% | - | - | 83.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 11.42% | 100.00% | 88.58% | - | - | - | 8.75 | -775.40% | - | - | 88.58% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 64.25% | 100.00% | 35.75% | - | - | - | 1.56 | -55.64% | - | - | 35.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 82.21% | 100.00% | 17.79% | - | - | - | 1.22 | -21.65% | - | - | 17.79% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 271180.00% | 100.00% | -271080.00% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1276.19% | 100.00% | -1176.19% | - | - | - | 0.08 | 92.16% | - | - | -1176.19% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 114.02% | 100.00% | -14.02% | - | - | - | 0.88 | 12.30% | - | - | -14.02% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 40.66% | 100.00% | 59.34% | - | - | - | 2.46 | -145.96% | - | - | 59.34% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 10.54% | 100.00% | 89.46% | - | - | - | 9.49 | -848.51% | - | - | 89.46% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 825.52 | -82452.00% | - | - | 99.88% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 163.42 | -16242.00% | - | - | 99.39% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.66% | 100.00% | -17.66% | - | - | - | 0.85 | 15.01% | - | - | -17.66% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 124.59 | -12359.00% | - | - | 99.20% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 88.49% | 0.00% | -88.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 161.81% | 0.00% | -161.81% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 159.97% | 0.00% | -159.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 159.97% | 0.00% | -159.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 159.97% | 0.00% | -159.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 210.83% | 0.00% | -210.83% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 185.82% | 0.00% | -185.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 185.82% | 0.00% | -185.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 69.66% | 0.00% | -69.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 106.66% | 0.00% | -106.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 106.66% | 0.00% | -106.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 59.31% | 0.00% | -59.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 58.29% | 0.00% | -58.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 167.95% | 0.00% | -167.95% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.84% | 0.00% | -163.84% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 0.00% | -99.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 0.00% | -42.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/2 A LA PARED
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 0.00% | -79.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 0.00% | -49.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 21
|
- | - | - | - | - | - | 1.30% | 1.25% | 62.76% | 42.53% | -20.23% | - | - | - | 0.68 | 32.23% | - | - | -47.55% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 92.96% | 63.07% | -29.89% | - | - | - | 0.68 | 32.16% | - | - | -47.40% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 140.89% | 100.00% | -40.89% | - | - | - | 0.71 | 29.02% | - | - | -40.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 192.22% | 100.00% | -92.22% | - | - | - | 0.52 | 47.98% | - | - | -92.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 323.95% | 100.00% | -223.95% | - | - | - | 0.31 | 69.13% | - | - | -223.95% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 144.69% | 100.00% | -44.69% | - | - | - | 0.69 | 30.89% | - | - | -44.69% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.67% | 100.00% | 18.33% | - | - | - | 1.22 | -22.44% | - | - | 18.33% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.03% | 100.00% | 31.97% | - | - | - | 1.47 | -47.00% | - | - | 31.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 37.34% | 100.00% | 62.66% | - | - | - | 2.68 | -167.83% | - | - | 62.66% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 95.90% | 100.00% | 4.10% | - | - | - | 1.04 | -4.28% | - | - | 4.10% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 95.90% | 100.00% | 4.10% | - | - | - | 1.04 | -4.28% | - | - | 4.10% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 92.85% | 67.00% | -25.85% | - | - | - | 0.72 | 27.84% | - | - | -38.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 134.82% | 67.00% | -67.82% | - | - | - | 0.50 | 50.30% | - | - | -101.22% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 493132.73% | 67.00% | -493065.73% | - | - | - | 0.00 | 99.99% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7250.16% | 67.00% | -7183.16% | - | - | - | 0.01 | 99.08% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2390.01% | 67.00% | -2323.01% | - | - | - | 0.03 | 97.20% | - | - | -3467.18% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 210.86% | 67.00% | -143.86% | - | - | - | 0.32 | 68.23% | - | - | -214.71% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 787.47% | 67.00% | -720.47% | - | - | - | 0.09 | 91.49% | - | - | -1075.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 207.22% | 67.00% | -140.22% | - | - | - | 0.32 | 67.67% | - | - | -209.28% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 151.11% | 67.00% | -84.11% | - | - | - | 0.44 | 55.66% | - | - | -125.53% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.40% | 67.00% | -40.40% | - | - | - | 0.62 | 37.62% | - | - | -60.30% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 31.32% | 67.00% | 35.68% | - | - | - | 2.14 | -113.93% | - | - | 53.26% | - | 0.00% |
|
ACERO DE 1/2 X 12 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 251.92% | 67.00% | -184.92% | - | - | - | 0.27 | 73.40% | - | - | -276.00% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.97% | 67.00% | -166.97% | - | - | - | 0.29 | 71.36% | - | - | -249.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 233.63% | 67.00% | -166.63% | - | - | - | 0.29 | 71.32% | - | - | -248.71% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1005.54% | 67.00% | -938.54% | - | - | - | 0.07 | 93.34% | - | - | -1400.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 109.15% | 67.00% | -42.15% | - | - | - | 0.61 | 38.62% | - | - | -62.91% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 47.08% | 67.00% | 19.92% | - | - | - | 1.42 | -42.31% | - | - | 29.73% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 47.08% | 67.00% | 19.92% | - | - | - | 1.42 | -42.31% | - | - | 29.73% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 106.32% | 100.00% | -6.32% | - | - | - | 0.94 | 5.94% | - | - | -6.32% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 151.49% | 100.00% | -51.49% | - | - | - | 0.66 | 33.99% | - | - | -51.49% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 17575.98% | 100.00% | -17475.98% | - | - | - | 0.01 | 99.43% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 335.90% | 100.00% | -235.90% | - | - | - | 0.30 | 70.23% | - | - | -235.90% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 127.90% | 100.00% | -27.90% | - | - | - | 0.78 | 21.81% | - | - | -27.90% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.47% | 100.00% | -20.47% | - | - | - | 0.83 | 16.99% | - | - | -20.47% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.11% | 100.00% | 83.89% | - | - | - | 6.21 | -520.85% | - | - | 83.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 321.52% | 100.00% | -221.52% | - | - | - | 0.31 | 68.90% | - | - | -221.52% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 174.74% | 100.00% | -74.74% | - | - | - | 0.57 | 42.77% | - | - | -74.74% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.93% | 100.00% | -74.93% | - | - | - | 0.57 | 42.83% | - | - | -74.93% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 57.34% | 100.00% | 42.66% | - | - | - | 1.74 | -74.40% | - | - | 42.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 57.34% | 100.00% | 42.66% | - | - | - | 1.74 | -74.40% | - | - | 42.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 56.37% | 0.00% | -56.37% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 15.41% | 0.00% | -15.41% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 13.15% | 0.00% | -13.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 107.03% | 0.00% | -107.03% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 83.28% | 0.00% | -83.28% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 66.74% | 0.00% | -66.74% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 828.94% | 0.00% | -828.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.44% | 0.00% | -4.44% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 81.49% | 0.00% | -81.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 81.49% | 0.00% | -81.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 52.94% | 69.88% | 16.94% | - | - | - | 1.32 | -31.99% | - | - | 24.24% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 99.79% | 68.00% | -31.79% | - | - | - | 0.68 | 31.86% | - | - | -46.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.17% | 72.00% | 71.83% | - | - | - | 433.81 | -43281.42% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 72.00% | 66.30% | - | - | - | 12.64 | -1163.54% | - | - | 92.09% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 25.96% | 0.00% | -25.96% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 3.67% | 0.00% | -3.67% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 36
|
- | - | - | - | - | - | 1.30% | 1.25% | 92.11% | 63.05% | -29.06% | - | - | - | 0.68 | 31.55% | - | - | -46.09% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 105.92% | 100.00% | -5.92% | - | - | - | 0.94 | 5.59% | - | - | -5.92% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 132.23% | 100.00% | -32.23% | - | - | - | 0.76 | 24.38% | - | - | -32.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 201.24% | 100.00% | -101.24% | - | - | - | 0.50 | 50.31% | - | - | -101.24% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 314.04% | 100.00% | -214.04% | - | - | - | 0.32 | 68.16% | - | - | -214.04% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 129.25% | 100.00% | -29.25% | - | - | - | 0.77 | 22.63% | - | - | -29.25% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.77% | 100.00% | 29.23% | - | - | - | 1.41 | -41.30% | - | - | 29.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.89% | 100.00% | -6.89% | - | - | - | 0.94 | 6.44% | - | - | -6.89% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.96% | 100.00% | -27.96% | - | - | - | 0.78 | 21.85% | - | - | -27.96% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 95.60% | 100.00% | 4.40% | - | - | - | 1.05 | -4.61% | - | - | 4.40% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 5982.33% | 100.00% | -5882.33% | - | - | - | 0.02 | 98.33% | - | - | -5882.33% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.63% | 100.00% | 34.37% | - | - | - | 1.52 | -52.37% | - | - | 34.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.63% | 100.00% | 34.37% | - | - | - | 1.52 | -52.37% | - | - | 34.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 129.48% | 100.00% | -29.48% | - | - | - | 0.77 | 22.77% | - | - | -29.48% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 174.77% | 100.00% | -74.77% | - | - | - | 0.57 | 42.78% | - | - | -74.77% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1204757.78% | 100.00% | -1204657.78% | - | - | - | 0.00 | 99.99% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4004.00% | 100.00% | -3904.00% | - | - | - | 0.02 | 97.50% | - | - | -3904.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 296.67% | 100.00% | -196.67% | - | - | - | 0.34 | 66.29% | - | - | -196.67% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 180.63% | 100.00% | -80.63% | - | - | - | 0.55 | 44.64% | - | - | -80.63% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.37% | 100.00% | 18.63% | - | - | - | 1.23 | -22.89% | - | - | 18.63% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.37% | 100.00% | 18.63% | - | - | - | 1.23 | -22.89% | - | - | 18.63% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 106.18% | 100.00% | -6.18% | - | - | - | 0.94 | 5.82% | - | - | -6.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 161.50% | 100.00% | -61.50% | - | - | - | 0.62 | 38.08% | - | - | -61.50% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 161.50% | 100.00% | -61.50% | - | - | - | 0.62 | 38.08% | - | - | -61.50% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 15.85% | 100.00% | 84.15% | - | - | - | 6.31 | -530.76% | - | - | 84.15% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 309.38% | 100.00% | -209.38% | - | - | - | 0.32 | 67.68% | - | - | -209.38% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 309.38% | 100.00% | -209.38% | - | - | - | 0.32 | 67.68% | - | - | -209.38% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 34.64% | 100.00% | 65.36% | - | - | - | 2.89 | -188.72% | - | - | 65.36% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.26% | 100.00% | 68.74% | - | - | - | 3.20 | -219.86% | - | - | 68.74% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 207.23% | 100.00% | -107.23% | - | - | - | 0.48 | 51.75% | - | - | -107.23% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 11.21% | 100.00% | 88.79% | - | - | - | 8.92 | -791.73% | - | - | 88.79% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 9.51% | 100.00% | 90.49% | - | - | - | 10.52 | -951.88% | - | - | 90.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.52% | 100.00% | 46.48% | - | - | - | 1.87 | -86.86% | - | - | 46.48% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 411.87% | 100.00% | -311.87% | - | - | - | 0.24 | 75.72% | - | - | -311.87% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 77.51% | 100.00% | 22.49% | - | - | - | 1.29 | -29.02% | - | - | 22.49% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 112.92% | 100.00% | -12.92% | - | - | - | 0.89 | 11.44% | - | - | -12.92% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 231465.45% | 100.00% | -231365.45% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 135.27% | 100.00% | -35.27% | - | - | - | 0.74 | 26.08% | - | - | -35.27% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.01% | 100.00% | 27.99% | - | - | - | 1.39 | -38.87% | - | - | 27.99% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 287.01% | 100.00% | -187.01% | - | - | - | 0.35 | 65.16% | - | - | -187.01% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.61% | 100.00% | -166.61% | - | - | - | 0.38 | 62.49% | - | - | -166.61% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 168.20% | 100.00% | -68.20% | - | - | - | 0.59 | 40.55% | - | - | -68.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 887.93% | 100.00% | -787.93% | - | - | - | 0.11 | 88.74% | - | - | -787.93% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 122.34% | 100.00% | -22.34% | - | - | - | 0.82 | 18.26% | - | - | -22.34% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 56.46% | 86.12% | 29.66% | - | - | - | 1.53 | -52.54% | - | - | 34.44% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 105.47% | 88.00% | -17.47% | - | - | - | 0.83 | 16.56% | - | - | -19.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 108.64% | 88.00% | -20.64% | - | - | - | 0.81 | 19.00% | - | - | -23.45% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.24% | 84.00% | 82.76% | - | - | - | 67.48 | -6648.30% | - | - | 98.52% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.74% | 84.00% | 41.26% | - | - | - | 1.97 | -96.55% | - | - | 49.12% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 91.31% | 0.00% | -91.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 174.22% | 0.00% | -174.22% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 170.33% | 0.00% | -170.33% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 75.79% | 0.00% | -75.79% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 73.87% | 0.00% | -73.87% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO SERVICIOS MATERIALES Y MANO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.26% | 0.00% | -129.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.26% | 0.00% | -129.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.26% | 0.00% | -129.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 34.83% | 0.00% | -34.83% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 16.40% | 0.00% | -16.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO SERVICIOS MATERIALES Y MANO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 143.62% | 0.00% | -143.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 133.18% | 0.00% | -133.18% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 133.18% | 0.00% | -133.18% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.29% | 0.00% | -163.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.29% | 0.00% | -163.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.29% | 0.00% | -163.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 19.53% | 0.00% | -19.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 56.26% | 0.00% | -56.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 52.15% | 0.00% | -52.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 17
|
- | - | - | - | - | - | 1.30% | 1.25% | 58.57% | 42.53% | -16.04% | - | - | - | 0.73 | 27.39% | - | - | -37.72% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 50.74% | 63.07% | 12.33% | - | - | - | 1.24 | -24.31% | - | - | 19.56% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 107.95% | 100.00% | -7.95% | - | - | - | 0.93 | 7.36% | - | - | -7.95% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 157.39% | 100.00% | -57.39% | - | - | - | 0.64 | 36.46% | - | - | -57.39% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 323.95% | 100.00% | -223.95% | - | - | - | 0.31 | 69.13% | - | - | -223.95% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 19.29% | 100.00% | 80.71% | - | - | - | 5.18 | -418.48% | - | - | 80.71% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.03% | 100.00% | 31.97% | - | - | - | 1.47 | -47.00% | - | - | 31.97% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 46.98% | 67.00% | 20.02% | - | - | - | 1.43 | -42.63% | - | - | 29.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 55.54% | 67.00% | 11.46% | - | - | - | 1.21 | -20.64% | - | - | 17.11% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 54205.45% | 67.00% | -54138.45% | - | - | - | 0.00 | 99.88% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2070.94% | 67.00% | -2003.94% | - | - | - | 0.03 | 96.76% | - | - | -2990.95% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2044.33% | 67.00% | -1977.33% | - | - | - | 0.03 | 96.72% | - | - | -2951.25% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 147.65% | 67.00% | -80.65% | - | - | - | 0.45 | 54.62% | - | - | -120.37% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 98.57% | 67.00% | -31.57% | - | - | - | 0.68 | 32.03% | - | - | -47.12% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 564.33 | -56332.76% | - | - | 99.82% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 434.35% | 67.00% | -367.35% | - | - | - | 0.15 | 84.57% | - | - | -548.29% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.97% | 67.00% | -166.97% | - | - | - | 0.29 | 71.36% | - | - | -249.21% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 232.47% | 67.00% | -165.47% | - | - | - | 0.29 | 71.18% | - | - | -246.97% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 710.93% | 67.00% | -643.93% | - | - | - | 0.09 | 90.58% | - | - | -961.09% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.14% | 67.00% | -65.14% | - | - | - | 0.51 | 49.30% | - | - | -97.23% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 452.79 | -45179.27% | - | - | 99.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 121.24 | -12024.32% | - | - | 99.18% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 67.00% | 67.00% | - | - | - | 13355.22 | -1335422.39% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 40.65% | 100.00% | 59.35% | - | - | - | 2.46 | -146.00% | - | - | 59.35% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 29.13% | 100.00% | 70.87% | - | - | - | 3.43 | -243.30% | - | - | 70.87% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2766.17% | 100.00% | -2666.17% | - | - | - | 0.04 | 96.38% | - | - | -2666.17% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 179.60% | 100.00% | -79.60% | - | - | - | 0.56 | 44.32% | - | - | -79.60% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 78.41% | 100.00% | 21.59% | - | - | - | 1.28 | -27.53% | - | - | 21.59% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 98.57% | 100.00% | 1.43% | - | - | - | 1.01 | -1.45% | - | - | 1.43% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 32.21% | 100.00% | 67.79% | - | - | - | 3.10 | -210.42% | - | - | 67.79% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.55% | 100.00% | -6.55% | - | - | - | 0.94 | 6.15% | - | - | -6.55% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 16308.96 | -1630796.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 40.70% | 0.00% | -40.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 3.52% | 0.00% | -3.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.15% | 0.00% | -0.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 15.02% | 0.00% | -15.02% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 621.70% | 0.00% | -621.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.13% | 0.00% | -37.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.13% | 0.00% | -37.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 63.46% | 0.00% | -63.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 63.46% | 0.00% | -63.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 52.96% | 69.88% | 16.92% | - | - | - | 1.32 | -31.96% | - | - | 24.22% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 99.79% | 68.00% | -31.79% | - | - | - | 0.68 | 31.86% | - | - | -46.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 72.00% | 71.81% | - | - | - | 375.83 | -37483.43% | - | - | 99.73% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 72.00% | 65.42% | - | - | - | 10.95 | -994.66% | - | - | 90.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.31% | 0.00% | -72.31% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 189.24% | 0.00% | -189.24% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 16
|
- | - | - | - | - | - | 1.30% | 1.25% | 57.79% | 42.53% | -15.26% | - | - | - | 0.74 | 26.41% | - | - | -35.89% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 49.26% | 63.07% | 13.81% | - | - | - | 1.28 | -28.03% | - | - | 21.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 58.91% | 67.00% | 8.09% | - | - | - | 1.14 | -13.74% | - | - | 12.08% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 77.95% | 67.00% | -10.95% | - | - | - | 0.86 | 14.05% | - | - | -16.35% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 54205.45% | 67.00% | -54138.45% | - | - | - | 0.00 | 99.88% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.37 | 63.15% | - | - | -171.37% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2044.33% | 67.00% | -1977.33% | - | - | - | 0.03 | 96.72% | - | - | -2951.25% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 7.59 | -659.11% | - | - | 86.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 237.50% | 67.00% | -170.50% | - | - | - | 0.28 | 71.79% | - | - | -254.47% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 240.93 | -23992.53% | - | - | 99.58% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.04 | 95.98% | - | - | -2387.56% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 220.23% | 67.00% | -153.23% | - | - | - | 0.30 | 69.58% | - | - | -228.70% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 125.45% | 67.00% | -58.45% | - | - | - | 0.53 | 46.59% | - | - | -87.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 32.64 | -3164.24% | - | - | 96.94% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 564.33 | -56332.76% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 446.51 | -44550.81% | - | - | 99.78% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 330.35% | 67.00% | -263.35% | - | - | - | 0.20 | 79.72% | - | - | -393.07% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 67.00% | -142.89% | - | - | - | 0.32 | 68.08% | - | - | -213.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 421.14% | 67.00% | -354.14% | - | - | - | 0.16 | 84.09% | - | - | -528.57% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 531.20% | 67.00% | -464.20% | - | - | - | 0.13 | 87.39% | - | - | -692.83% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1375.57% | 67.00% | -1308.57% | - | - | - | 0.05 | 95.13% | - | - | -1953.09% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 18.51 | -1751.21% | - | - | 94.60% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 452.79 | -45179.27% | - | - | 99.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 121.24 | -12024.32% | - | - | 99.18% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 67.94 | -6694.47% | - | - | 98.53% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 263.60 | -26260.48% | - | - | 99.62% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 1289.80 | -128880.36% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 760.07 | -75906.81% | - | - | 99.87% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 529.74 | -52873.55% | - | - | 99.81% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 67.00% | 67.00% | - | - | - | 13355.22 | -1335422.39% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 67.00% | 67.00% | - | - | - | 7644.61 | -764360.62% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 67.00% | 67.00% | - | - | - | 5710.62 | -570961.77% | - | - | 99.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 67.00% | 28.13% | - | - | - | 1.72 | -72.39% | - | - | 41.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 67.00% | 67.00% | - | - | - | 2135.65 | -213465.18% | - | - | 99.95% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 67.00% | 67.00% | - | - | - | 17336.39 | -1733539.07% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 67.00% | 67.00% | - | - | - | 849.50 | -84849.97% | - | - | 99.88% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 46.93% | 100.00% | 53.07% | - | - | - | 2.13 | -113.06% | - | - | 53.07% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 40.94% | 100.00% | 59.06% | - | - | - | 2.44 | -144.26% | - | - | 59.06% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 82755.56% | 100.00% | -82655.56% | - | - | - | 0.00 | 99.88% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 117.20% | 100.00% | -17.20% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 142.38% | 100.00% | -42.38% | - | - | - | 0.70 | 29.76% | - | - | -42.38% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 12 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 186.93% | 100.00% | -86.93% | - | - | - | 0.53 | 46.50% | - | - | -86.93% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 68.19% | 100.00% | 31.81% | - | - | - | 1.47 | -46.65% | - | - | 31.81% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.95% | 100.00% | -142.95% | - | - | - | 0.41 | 58.84% | - | - | -142.95% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 33.13% | 100.00% | 66.87% | - | - | - | 3.02 | -201.81% | - | - | 66.87% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 16308.96 | -1630796.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 38.41% | 100.00% | 61.59% | - | - | - | 2.60 | -160.34% | - | - | 61.59% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 22.08% | 100.00% | 77.92% | - | - | - | 4.53 | -352.98% | - | - | 77.92% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 764.78% | 100.00% | -664.78% | - | - | - | 0.13 | 86.92% | - | - | -664.78% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 47858.63% | 100.00% | -47758.63% | - | - | - | 0.00 | 99.79% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 124.56% | 100.00% | -24.56% | - | - | - | 0.80 | 19.72% | - | - | -24.56% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 5.36% | 100.00% | 94.64% | - | - | - | 18.67 | -1766.97% | - | - | 94.64% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 78.91% | 100.00% | 21.09% | - | - | - | 1.27 | -26.72% | - | - | 21.09% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2594.18 | -259318.00% | - | - | 99.96% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1887.30 | -188630.00% | - | - | 99.95% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 43.79% | 0.00% | -43.79% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.98% | 0.00% | -0.98% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 8.77% | 0.00% | -8.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 0.00% | -71.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 69.97% | 0.00% | -69.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 69.97% | 0.00% | -69.97% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 52.96% | 69.88% | 16.92% | - | - | - | 1.32 | -31.96% | - | - | 24.22% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 99.79% | 68.00% | -31.79% | - | - | - | 0.68 | 31.86% | - | - | -46.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 102.79% | 68.00% | -34.79% | - | - | - | 0.66 | 33.84% | - | - | -51.16% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 68.00% | -32.00% | - | - | - | 0.68 | 32.00% | - | - | -47.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 68.00% | 68.00% | - | - | - | 731.97 | -73097.24% | - | - | 99.86% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 72.00% | 71.81% | - | - | - | 375.83 | -37483.43% | - | - | 99.73% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 72.00% | 65.42% | - | - | - | 10.95 | -994.66% | - | - | 90.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 688.00 | -68699.60% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 72.00% | 72.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 72.00% | 72.00% | - | - | - | 22933.19 | -2293218.80% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.10% | 0.00% | -72.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.26% | 0.00% | -188.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.72% | 0.00% | -93.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 0.00% | -121.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 2.14% | 0.00% | -2.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 6.17% | 0.00% | -6.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.07% | 0.00% | -2.07% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.46% | 0.00% | -68.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 46.59% | 0.00% | -46.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 35
|
- | - | - | - | - | - | 1.30% | 1.25% | 83.66% | 63.05% | -20.61% | - | - | - | 0.75 | 24.64% | - | - | -32.69% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 103.59% | 100.00% | -3.59% | - | - | - | 0.97 | 3.46% | - | - | -3.59% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 126.21% | 100.00% | -26.21% | - | - | - | 0.79 | 20.77% | - | - | -26.21% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 168.24% | 100.00% | -68.24% | - | - | - | 0.59 | 40.56% | - | - | -68.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 168.24% | 100.00% | -68.24% | - | - | - | 0.59 | 40.56% | - | - | -68.24% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 57.99% | 100.00% | 42.01% | - | - | - | 1.72 | -72.46% | - | - | 42.01% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 214.13% | 100.00% | -114.13% | - | - | - | 0.47 | 53.30% | - | - | -114.13% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.27% | 100.00% | 3.73% | - | - | - | 1.04 | -3.87% | - | - | 3.73% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 5087.30% | 100.00% | -4987.30% | - | - | - | 0.02 | 98.03% | - | - | -4987.30% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 154.69% | 100.00% | -54.69% | - | - | - | 0.65 | 35.36% | - | - | -54.69% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 154.69% | 100.00% | -54.69% | - | - | - | 0.65 | 35.36% | - | - | -54.69% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 52.93% | 100.00% | 47.07% | - | - | - | 1.89 | -88.93% | - | - | 47.07% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.32% | 100.00% | 85.68% | - | - | - | 6.98 | -598.31% | - | - | 85.68% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 12.01% | 100.00% | 87.99% | - | - | - | 8.33 | -732.68% | - | - | 87.99% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.78% | 100.00% | 32.22% | - | - | - | 1.48 | -47.53% | - | - | 32.22% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 122.21% | 100.00% | -22.21% | - | - | - | 0.82 | 18.18% | - | - | -22.21% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 152.23% | 100.00% | -52.23% | - | - | - | 0.66 | 34.31% | - | - | -52.23% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 139946.67% | 100.00% | -139846.67% | - | - | - | 0.00 | 99.93% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 317.41% | 100.00% | -217.41% | - | - | - | 0.32 | 68.49% | - | - | -217.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.34% | 100.00% | -39.34% | - | - | - | 0.72 | 28.23% | - | - | -39.34% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 83.39% | 100.00% | 16.61% | - | - | - | 1.20 | -19.92% | - | - | 16.61% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 109.60% | 100.00% | -9.60% | - | - | - | 0.91 | 8.76% | - | - | -9.60% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 204.78% | 100.00% | -104.78% | - | - | - | 0.49 | 51.17% | - | - | -104.78% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.85% | 100.00% | -8.85% | - | - | - | 0.92 | 8.13% | - | - | -8.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 175.59% | 100.00% | -75.59% | - | - | - | 0.57 | 43.05% | - | - | -75.59% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 219.35% | 100.00% | -119.35% | - | - | - | 0.46 | 54.41% | - | - | -119.35% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 43.87% | 100.00% | 56.13% | - | - | - | 2.28 | -127.95% | - | - | 56.13% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 78.46% | 100.00% | 21.54% | - | - | - | 1.27 | -27.45% | - | - | 21.54% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 114.71% | 100.00% | -14.71% | - | - | - | 0.87 | 12.82% | - | - | -14.71% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 342969.09% | 100.00% | -342869.09% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 135.31% | 100.00% | -35.31% | - | - | - | 0.74 | 26.10% | - | - | -35.31% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.01% | 100.00% | 27.99% | - | - | - | 1.39 | -38.87% | - | - | 27.99% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 287.01% | 100.00% | -187.01% | - | - | - | 0.35 | 65.16% | - | - | -187.01% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.61% | 100.00% | -166.61% | - | - | - | 0.38 | 62.49% | - | - | -166.61% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 168.20% | 100.00% | -68.20% | - | - | - | 0.59 | 40.55% | - | - | -68.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 887.93% | 100.00% | -787.93% | - | - | - | 0.11 | 88.74% | - | - | -787.93% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 122.34% | 100.00% | -22.34% | - | - | - | 0.82 | 18.26% | - | - | -22.34% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 65.27% | 86.12% | 20.85% | - | - | - | 1.32 | -31.95% | - | - | 24.22% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 104.28% | 88.00% | -16.28% | - | - | - | 0.84 | 15.61% | - | - | -18.50% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 107.02% | 88.00% | -19.02% | - | - | - | 0.82 | 17.77% | - | - | -21.61% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.91% | 88.00% | 75.09% | - | - | - | 6.82 | -581.53% | - | - | 85.33% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 21.32% | 84.00% | 62.68% | - | - | - | 3.94 | -294.06% | - | - | 74.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 731.87% | 84.00% | -647.87% | - | - | - | 0.11 | 88.52% | - | - | -771.27% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 65.52% | 0.00% | -65.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.42% | 0.00% | -98.42% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 0.00% | -94.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 247.29% | 0.00% | -247.29% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.86% | 0.00% | -193.86% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.86% | 0.00% | -193.86% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 88.59% | 0.00% | -88.59% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 105.08% | 0.00% | -105.08% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 105.08% | 0.00% | -105.08% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC SISATEC SISA NEGRO DE 10 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 57.57% | 0.00% | -57.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 57.57% | 0.00% | -57.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 57.57% | 0.00% | -57.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.92% | 0.00% | -1.92% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 5.54% | 0.00% | -5.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 1.43% | 0.00% | -1.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 10
|
- | - | - | - | - | - | 1.30% | 1.25% | 130.03% | 98.52% | -31.51% | - | - | - | 0.76 | 24.23% | - | - | -31.98% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 155.66% | 98.98% | -56.68% | - | - | - | 0.64 | 36.41% | - | - | -57.26% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 382.81% | 100.00% | -282.81% | - | - | - | 0.26 | 73.88% | - | - | -282.81% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 231.39% | 100.00% | -131.39% | - | - | - | 0.43 | 56.78% | - | - | -131.39% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 231.39% | 100.00% | -131.39% | - | - | - | 0.43 | 56.78% | - | - | -131.39% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 195.39% | 100.00% | -95.39% | - | - | - | 0.51 | 48.82% | - | - | -95.39% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA SIN RODILLO DE FIBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA MOUNTAIN FULL WEATHER CUBETA MATE COLOR BLANCO DE LINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA PROCOAT CUBETA MATE COLOR BLANCO DE LINEA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 293.44% | 100.00% | -193.44% | - | - | - | 0.34 | 65.92% | - | - | -193.44% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 288.18% | 100.00% | -188.18% | - | - | - | 0.35 | 65.30% | - | - | -188.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 193.64% | 100.00% | -93.64% | - | - | - | 0.52 | 48.36% | - | - | -93.64% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 193.64% | 100.00% | -93.64% | - | - | - | 0.52 | 48.36% | - | - | -93.64% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 263.66% | 100.00% | -163.66% | - | - | - | 0.38 | 62.07% | - | - | -163.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 238.18% | 100.00% | -138.18% | - | - | - | 0.42 | 58.01% | - | - | -138.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 112.49% | 100.00% | -12.49% | - | - | - | 0.89 | 11.10% | - | - | -12.49% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 184.50% | 100.00% | -84.50% | - | - | - | 0.54 | 45.80% | - | - | -84.50% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 164.24% | 100.00% | -64.24% | - | - | - | 0.61 | 39.11% | - | - | -64.24% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 164.24% | 100.00% | -64.24% | - | - | - | 0.61 | 39.11% | - | - | -64.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 74.23% | 100.00% | 25.77% | - | - | - | 1.35 | -34.71% | - | - | 25.77% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 74.23% | 100.00% | 25.77% | - | - | - | 1.35 | -34.71% | - | - | 25.77% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1950.66 | -194966.00% | - | - | 99.95% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 47.67% | 100.00% | 52.33% | - | - | - | 2.10 | -109.76% | - | - | 52.33% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 35.36% | 100.00% | 64.64% | - | - | - | 2.83 | -182.80% | - | - | 64.64% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 101.89% | 100.00% | -1.89% | - | - | - | 0.98 | 1.85% | - | - | -1.89% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 97.78% | 100.00% | 2.22% | - | - | - | 1.02 | -2.27% | - | - | 2.22% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.95% | 100.00% | -154.95% | - | - | - | 0.39 | 60.78% | - | - | -154.95% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 406.92% | 100.00% | -306.92% | - | - | - | 0.25 | 75.43% | - | - | -306.92% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 41.26% | 100.00% | 58.74% | - | - | - | 2.42 | -142.37% | - | - | 58.74% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 549.22% | 0.00% | -549.22% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPONJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 532.90% | 0.00% | -532.90% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 532.90% | 0.00% | -532.90% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 138.18% | 100.00% | -38.18% | - | - | - | 0.72 | 27.63% | - | - | -38.18% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 159.85% | 100.00% | -59.85% | - | - | - | 0.63 | 37.44% | - | - | -59.85% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 216.53% | 100.00% | -116.53% | - | - | - | 0.46 | 53.82% | - | - | -116.53% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 424.58% | 100.00% | -324.58% | - | - | - | 0.24 | 76.45% | - | - | -324.58% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 297.37% | 100.00% | -197.37% | - | - | - | 0.34 | 66.37% | - | - | -197.37% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 99.17% | 100.00% | 0.83% | - | - | - | 1.01 | -0.84% | - | - | 0.83% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.06% | 100.00% | -20.06% | - | - | - | 0.83 | 16.71% | - | - | -20.06% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.53% | 100.00% | 73.47% | - | - | - | 3.77 | -276.87% | - | - | 73.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 99.54% | 100.00% | 0.46% | - | - | - | 1.00 | -0.46% | - | - | 0.46% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 99.54% | 100.00% | 0.46% | - | - | - | 1.00 | -0.46% | - | - | 0.46% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 158.91% | 100.00% | -58.91% | - | - | - | 0.63 | 37.07% | - | - | -58.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 240.74% | 100.00% | -140.74% | - | - | - | 0.42 | 58.46% | - | - | -140.74% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 422.42% | 100.00% | -322.42% | - | - | - | 0.24 | 76.33% | - | - | -322.42% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.00% | 100.00% | -7.00% | - | - | - | 0.93 | 6.54% | - | - | -7.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.93% | 100.00% | 39.07% | - | - | - | 1.64 | -64.13% | - | - | 39.07% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.17% | 100.00% | -0.17% | - | - | - | 1.00 | 0.17% | - | - | -0.17% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.65% | 100.00% | 18.35% | - | - | - | 1.22 | -22.48% | - | - | 18.35% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.15% | 100.00% | 19.85% | - | - | - | 1.25 | -24.76% | - | - | 19.85% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.15% | 100.00% | 19.85% | - | - | - | 1.25 | -24.76% | - | - | 19.85% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 145.31% | 100.00% | -45.31% | - | - | - | 0.69 | 31.18% | - | - | -45.31% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 169.51% | 100.00% | -69.51% | - | - | - | 0.59 | 41.00% | - | - | -69.51% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 169.51% | 100.00% | -69.51% | - | - | - | 0.59 | 41.00% | - | - | -69.51% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 106.65% | 100.00% | -6.65% | - | - | - | 0.94 | 6.24% | - | - | -6.65% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1086.96% | 100.00% | -986.96% | - | - | - | 0.09 | 90.80% | - | - | -986.96% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1020.97% | 100.00% | -920.97% | - | - | - | 0.10 | 90.21% | - | - | -920.97% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1020.97% | 100.00% | -920.97% | - | - | - | 0.10 | 90.21% | - | - | -920.97% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 269.46% | 100.00% | -169.46% | - | - | - | 0.37 | 62.89% | - | - | -169.46% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 177.19% | 100.00% | -77.19% | - | - | - | 0.56 | 43.56% | - | - | -77.19% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4202.73% | 100.00% | -4102.73% | - | - | - | 0.02 | 97.62% | - | - | -4102.73% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 156.91% | 100.00% | -56.91% | - | - | - | 0.64 | 36.27% | - | - | -56.91% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4'X8'X1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 101.50% | 100.00% | -1.50% | - | - | - | 0.99 | 1.48% | - | - | -1.50% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.78% | 100.00% | 73.22% | - | - | - | 3.73 | -273.46% | - | - | 73.22% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 4269.91% | 100.00% | -4169.91% | - | - | - | 0.02 | 97.66% | - | - | -4169.91% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 2221.04% | 100.00% | -2121.04% | - | - | - | 0.05 | 95.50% | - | - | -2121.04% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.36% | 100.00% | 86.64% | - | - | - | 7.48 | -648.42% | - | - | 86.64% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 108.14% | 100.00% | -8.14% | - | - | - | 0.92 | 7.52% | - | - | -8.14% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 162.69% | 100.00% | -62.69% | - | - | - | 0.61 | 38.53% | - | - | -62.69% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6432.68% | 100.00% | -6332.68% | - | - | - | 0.02 | 98.45% | - | - | -6332.68% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.98% | 100.00% | -133.98% | - | - | - | 0.43 | 57.26% | - | - | -133.98% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 195.61% | 100.00% | -95.61% | - | - | - | 0.51 | 48.88% | - | - | -95.61% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 134.10% | 100.00% | -34.10% | - | - | - | 0.75 | 25.43% | - | - | -34.10% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.03% | 100.00% | 10.97% | - | - | - | 1.12 | -12.33% | - | - | 10.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 84.88% | 100.00% | 15.12% | - | - | - | 1.18 | -17.81% | - | - | 15.12% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 301.27% | 100.00% | -201.27% | - | - | - | 0.33 | 66.81% | - | - | -201.27% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 354.24% | 100.00% | -254.24% | - | - | - | 0.28 | 71.77% | - | - | -254.24% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 195.69% | 100.00% | -95.69% | - | - | - | 0.51 | 48.90% | - | - | -95.69% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 911.34% | 100.00% | -811.34% | - | - | - | 0.11 | 89.03% | - | - | -811.34% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.11% | 100.00% | 51.89% | - | - | - | 2.08 | -107.87% | - | - | 51.89% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.11% | 100.00% | 51.89% | - | - | - | 2.08 | -107.87% | - | - | 51.89% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.88% | 100.00% | 54.12% | - | - | - | 2.18 | -117.95% | - | - | 54.12% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 58.26% | 93.64% | 35.38% | - | - | - | 1.61 | -60.74% | - | - | 37.79% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 88.00% | -12.13% | - | - | - | 0.88 | 12.12% | - | - | -13.79% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 88.00% | -15.14% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 11.08% | 100.00% | 88.92% | - | - | - | 9.02 | -802.33% | - | - | 88.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 11.22% | 100.00% | 88.78% | - | - | - | 8.91 | -791.46% | - | - | 88.78% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 37
|
- | - | - | - | - | - | 1.30% | 1.25% | 82.78% | 63.05% | -19.73% | - | - | - | 0.76 | 23.83% | - | - | -31.29% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 100.56% | 100.00% | -0.56% | - | - | - | 0.99 | 0.56% | - | - | -0.56% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 124.37% | 100.00% | -24.37% | - | - | - | 0.80 | 19.59% | - | - | -24.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 154.11% | 100.00% | -54.11% | - | - | - | 0.65 | 35.11% | - | - | -54.11% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 289315.56% | 100.00% | -289215.56% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 500.50% | 100.00% | -400.50% | - | - | - | 0.20 | 80.02% | - | - | -400.50% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 360.65% | 100.00% | -260.65% | - | - | - | 0.28 | 72.27% | - | - | -260.65% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 94.49% | 100.00% | 5.51% | - | - | - | 1.06 | -5.83% | - | - | 5.51% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 94.49% | 100.00% | 5.51% | - | - | - | 1.06 | -5.83% | - | - | 5.51% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 109.16% | 100.00% | -9.16% | - | - | - | 0.92 | 8.39% | - | - | -9.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 154.62% | 100.00% | -54.62% | - | - | - | 0.65 | 35.32% | - | - | -54.62% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 213.89% | 100.00% | -113.89% | - | - | - | 0.47 | 53.25% | - | - | -113.89% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 129.40% | 100.00% | -29.40% | - | - | - | 0.77 | 22.72% | - | - | -29.40% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.77% | 100.00% | 29.23% | - | - | - | 1.41 | -41.30% | - | - | 29.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.89% | 100.00% | -6.89% | - | - | - | 0.94 | 6.44% | - | - | -6.89% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 128.35% | 100.00% | -28.35% | - | - | - | 0.78 | 22.09% | - | - | -28.35% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 67.65% | 100.00% | 32.35% | - | - | - | 1.48 | -47.82% | - | - | 32.35% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 67.65% | 100.00% | 32.35% | - | - | - | 1.48 | -47.82% | - | - | 32.35% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 101.37% | 100.00% | -1.37% | - | - | - | 0.99 | 1.35% | - | - | -1.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 126.76% | 100.00% | -26.76% | - | - | - | 0.79 | 21.11% | - | - | -26.76% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 126.76% | 100.00% | -26.76% | - | - | - | 0.79 | 21.11% | - | - | -26.76% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 60.37% | 100.00% | 39.63% | - | - | - | 1.66 | -65.64% | - | - | 39.63% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 866.27% | 100.00% | -766.27% | - | - | - | 0.12 | 88.46% | - | - | -766.27% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 866.27% | 100.00% | -766.27% | - | - | - | 0.12 | 88.46% | - | - | -766.27% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 162.91% | 100.00% | -62.91% | - | - | - | 0.61 | 38.62% | - | - | -62.91% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 5.56% | 100.00% | 94.44% | - | - | - | 17.98 | -1697.97% | - | - | 94.44% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4780.08% | 100.00% | -4680.08% | - | - | - | 0.02 | 97.91% | - | - | -4680.08% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 21.53% | 100.00% | 78.47% | - | - | - | 4.65 | -364.52% | - | - | 78.47% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.32% | 100.00% | 85.68% | - | - | - | 6.98 | -598.31% | - | - | 85.68% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 10.04% | 100.00% | 89.96% | - | - | - | 9.96 | -895.72% | - | - | 89.96% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 49.97% | 100.00% | 50.03% | - | - | - | 2.00 | -100.14% | - | - | 50.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 77.56% | 100.00% | 22.44% | - | - | - | 1.29 | -28.94% | - | - | 22.44% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 113.01% | 100.00% | -13.01% | - | - | - | 0.88 | 11.51% | - | - | -13.01% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 33585.45% | 100.00% | -33485.45% | - | - | - | 0.00 | 99.70% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 218.82% | 100.00% | -118.82% | - | - | - | 0.46 | 54.30% | - | - | -118.82% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 171.68% | 100.00% | -71.68% | - | - | - | 0.58 | 41.75% | - | - | -71.68% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 294.90% | 100.00% | -194.90% | - | - | - | 0.34 | 66.09% | - | - | -194.90% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 131.93% | 100.00% | -31.93% | - | - | - | 0.76 | 24.20% | - | - | -31.93% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.01% | 100.00% | 27.99% | - | - | - | 1.39 | -38.86% | - | - | 27.99% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 303.60% | 100.00% | -203.60% | - | - | - | 0.33 | 67.06% | - | - | -203.60% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 268.68% | 100.00% | -168.68% | - | - | - | 0.37 | 62.78% | - | - | -168.68% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.97% | 100.00% | -43.97% | - | - | - | 0.69 | 30.54% | - | - | -43.97% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 898.58% | 100.00% | -798.58% | - | - | - | 0.11 | 88.87% | - | - | -798.58% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.79% | 86.12% | 31.33% | - | - | - | 1.57 | -57.19% | - | - | 36.38% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 103.27% | 88.00% | -15.27% | - | - | - | 0.85 | 14.79% | - | - | -17.36% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.40% | 88.00% | -17.40% | - | - | - | 0.83 | 16.51% | - | - | -19.78% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 32.22% | 88.00% | 55.78% | - | - | - | 2.73 | -173.16% | - | - | 63.39% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.17% | 84.00% | 83.83% | - | - | - | 506.12 | -50511.66% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 84.00% | 78.30% | - | - | - | 14.74 | -1374.13% | - | - | 93.22% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.55% | 0.00% | -72.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 0.00% | -94.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 0.00% | -94.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 219.27% | 0.00% | -219.27% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 150.89% | 0.00% | -150.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 150.89% | 0.00% | -150.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 131.16% | 0.00% | -131.16% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 85.74% | 0.00% | -85.74% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 85.74% | 0.00% | -85.74% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 0.00% | -32.30% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 216.63% | 0.00% | -216.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 216.63% | 0.00% | -216.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 216.63% | 0.00% | -216.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 19.53% | 0.00% | -19.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 56.26% | 0.00% | -56.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 52.15% | 0.00% | -52.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 34
|
- | - | - | - | - | - | 1.30% | 1.25% | 81.93% | 63.05% | -18.88% | - | - | - | 0.77 | 23.04% | - | - | -29.94% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 99.34% | 100.00% | 0.66% | - | - | - | 1.01 | -0.67% | - | - | 0.66% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 147.52% | 100.00% | -47.52% | - | - | - | 0.68 | 32.21% | - | - | -47.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 200.67% | 100.00% | -100.67% | - | - | - | 0.50 | 50.17% | - | - | -100.67% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 200.67% | 100.00% | -100.67% | - | - | - | 0.50 | 50.17% | - | - | -100.67% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 61.12% | 100.00% | 38.88% | - | - | - | 1.64 | -63.61% | - | - | 38.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2262.92% | 100.00% | -2162.92% | - | - | - | 0.04 | 95.58% | - | - | -2162.92% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 247.51% | 100.00% | -147.51% | - | - | - | 0.40 | 59.60% | - | - | -147.51% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 247.51% | 100.00% | -147.51% | - | - | - | 0.40 | 59.60% | - | - | -147.51% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 216.91% | 100.00% | -116.91% | - | - | - | 0.46 | 53.90% | - | - | -116.91% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 111.38% | 100.00% | -11.38% | - | - | - | 0.90 | 10.22% | - | - | -11.38% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1554.26% | 100.00% | -1454.26% | - | - | - | 0.06 | 93.57% | - | - | -1454.26% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 169.47% | 100.00% | -69.47% | - | - | - | 0.59 | 40.99% | - | - | -69.47% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.45% | 100.00% | 97.55% | - | - | - | 40.89 | -3989.44% | - | - | 97.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 122.32% | 100.00% | -22.32% | - | - | - | 0.82 | 18.24% | - | - | -22.32% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 182.04% | 100.00% | -82.04% | - | - | - | 0.55 | 45.07% | - | - | -82.04% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 124.55% | 100.00% | -24.55% | - | - | - | 0.80 | 19.71% | - | - | -24.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.76% | 100.00% | 29.24% | - | - | - | 1.41 | -41.33% | - | - | 29.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.54% | 100.00% | 1.46% | - | - | - | 1.01 | -1.48% | - | - | 1.46% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.46% | 100.00% | -27.46% | - | - | - | 0.78 | 21.54% | - | - | -27.46% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.51% | 100.00% | 34.49% | - | - | - | 1.53 | -52.65% | - | - | 34.49% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.51% | 100.00% | 34.49% | - | - | - | 1.53 | -52.65% | - | - | 34.49% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 76.80% | 100.00% | 23.20% | - | - | - | 1.30 | -30.21% | - | - | 23.20% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 111.58% | 100.00% | -11.58% | - | - | - | 0.90 | 10.38% | - | - | -11.58% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 3284.07% | 100.00% | -3184.07% | - | - | - | 0.03 | 96.96% | - | - | -3184.07% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 141.75% | 100.00% | -41.75% | - | - | - | 0.71 | 29.45% | - | - | -41.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 138.24% | 100.00% | -38.24% | - | - | - | 0.72 | 27.66% | - | - | -38.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 73.82% | 100.00% | 26.18% | - | - | - | 1.35 | -35.47% | - | - | 26.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 287.01% | 100.00% | -187.01% | - | - | - | 0.35 | 65.16% | - | - | -187.01% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 267.12% | 100.00% | -167.12% | - | - | - | 0.37 | 62.56% | - | - | -167.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.54% | 100.00% | -83.54% | - | - | - | 0.54 | 45.52% | - | - | -83.54% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 890.14% | 100.00% | -790.14% | - | - | - | 0.11 | 88.77% | - | - | -790.14% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 38.87% | 100.00% | 61.13% | - | - | - | 2.57 | -157.29% | - | - | 61.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 73.74% | 100.00% | 26.26% | - | - | - | 1.36 | -35.61% | - | - | 26.26% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.92% | 100.00% | 8.08% | - | - | - | 1.09 | -8.79% | - | - | 8.08% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 56.88% | 100.00% | 43.12% | - | - | - | 1.76 | -75.81% | - | - | 43.12% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 504480.00% | 100.00% | -504380.00% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 208.66% | 100.00% | -108.66% | - | - | - | 0.48 | 52.07% | - | - | -108.66% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 16308.96 | -1630796.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RECARGO POR SUSPENSIÓN DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 64.45% | 86.12% | 21.67% | - | - | - | 1.34 | -33.63% | - | - | 25.17% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 102.76% | 88.00% | -14.76% | - | - | - | 0.86 | 14.36% | - | - | -16.77% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.40% | 88.00% | -17.40% | - | - | - | 0.83 | 16.51% | - | - | -19.78% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.51% | 88.00% | 73.49% | - | - | - | 6.07 | -506.52% | - | - | 83.51% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 21.29% | 84.00% | 62.71% | - | - | - | 3.95 | -294.56% | - | - | 74.66% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 730.94% | 84.00% | -646.94% | - | - | - | 0.11 | 88.51% | - | - | -770.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 66.80% | 0.00% | -66.80% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.53% | 0.00% | -98.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 0.00% | -94.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.19% | 0.00% | -157.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 190.10% | 0.00% | -190.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 190.10% | 0.00% | -190.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 190.10% | 0.00% | -190.10% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 102.54% | 0.00% | -102.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 119.57% | 0.00% | -119.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 119.57% | 0.00% | -119.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC SISATEC SISA NEGRO DE 10 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.92% | 0.00% | -1.92% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 5.54% | 0.00% | -5.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 1.43% | 0.00% | -1.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.89% | 0.00% | -68.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.89% | 0.00% | -68.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.89% | 0.00% | -68.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.89% | 0.00% | -68.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 33
|
- | - | - | - | - | - | 1.30% | 1.25% | 84.13% | 68.25% | -15.88% | - | - | - | 0.81 | 18.87% | - | - | -23.26% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 62.55% | 15.07% | -47.48% | - | - | - | 0.24 | 75.91% | - | - | -315.06% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.82% | 100.00% | 27.18% | - | - | - | 1.37 | -37.33% | - | - | 27.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.82% | 100.00% | 27.18% | - | - | - | 1.37 | -37.33% | - | - | 27.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.82% | 100.00% | 27.18% | - | - | - | 1.37 | -37.33% | - | - | 27.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 100.00% | 64.00% | - | - | - | 2.78 | -177.80% | - | - | 64.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 100.00% | 64.00% | - | - | - | 2.78 | -177.80% | - | - | 64.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 100.00% | 64.00% | - | - | - | 2.78 | -177.80% | - | - | 64.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9423.16 | -942216.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 104.16% | 0.00% | -104.16% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 0.00% | -94.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 77.76% | 0.00% | -77.76% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 81.63% | 0.00% | -81.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 81.63% | 0.00% | -81.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC SISATEC SISA NEGRO DE 10 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 70.48% | 0.00% | -70.48% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.92% | 0.00% | -1.92% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 5.54% | 0.00% | -5.54% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 1.43% | 0.00% | -1.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.57% | 0.00% | -68.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.57% | 0.00% | -68.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.57% | 0.00% | -68.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.57% | 0.00% | -68.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 0.00% | -85.63% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7025.06 | -702406.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7025.06 | -702406.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7025.06 | -702406.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7025.06 | -702406.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 106.83% | 100.00% | -6.83% | - | - | - | 0.94 | 6.39% | - | - | -6.83% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 126.71% | 100.00% | -26.71% | - | - | - | 0.79 | 21.08% | - | - | -26.71% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 153.50% | 100.00% | -53.50% | - | - | - | 0.65 | 34.86% | - | - | -53.50% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1771.37% | 100.00% | -1671.37% | - | - | - | 0.06 | 94.35% | - | - | -1671.37% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 262.29% | 100.00% | -162.29% | - | - | - | 0.38 | 61.87% | - | - | -162.29% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 450.53% | 100.00% | -350.53% | - | - | - | 0.22 | 77.80% | - | - | -350.53% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 208.66% | 100.00% | -108.66% | - | - | - | 0.48 | 52.07% | - | - | -108.66% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 120.83% | 100.00% | -20.83% | - | - | - | 0.83 | 17.24% | - | - | -20.83% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 182.45% | 100.00% | -82.45% | - | - | - | 0.55 | 45.19% | - | - | -82.45% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 125.51% | 100.00% | -25.51% | - | - | - | 0.80 | 20.32% | - | - | -25.51% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.76% | 100.00% | 29.24% | - | - | - | 1.41 | -41.33% | - | - | 29.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.34% | 100.00% | -0.34% | - | - | - | 1.00 | 0.34% | - | - | -0.34% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.44% | 100.00% | -27.44% | - | - | - | 0.78 | 21.53% | - | - | -27.44% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.64% | 100.00% | 38.36% | - | - | - | 1.62 | -62.22% | - | - | 38.36% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 114.49% | 100.00% | -14.49% | - | - | - | 0.87 | 12.65% | - | - | -14.49% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 147.61% | 100.00% | -47.61% | - | - | - | 0.68 | 32.25% | - | - | -47.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 147.61% | 100.00% | -47.61% | - | - | - | 0.68 | 32.25% | - | - | -47.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 60.85% | 100.00% | 39.15% | - | - | - | 1.64 | -64.34% | - | - | 39.15% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 525.95% | 100.00% | -425.95% | - | - | - | 0.19 | 80.99% | - | - | -425.95% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 525.95% | 100.00% | -425.95% | - | - | - | 0.19 | 80.99% | - | - | -425.95% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 219.23% | 100.00% | -119.23% | - | - | - | 0.46 | 54.39% | - | - | -119.23% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.19% | 100.00% | 1.81% | - | - | - | 1.02 | -1.84% | - | - | 1.81% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 5223.04% | 100.00% | -5123.04% | - | - | - | 0.02 | 98.09% | - | - | -5123.04% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 183.27% | 100.00% | -83.27% | - | - | - | 0.55 | 45.44% | - | - | -83.27% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 12.29% | 100.00% | 87.71% | - | - | - | 8.14 | -713.91% | - | - | 87.71% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.36% | 100.00% | 28.64% | - | - | - | 1.40 | -40.13% | - | - | 28.64% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 433.72% | 100.00% | -333.72% | - | - | - | 0.23 | 76.94% | - | - | -333.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 80.14% | 100.00% | 19.86% | - | - | - | 1.25 | -24.79% | - | - | 19.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 112.06% | 100.00% | -12.06% | - | - | - | 0.89 | 10.76% | - | - | -12.06% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 204381.82% | 100.00% | -204281.82% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 133.90% | 100.00% | -33.90% | - | - | - | 0.75 | 25.32% | - | - | -33.90% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.18% | 100.00% | 28.82% | - | - | - | 1.40 | -40.49% | - | - | 28.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 338.69% | 100.00% | -238.69% | - | - | - | 0.30 | 70.47% | - | - | -238.69% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 267.12% | 100.00% | -167.12% | - | - | - | 0.37 | 62.56% | - | - | -167.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.61% | 100.00% | -44.61% | - | - | - | 0.69 | 30.85% | - | - | -44.61% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 890.14% | 100.00% | -790.14% | - | - | - | 0.11 | 88.77% | - | - | -790.14% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 125.28% | 100.00% | -25.28% | - | - | - | 0.80 | 20.18% | - | - | -25.28% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.75% | 100.00% | 54.25% | - | - | - | 2.19 | -118.59% | - | - | 54.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 64.94% | 86.12% | 21.18% | - | - | - | 1.33 | -32.62% | - | - | 24.60% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 102.66% | 88.00% | -14.66% | - | - | - | 0.86 | 14.28% | - | - | -16.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.40% | 88.00% | -17.40% | - | - | - | 0.83 | 16.51% | - | - | -19.78% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 11.27% | 88.00% | 76.73% | - | - | - | 7.81 | -680.73% | - | - | 87.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 22.44% | 84.00% | 61.56% | - | - | - | 3.74 | -274.40% | - | - | 73.29% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 730.94% | 84.00% | -646.94% | - | - | - | 0.11 | 88.51% | - | - | -770.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.18% | 84.00% | 82.82% | - | - | - | 71.12 | -7012.01% | - | - | 98.59% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 8
|
- | - | - | - | - | - | 1.30% | 1.25% | 116.49% | 98.87% | -17.62% | - | - | - | 0.85 | 15.13% | - | - | -17.82% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 161.69% | 100.00% | -61.69% | - | - | - | 0.62 | 38.15% | - | - | -61.69% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 726.76% | 100.00% | -626.76% | - | - | - | 0.14 | 86.24% | - | - | -626.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 689.42% | 100.00% | -589.42% | - | - | - | 0.15 | 85.50% | - | - | -589.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 689.42% | 100.00% | -589.42% | - | - | - | 0.15 | 85.50% | - | - | -589.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MICROFIBRA 20U SURTIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPONJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 340.74% | 100.00% | -240.74% | - | - | - | 0.29 | 70.65% | - | - | -240.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 231.39% | 100.00% | -131.39% | - | - | - | 0.43 | 56.78% | - | - | -131.39% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 231.39% | 100.00% | -131.39% | - | - | - | 0.43 | 56.78% | - | - | -131.39% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 195.39% | 100.00% | -95.39% | - | - | - | 0.51 | 48.82% | - | - | -95.39% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA MOUNTAIN FULL WEATHER CUBETA MATE COLOR BLANCO DE LINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA PROCOAT CUBETA MATE COLOR BLANCO DE LINEA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 306.58% | 100.00% | -206.58% | - | - | - | 0.33 | 67.38% | - | - | -206.58% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 254.34% | 100.00% | -154.34% | - | - | - | 0.39 | 60.68% | - | - | -154.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 290.55% | 100.00% | -190.55% | - | - | - | 0.34 | 65.58% | - | - | -190.55% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 289.41% | 100.00% | -189.41% | - | - | - | 0.35 | 65.45% | - | - | -189.41% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 194.88% | 100.00% | -94.88% | - | - | - | 0.51 | 48.69% | - | - | -94.88% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 194.88% | 100.00% | -94.88% | - | - | - | 0.51 | 48.69% | - | - | -94.88% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 149.29% | 100.00% | -49.29% | - | - | - | 0.67 | 33.01% | - | - | -49.29% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 194.99% | 100.00% | -94.99% | - | - | - | 0.51 | 48.71% | - | - | -94.99% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 174.72% | 100.00% | -74.72% | - | - | - | 0.57 | 42.77% | - | - | -74.72% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 174.72% | 100.00% | -74.72% | - | - | - | 0.57 | 42.77% | - | - | -74.72% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 125.01% | 100.00% | -25.01% | - | - | - | 0.80 | 20.00% | - | - | -25.01% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 124.41% | 100.00% | -24.41% | - | - | - | 0.80 | 19.62% | - | - | -24.41% | - | 0.00% |
|
ESTUQUE ARENA SIN ARENA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1950.66 | -194966.00% | - | - | 99.95% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA AVELLANA MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 80.57% | 100.00% | 19.43% | - | - | - | 1.24 | -24.12% | - | - | 19.43% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 43.74% | 100.00% | 56.26% | - | - | - | 2.29 | -128.63% | - | - | 56.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 117.00% | 100.00% | -17.00% | - | - | - | 0.85 | 14.53% | - | - | -17.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 83.19% | 100.00% | 16.81% | - | - | - | 1.20 | -20.21% | - | - | 16.81% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.95% | 100.00% | -154.95% | - | - | - | 0.39 | 60.78% | - | - | -154.95% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 406.92% | 100.00% | -306.92% | - | - | - | 0.25 | 75.43% | - | - | -306.92% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE ARENA SIN ARENA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA AVELLANA MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 4.80% | 100.00% | 95.20% | - | - | - | 20.84 | -1984.16% | - | - | 95.20% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 4.80% | 100.00% | 95.20% | - | - | - | 20.84 | -1984.16% | - | - | 95.20% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 106.81% | 100.00% | -6.81% | - | - | - | 0.94 | 6.37% | - | - | -6.81% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 130.52% | 100.00% | -30.52% | - | - | - | 0.77 | 23.38% | - | - | -30.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 163.69% | 100.00% | -63.69% | - | - | - | 0.61 | 38.91% | - | - | -63.69% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 163.69% | 100.00% | -63.69% | - | - | - | 0.61 | 38.91% | - | - | -63.69% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 76.93% | 100.00% | 23.07% | - | - | - | 1.30 | -29.99% | - | - | 23.07% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8297.36% | 100.00% | -8197.36% | - | - | - | 0.01 | 98.79% | - | - | -8197.36% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 680.64% | 100.00% | -580.64% | - | - | - | 0.15 | 85.31% | - | - | -580.64% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 680.64% | 100.00% | -580.64% | - | - | - | 0.15 | 85.31% | - | - | -580.64% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 261.45% | 100.00% | -161.45% | - | - | - | 0.38 | 61.75% | - | - | -161.45% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 211.46% | 100.00% | -111.46% | - | - | - | 0.47 | 52.71% | - | - | -111.46% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2090.53% | 100.00% | -1990.53% | - | - | - | 0.05 | 95.22% | - | - | -1990.53% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.35% | 100.00% | 20.65% | - | - | - | 1.26 | -26.03% | - | - | 20.65% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 4.08% | 100.00% | 95.92% | - | - | - | 24.51 | -2350.99% | - | - | 95.92% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 341.79% | 100.00% | -241.79% | - | - | - | 0.29 | 70.74% | - | - | -241.79% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 119.10% | 100.00% | -19.10% | - | - | - | 0.84 | 16.04% | - | - | -19.10% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 176.67% | 100.00% | -76.67% | - | - | - | 0.57 | 43.40% | - | - | -76.67% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 284.21% | 100.00% | -184.21% | - | - | - | 0.35 | 64.82% | - | - | -184.21% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.23% | 100.00% | -6.23% | - | - | - | 0.94 | 5.87% | - | - | -6.23% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 63.88% | 100.00% | 36.12% | - | - | - | 1.57 | -56.56% | - | - | 36.12% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.38% | 100.00% | 1.62% | - | - | - | 1.02 | -1.64% | - | - | 1.62% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.65% | 100.00% | 18.35% | - | - | - | 1.22 | -22.48% | - | - | 18.35% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 64.48% | 100.00% | 35.52% | - | - | - | 1.55 | -55.09% | - | - | 35.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 64.48% | 100.00% | 35.52% | - | - | - | 1.55 | -55.09% | - | - | 35.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 117.32% | 100.00% | -17.32% | - | - | - | 0.85 | 14.76% | - | - | -17.32% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 143.21% | 100.00% | -43.21% | - | - | - | 0.70 | 30.17% | - | - | -43.21% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 148.69% | 100.00% | -48.69% | - | - | - | 0.67 | 32.74% | - | - | -48.69% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 111.45% | 100.00% | -11.45% | - | - | - | 0.90 | 10.28% | - | - | -11.45% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 141.88% | 100.00% | -41.88% | - | - | - | 0.70 | 29.52% | - | - | -41.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.53% | 100.00% | 73.47% | - | - | - | 3.77 | -276.87% | - | - | 73.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.70% | 100.00% | 8.30% | - | - | - | 1.09 | -9.05% | - | - | 8.30% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.70% | 100.00% | 8.30% | - | - | - | 1.09 | -9.05% | - | - | 8.30% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 76.48% | 100.00% | 23.52% | - | - | - | 1.31 | -30.75% | - | - | 23.52% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 102.47% | 100.00% | -2.47% | - | - | - | 0.98 | 2.41% | - | - | -2.47% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6157.64% | 100.00% | -6057.64% | - | - | - | 0.02 | 98.38% | - | - | -6057.64% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.98% | 100.00% | -133.98% | - | - | - | 0.43 | 57.26% | - | - | -133.98% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 126.01% | 100.00% | -26.01% | - | - | - | 0.79 | 20.64% | - | - | -26.01% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.15% | 100.00% | 10.85% | - | - | - | 1.12 | -12.17% | - | - | 10.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.44% | 100.00% | 27.56% | - | - | - | 1.38 | -38.05% | - | - | 27.56% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.29% | 100.00% | -136.29% | - | - | - | 0.42 | 57.68% | - | - | -136.29% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 354.24% | 100.00% | -254.24% | - | - | - | 0.28 | 71.77% | - | - | -254.24% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.82% | 100.00% | -83.82% | - | - | - | 0.54 | 45.60% | - | - | -83.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 895.69% | 100.00% | -795.69% | - | - | - | 0.11 | 88.84% | - | - | -795.69% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 96.26% | 100.00% | 3.74% | - | - | - | 1.04 | -3.89% | - | - | 3.74% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 76.13% | 100.00% | 23.87% | - | - | - | 1.31 | -31.35% | - | - | 23.87% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.97% | 100.00% | 51.03% | - | - | - | 2.04 | -104.19% | - | - | 51.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.97% | 100.00% | 51.03% | - | - | - | 2.04 | -104.19% | - | - | 51.03% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.18% | 100.00% | 54.82% | - | - | - | 2.21 | -121.36% | - | - | 54.82% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.69% | 93.64% | 38.95% | - | - | - | 1.71 | -71.23% | - | - | 41.60% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 88.00% | -12.13% | - | - | - | 0.88 | 12.12% | - | - | -13.79% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 88.00% | -15.14% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.49% | 100.00% | 96.51% | - | - | - | 28.64 | -2764.38% | - | - | 96.51% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.40% | 100.00% | 96.60% | - | - | - | 29.42 | -2842.42% | - | - | 96.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 6
|
- | - | - | - | - | - | 1.30% | 1.25% | 111.98% | 98.52% | -13.46% | - | - | - | 0.88 | 12.02% | - | - | -13.66% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 126.71% | 100.00% | -26.71% | - | - | - | 0.79 | 21.08% | - | - | -26.71% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 156.97% | 100.00% | -56.97% | - | - | - | 0.64 | 36.29% | - | - | -56.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 201.76% | 100.00% | -101.76% | - | - | - | 0.50 | 50.44% | - | - | -101.76% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5365.37% | 100.00% | -5265.37% | - | - | - | 0.02 | 98.14% | - | - | -5265.37% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 293.70% | 100.00% | -193.70% | - | - | - | 0.34 | 65.95% | - | - | -193.70% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 237.88% | 100.00% | -137.88% | - | - | - | 0.42 | 57.96% | - | - | -137.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 61.55% | 100.00% | 38.45% | - | - | - | 1.62 | -62.47% | - | - | 38.45% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 54.61% | 100.00% | 45.39% | - | - | - | 1.83 | -83.13% | - | - | 45.39% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.11% | 100.00% | 83.89% | - | - | - | 6.21 | -520.79% | - | - | 83.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.61% | 100.00% | -5.61% | - | - | - | 0.95 | 5.31% | - | - | -5.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.61% | 100.00% | -5.61% | - | - | - | 0.95 | 5.31% | - | - | -5.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 65.57% | 100.00% | 34.43% | - | - | - | 1.53 | -52.51% | - | - | 34.43% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RECARGO POR SUSPENSIÓN DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 151.43% | 100.00% | -51.43% | - | - | - | 0.66 | 33.96% | - | - | -51.43% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 231.64% | 100.00% | -131.64% | - | - | - | 0.43 | 56.83% | - | - | -131.64% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 404.64% | 100.00% | -304.64% | - | - | - | 0.25 | 75.29% | - | - | -304.64% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 161.95% | 100.00% | -61.95% | - | - | - | 0.62 | 38.25% | - | - | -61.95% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.20% | 100.00% | -7.20% | - | - | - | 0.93 | 6.71% | - | - | -7.20% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 56.78% | 100.00% | 43.22% | - | - | - | 1.76 | -76.12% | - | - | 43.22% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.12% | 100.00% | -0.12% | - | - | - | 1.00 | 0.12% | - | - | -0.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 82.94% | 100.00% | 17.06% | - | - | - | 1.21 | -20.57% | - | - | 17.06% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.78% | 100.00% | 26.22% | - | - | - | 1.36 | -35.53% | - | - | 26.22% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.78% | 100.00% | 26.22% | - | - | - | 1.36 | -35.53% | - | - | 26.22% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 150.65% | 100.00% | -50.65% | - | - | - | 0.66 | 33.62% | - | - | -50.65% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 201.08% | 100.00% | -101.08% | - | - | - | 0.50 | 50.27% | - | - | -101.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 201.08% | 100.00% | -101.08% | - | - | - | 0.50 | 50.27% | - | - | -101.08% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 68.78% | 100.00% | 31.22% | - | - | - | 1.45 | -45.38% | - | - | 31.22% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 281.60% | 100.00% | -181.60% | - | - | - | 0.36 | 64.49% | - | - | -181.60% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 112.24% | 100.00% | -12.24% | - | - | - | 0.89 | 10.90% | - | - | -12.24% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 6163.04% | 100.00% | -6063.04% | - | - | - | 0.02 | 98.38% | - | - | -6063.04% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.19% | 100.00% | 32.81% | - | - | - | 1.49 | -48.84% | - | - | 32.81% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 46.97% | 100.00% | 53.03% | - | - | - | 2.13 | -112.90% | - | - | 53.03% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.92% | 100.00% | 91.08% | - | - | - | 11.21 | -1020.71% | - | - | 91.08% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1523.76% | 100.00% | -1423.76% | - | - | - | 0.07 | 93.44% | - | - | -1423.76% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1417.87% | 100.00% | -1317.87% | - | - | - | 0.07 | 92.95% | - | - | -1317.87% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.63% | 100.00% | -446.63% | - | - | - | 0.18 | 81.71% | - | - | -446.63% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 34.91% | 100.00% | 65.09% | - | - | - | 2.86 | -186.42% | - | - | 65.09% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 75.84% | 100.00% | 24.16% | - | - | - | 1.32 | -31.86% | - | - | 24.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 106.23% | 100.00% | -6.23% | - | - | - | 0.94 | 5.86% | - | - | -6.23% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6157.64% | 100.00% | -6057.64% | - | - | - | 0.02 | 98.38% | - | - | -6057.64% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 306.28% | 100.00% | -206.28% | - | - | - | 0.33 | 67.35% | - | - | -206.28% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 124.37% | 100.00% | -24.37% | - | - | - | 0.80 | 19.59% | - | - | -24.37% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.15% | 100.00% | 10.85% | - | - | - | 1.12 | -12.17% | - | - | 10.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 69.51% | 100.00% | 30.49% | - | - | - | 1.44 | -43.87% | - | - | 30.49% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.23% | 100.00% | -136.23% | - | - | - | 0.42 | 57.67% | - | - | -136.23% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 353.84% | 100.00% | -253.84% | - | - | - | 0.28 | 71.74% | - | - | -253.84% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.78% | 100.00% | -83.78% | - | - | - | 0.54 | 45.59% | - | - | -83.78% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 839.13% | 100.00% | -739.13% | - | - | - | 0.12 | 88.08% | - | - | -739.13% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 102.41% | 100.00% | -2.41% | - | - | - | 0.98 | 2.36% | - | - | -2.41% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 119.37% | 98.98% | -20.39% | - | - | - | 0.83 | 17.08% | - | - | -20.60% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 201.47% | 100.00% | -101.47% | - | - | - | 0.50 | 50.36% | - | - | -101.47% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 200.54% | 100.00% | -100.54% | - | - | - | 0.50 | 50.13% | - | - | -100.54% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 106.00% | 100.00% | -6.00% | - | - | - | 0.94 | 5.66% | - | - | -6.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 106.00% | 100.00% | -6.00% | - | - | - | 0.94 | 5.66% | - | - | -6.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 174.38% | 100.00% | -74.38% | - | - | - | 0.57 | 42.65% | - | - | -74.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 196.47% | 100.00% | -96.47% | - | - | - | 0.51 | 49.10% | - | - | -96.47% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 176.20% | 100.00% | -76.20% | - | - | - | 0.57 | 43.25% | - | - | -76.20% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 176.20% | 100.00% | -76.20% | - | - | - | 0.57 | 43.25% | - | - | -76.20% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 162.64% | 100.00% | -62.64% | - | - | - | 0.61 | 38.51% | - | - | -62.64% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 162.64% | 100.00% | -62.64% | - | - | - | 0.61 | 38.51% | - | - | -62.64% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 124.98% | 100.00% | -24.98% | - | - | - | 0.80 | 19.99% | - | - | -24.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 100.00% | 50.25% | - | - | - | 2.01 | -100.99% | - | - | 50.25% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 113.06% | 100.00% | -13.06% | - | - | - | 0.88 | 11.55% | - | - | -13.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 113.06% | 100.00% | -13.06% | - | - | - | 0.88 | 11.55% | - | - | -13.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 113.06% | 100.00% | -13.06% | - | - | - | 0.88 | 11.55% | - | - | -13.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 111.60% | 100.00% | -11.60% | - | - | - | 0.90 | 10.39% | - | - | -11.60% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 23.17% | 100.00% | 76.83% | - | - | - | 4.32 | -331.57% | - | - | 76.83% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 66.77% | 100.00% | 33.23% | - | - | - | 1.50 | -49.78% | - | - | 33.23% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 62.66% | 100.00% | 37.34% | - | - | - | 1.60 | -59.59% | - | - | 37.34% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 183.57% | 0.00% | -183.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 183.57% | 0.00% | -183.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 183.57% | 0.00% | -183.57% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 57.91% | 93.64% | 35.73% | - | - | - | 1.62 | -61.71% | - | - | 38.16% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.66% | 88.00% | -12.66% | - | - | - | 0.87 | 12.57% | - | - | -14.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.68% | 88.00% | -15.68% | - | - | - | 0.85 | 15.12% | - | - | -17.81% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 9.75% | 100.00% | 90.25% | - | - | - | 10.26 | -925.59% | - | - | 90.25% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 9.85% | 100.00% | 90.15% | - | - | - | 10.16 | -915.68% | - | - | 90.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 7
|
- | - | - | - | - | - | 1.30% | 1.25% | 105.31% | 98.87% | -6.44% | - | - | - | 0.94 | 6.11% | - | - | -6.51% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 136.88% | 100.00% | -36.88% | - | - | - | 0.73 | 26.94% | - | - | -36.88% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 368.98% | 100.00% | -268.98% | - | - | - | 0.27 | 72.90% | - | - | -268.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 355.18% | 100.00% | -255.18% | - | - | - | 0.28 | 71.85% | - | - | -255.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 355.18% | 100.00% | -255.18% | - | - | - | 0.28 | 71.85% | - | - | -255.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 276.59% | 100.00% | -176.59% | - | - | - | 0.36 | 63.84% | - | - | -176.59% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 275.34% | 100.00% | -175.34% | - | - | - | 0.36 | 63.68% | - | - | -175.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 180.81% | 100.00% | -80.81% | - | - | - | 0.55 | 44.69% | - | - | -80.81% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 180.81% | 100.00% | -80.81% | - | - | - | 0.55 | 44.69% | - | - | -80.81% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 201.03% | 100.00% | -101.03% | - | - | - | 0.50 | 50.26% | - | - | -101.03% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 100.00% | -59.52% | - | - | - | 0.63 | 37.31% | - | - | -59.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 100.00% | -59.52% | - | - | - | 0.63 | 37.31% | - | - | -59.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 123.52% | 100.00% | -23.52% | - | - | - | 0.81 | 19.04% | - | - | -23.52% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA SIN RODILLO DE FIBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 149.05% | 100.00% | -49.05% | - | - | - | 0.67 | 32.91% | - | - | -49.05% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 146.10% | 100.00% | -46.10% | - | - | - | 0.68 | 31.55% | - | - | -46.10% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 127.69% | 100.00% | -27.69% | - | - | - | 0.78 | 21.68% | - | - | -27.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 199.29% | 100.00% | -99.29% | - | - | - | 0.50 | 49.82% | - | - | -99.29% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 176.20% | 100.00% | -76.20% | - | - | - | 0.57 | 43.25% | - | - | -76.20% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 176.20% | 100.00% | -76.20% | - | - | - | 0.57 | 43.25% | - | - | -76.20% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 89.65% | 100.00% | 10.35% | - | - | - | 1.12 | -11.55% | - | - | 10.35% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 89.65% | 100.00% | 10.35% | - | - | - | 1.12 | -11.55% | - | - | 10.35% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1950.66 | -194966.00% | - | - | 99.95% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 105.57% | 100.00% | -5.57% | - | - | - | 0.95 | 5.28% | - | - | -5.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 82.01% | 100.00% | 17.99% | - | - | - | 1.22 | -21.94% | - | - | 17.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISTOLA PARA CALAFATEO SENCILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 48.56% | 100.00% | 51.44% | - | - | - | 2.06 | -105.91% | - | - | 51.44% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 30.30% | 100.00% | 69.70% | - | - | - | 3.30 | -230.08% | - | - | 69.70% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.29% | 100.00% | 12.71% | - | - | - | 1.15 | -14.56% | - | - | 12.71% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 83.19% | 100.00% | 16.81% | - | - | - | 1.20 | -20.21% | - | - | 16.81% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.95% | 100.00% | -154.95% | - | - | - | 0.39 | 60.78% | - | - | -154.95% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 406.92% | 100.00% | -306.92% | - | - | - | 0.25 | 75.43% | - | - | -306.92% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 101.38% | 100.00% | -1.38% | - | - | - | 0.99 | 1.36% | - | - | -1.38% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 116.87% | 100.00% | -16.87% | - | - | - | 0.86 | 14.43% | - | - | -16.87% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 130.89% | 100.00% | -30.89% | - | - | - | 0.76 | 23.60% | - | - | -30.89% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 148.83% | 100.00% | -48.83% | - | - | - | 0.67 | 32.81% | - | - | -48.83% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 99.17% | 100.00% | 0.83% | - | - | - | 1.01 | -0.84% | - | - | 0.83% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.06% | 100.00% | -20.06% | - | - | - | 0.83 | 16.71% | - | - | -20.06% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.53% | 100.00% | 73.47% | - | - | - | 3.77 | -276.87% | - | - | 73.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.33% | 100.00% | -5.33% | - | - | - | 0.95 | 5.06% | - | - | -5.33% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.33% | 100.00% | -5.33% | - | - | - | 0.95 | 5.06% | - | - | -5.33% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 67.29% | 100.00% | 32.71% | - | - | - | 1.49 | -48.60% | - | - | 32.71% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 111.40% | 100.00% | -11.40% | - | - | - | 0.90 | 10.23% | - | - | -11.40% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 161.69% | 100.00% | -61.69% | - | - | - | 0.62 | 38.15% | - | - | -61.69% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 146080.90% | 100.00% | -145980.90% | - | - | - | 0.00 | 99.93% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 152173.91% | 100.00% | -152073.91% | - | - | - | 0.00 | 99.93% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 956.64% | 100.00% | -856.64% | - | - | - | 0.10 | 89.55% | - | - | -856.64% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 59865.06% | 100.00% | -59765.06% | - | - | - | 0.00 | 99.83% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 195.31% | 100.00% | -95.31% | - | - | - | 0.51 | 48.80% | - | - | -95.31% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.74% | 100.00% | -7.74% | - | - | - | 0.93 | 7.19% | - | - | -7.74% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 63.88% | 100.00% | 36.12% | - | - | - | 1.57 | -56.56% | - | - | 36.12% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.17% | 100.00% | -0.17% | - | - | - | 1.00 | 0.17% | - | - | -0.17% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.44% | - | - | 16.97% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 64.48% | 100.00% | 35.52% | - | - | - | 1.55 | -55.09% | - | - | 35.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 64.48% | 100.00% | 35.52% | - | - | - | 1.55 | -55.09% | - | - | 35.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 106.13% | 100.00% | -6.13% | - | - | - | 0.94 | 5.77% | - | - | -6.13% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 108.59% | 100.00% | -8.59% | - | - | - | 0.92 | 7.91% | - | - | -8.59% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4525.83% | 100.00% | -4425.83% | - | - | - | 0.02 | 97.79% | - | - | -4425.83% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 346.28% | 100.00% | -246.28% | - | - | - | 0.29 | 71.12% | - | - | -246.28% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 241.98% | 100.00% | -141.98% | - | - | - | 0.41 | 58.67% | - | - | -141.98% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3655.84% | 100.00% | -3555.84% | - | - | - | 0.03 | 97.26% | - | - | -3555.84% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 192.02% | 100.00% | -92.02% | - | - | - | 0.52 | 47.92% | - | - | -92.02% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 53.55% | 100.00% | 46.45% | - | - | - | 1.87 | -86.74% | - | - | 46.45% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 35.68% | 100.00% | 64.32% | - | - | - | 2.80 | -180.24% | - | - | 64.32% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1980.90% | 100.00% | -1880.90% | - | - | - | 0.05 | 94.95% | - | - | -1880.90% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 512.68% | 100.00% | -412.68% | - | - | - | 0.20 | 80.49% | - | - | -412.68% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.63% | 100.00% | -446.63% | - | - | - | 0.18 | 81.71% | - | - | -446.63% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.38% | 100.00% | 62.62% | - | - | - | 2.68 | -167.52% | - | - | 62.62% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 105.19% | 100.00% | -5.19% | - | - | - | 0.95 | 4.93% | - | - | -5.19% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 105.19% | 100.00% | -5.19% | - | - | - | 0.95 | 4.93% | - | - | -5.19% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 81.79% | 100.00% | 18.21% | - | - | - | 1.22 | -22.26% | - | - | 18.21% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 106.26% | 100.00% | -6.26% | - | - | - | 0.94 | 5.89% | - | - | -6.26% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6157.64% | 100.00% | -6057.64% | - | - | - | 0.02 | 98.38% | - | - | -6057.64% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 306.28% | 100.00% | -206.28% | - | - | - | 0.33 | 67.35% | - | - | -206.28% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 126.09% | 100.00% | -26.09% | - | - | - | 0.79 | 20.69% | - | - | -26.09% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.15% | 100.00% | 10.85% | - | - | - | 1.12 | -12.17% | - | - | 10.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.37% | 100.00% | 27.63% | - | - | - | 1.38 | -38.18% | - | - | 27.63% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.29% | 100.00% | -136.29% | - | - | - | 0.42 | 57.68% | - | - | -136.29% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 354.24% | 100.00% | -254.24% | - | - | - | 0.28 | 71.77% | - | - | -254.24% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.84% | 100.00% | -83.84% | - | - | - | 0.54 | 45.60% | - | - | -83.84% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 903.31% | 100.00% | -803.31% | - | - | - | 0.11 | 88.93% | - | - | -803.31% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 101.47% | 100.00% | -1.47% | - | - | - | 0.99 | 1.45% | - | - | -1.47% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.32% | 100.00% | 43.68% | - | - | - | 1.78 | -77.55% | - | - | 43.68% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 56.32% | 100.00% | 43.68% | - | - | - | 1.78 | -77.55% | - | - | 43.68% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.88% | 100.00% | 54.12% | - | - | - | 2.18 | -117.95% | - | - | 54.12% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.51% | 93.64% | 39.13% | - | - | - | 1.72 | -71.79% | - | - | 41.79% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.19% | 88.00% | -12.19% | - | - | - | 0.88 | 12.17% | - | - | -13.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 88.00% | -15.14% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.06% | 88.00% | 85.94% | - | - | - | 42.65 | -4165.01% | - | - | 97.66% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.04% | 100.00% | 96.96% | - | - | - | 32.89 | -3189.37% | - | - | 96.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 2.93% | 100.00% | 97.07% | - | - | - | 34.08 | -3308.34% | - | - | 97.07% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 15
|
- | - | - | - | - | - | 1.30% | 1.27% | 104.80% | 98.89% | -5.91% | - | - | - | 0.94 | 5.64% | - | - | -5.98% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.45% | 133.36% | 100.00% | -33.36% | - | - | - | 0.75 | 25.02% | - | - | -33.36% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 486.35% | 100.00% | -386.35% | - | - | - | 0.21 | 79.44% | - | - | -386.35% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 454.50% | 100.00% | -354.50% | - | - | - | 0.22 | 78.00% | - | - | -354.50% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 454.50% | 100.00% | -354.50% | - | - | - | 0.22 | 78.00% | - | - | -354.50% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MICROFIBRA 20U SURTIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 274.34% | 100.00% | -174.34% | - | - | - | 0.36 | 63.55% | - | - | -174.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 273.16% | 100.00% | -173.16% | - | - | - | 0.37 | 63.39% | - | - | -173.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 178.63% | 100.00% | -78.63% | - | - | - | 0.56 | 44.02% | - | - | -78.63% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 178.63% | 100.00% | -78.63% | - | - | - | 0.56 | 44.02% | - | - | -78.63% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 245.35% | 100.00% | -145.35% | - | - | - | 0.41 | 59.24% | - | - | -145.35% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 146.27% | 100.00% | -46.27% | - | - | - | 0.68 | 31.64% | - | - | -46.27% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 146.27% | 100.00% | -46.27% | - | - | - | 0.68 | 31.64% | - | - | -46.27% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 110.28% | 100.00% | -10.28% | - | - | - | 0.91 | 9.32% | - | - | -10.28% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA LATEX BLANCO TRADICIONAL INTERIOR E EXTERIOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLOR BLANCO LATEX PLUS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 219.56% | 100.00% | -119.56% | - | - | - | 0.46 | 54.45% | - | - | -119.56% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 207.28% | 100.00% | -107.28% | - | - | - | 0.48 | 51.76% | - | - | -107.28% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 240 P/AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 400 P/AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR ACRILICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO 4'X8'X 1/2" INT GYPCEN
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 122.45% | 100.00% | -22.45% | - | - | - | 0.82 | 18.33% | - | - | -22.45% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.33% | 100.00% | -2.33% | - | - | - | 0.98 | 2.27% | - | - | -2.33% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.33% | 100.00% | -2.33% | - | - | - | 0.98 | 2.27% | - | - | -2.33% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.33% | 100.00% | -2.33% | - | - | - | 0.98 | 2.27% | - | - | -2.33% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CARPINTERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASADOR CORREDIZO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.09% | 100.00% | 18.91% | - | - | - | 1.23 | -23.31% | - | - | 18.91% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.04% | 65.31% | 100.00% | 34.69% | - | - | - | 1.53 | -53.12% | - | - | 34.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 89.94% | 100.00% | 10.06% | - | - | - | 1.11 | -11.19% | - | - | 10.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 89.94% | 100.00% | 10.06% | - | - | - | 1.11 | -11.19% | - | - | 10.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.03% | 89.94% | 100.00% | 10.06% | - | - | - | 1.11 | -11.19% | - | - | 10.06% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 10.52% | 100.00% | 89.48% | - | - | - | 9.50 | -850.12% | - | - | 89.48% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 10.52% | 100.00% | 89.48% | - | - | - | 9.50 | -850.12% | - | - | 89.48% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.01% | 17.14% | 100.00% | 82.86% | - | - | - | 5.83 | -483.50% | - | - | 82.86% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.01% | 3.91% | 100.00% | 96.09% | - | - | - | 25.56 | -2456.25% | - | - | 96.09% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 51.38% | 100.00% | 48.62% | - | - | - | 1.95 | -94.64% | - | - | 48.62% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 116.32% | 100.00% | -16.32% | - | - | - | 0.86 | 14.03% | - | - | -16.32% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 77.65% | 100.00% | 22.35% | - | - | - | 1.29 | -28.79% | - | - | 22.35% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 77.65% | 100.00% | 22.35% | - | - | - | 1.29 | -28.79% | - | - | 22.35% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 16.88% | 100.00% | 83.12% | - | - | - | 5.93 | -492.58% | - | - | 83.12% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 16.88% | 100.00% | 83.12% | - | - | - | 5.93 | -492.58% | - | - | 83.12% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.37% | 100.00% | -3.37% | - | - | - | 0.97 | 3.26% | - | - | -3.37% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1950.66 | -194966.00% | - | - | 99.95% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.65% | 100.00% | 54.35% | - | - | - | 2.19 | -119.05% | - | - | 54.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 136.03% | 100.00% | -36.03% | - | - | - | 0.74 | 26.49% | - | - | -36.03% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 70.18% | 100.00% | 29.82% | - | - | - | 1.42 | -42.50% | - | - | 29.82% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 101.45% | 100.00% | -1.45% | - | - | - | 0.99 | 1.43% | - | - | -1.45% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 117.64% | 100.00% | -17.64% | - | - | - | 0.85 | 14.99% | - | - | -17.64% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 143.74% | 100.00% | -43.74% | - | - | - | 0.70 | 30.43% | - | - | -43.74% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 331071.11% | 100.00% | -330971.11% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7507.51% | 100.00% | -7407.51% | - | - | - | 0.01 | 98.67% | - | - | -7407.51% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 325.04% | 100.00% | -225.04% | - | - | - | 0.31 | 69.23% | - | - | -225.04% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEDAZO METALICO 1/16"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 142.08% | 100.00% | -42.08% | - | - | - | 0.70 | 29.62% | - | - | -42.08% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 130.99% | 100.00% | -30.99% | - | - | - | 0.76 | 23.66% | - | - | -30.99% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.89% | 100.00% | 45.11% | - | - | - | 1.82 | -82.17% | - | - | 45.11% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.51% | 100.00% | -154.51% | - | - | - | 0.39 | 60.71% | - | - | -154.51% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 218.91% | 100.00% | -118.91% | - | - | - | 0.46 | 54.32% | - | - | -118.91% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 327.47% | 100.00% | -227.47% | - | - | - | 0.31 | 69.46% | - | - | -227.47% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 134.53% | 100.00% | -34.53% | - | - | - | 0.74 | 25.66% | - | - | -34.53% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.79% | 100.00% | 8.21% | - | - | - | 1.09 | -8.94% | - | - | 8.21% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 91.79% | 100.00% | 8.21% | - | - | - | 1.09 | -8.94% | - | - | 8.21% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 109.67% | 100.00% | -9.67% | - | - | - | 0.91 | 8.82% | - | - | -9.67% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 171.73% | 100.00% | -71.73% | - | - | - | 0.58 | 41.77% | - | - | -71.73% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 787303.64% | 100.00% | -787203.64% | - | - | - | 0.00 | 99.99% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13364.35% | 100.00% | -13264.35% | - | - | - | 0.01 | 99.25% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 11107.72% | 100.00% | -11007.72% | - | - | - | 0.01 | 99.10% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 484.17% | 100.00% | -384.17% | - | - | - | 0.21 | 79.35% | - | - | -384.17% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
VARILLA ROSCADA DE 1/4 X 3.MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 159.86% | 100.00% | -59.86% | - | - | - | 0.63 | 37.45% | - | - | -59.86% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 100.97% | 100.00% | -0.97% | - | - | - | 0.99 | 0.96% | - | - | -0.97% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.27% | 100.00% | 14.73% | - | - | - | 1.17 | -17.28% | - | - | 14.73% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 140.59% | 100.00% | -40.59% | - | - | - | 0.71 | 28.87% | - | - | -40.59% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 93.15% | 100.00% | 6.85% | - | - | - | 1.07 | -7.35% | - | - | 6.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.53% | 100.00% | 27.47% | - | - | - | 1.38 | -37.87% | - | - | 27.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 234.86% | 100.00% | -134.86% | - | - | - | 0.43 | 57.42% | - | - | -134.86% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 707.97% | 100.00% | -607.97% | - | - | - | 0.14 | 85.88% | - | - | -607.97% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 214.98% | 100.00% | -114.98% | - | - | - | 0.47 | 53.48% | - | - | -114.98% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1026.64% | 100.00% | -926.64% | - | - | - | 0.10 | 90.26% | - | - | -926.64% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.81% | 100.00% | 59.19% | - | - | - | 2.45 | -145.02% | - | - | 59.19% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.81% | 100.00% | 59.19% | - | - | - | 2.45 | -145.02% | - | - | 59.19% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 90.14% | 100.00% | 9.86% | - | - | - | 1.11 | -10.94% | - | - | 9.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 116.30% | 100.00% | -16.30% | - | - | - | 0.86 | 14.01% | - | - | -16.30% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 116.30% | 100.00% | -16.30% | - | - | - | 0.86 | 14.01% | - | - | -16.30% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 47.77% | 100.00% | 52.23% | - | - | - | 2.09 | -109.32% | - | - | 52.23% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2365.39% | 100.00% | -2265.39% | - | - | - | 0.04 | 95.77% | - | - | -2265.39% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 214.09% | 100.00% | -114.09% | - | - | - | 0.47 | 53.29% | - | - | -114.09% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.79% | 100.00% | -69.79% | - | - | - | 0.59 | 41.10% | - | - | -69.79% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2201.29% | 100.00% | -2101.29% | - | - | - | 0.05 | 95.46% | - | - | -2101.29% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 153.15% | 100.00% | -53.15% | - | - | - | 0.65 | 34.70% | - | - | -53.15% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 153.15% | 100.00% | -53.15% | - | - | - | 0.65 | 34.70% | - | - | -53.15% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.64% | 100.00% | 45.36% | - | - | - | 1.83 | -83.01% | - | - | 45.36% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 5.30% | 100.00% | 94.70% | - | - | - | 18.86 | -1785.94% | - | - | 94.70% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 19.24% | 100.00% | 80.76% | - | - | - | 5.20 | -419.65% | - | - | 80.76% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.53% | 100.00% | -45.53% | - | - | - | 0.69 | 31.29% | - | - | -45.53% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 62.96% | 100.00% | 37.04% | - | - | - | 1.59 | -58.83% | - | - | 37.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 82.43% | 100.00% | 17.57% | - | - | - | 1.21 | -21.31% | - | - | 17.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 82.43% | 100.00% | 17.57% | - | - | - | 1.21 | -21.31% | - | - | 17.57% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 52.09% | 100.00% | 47.91% | - | - | - | 1.92 | -91.97% | - | - | 47.91% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 116.06% | 100.00% | -16.06% | - | - | - | 0.86 | 13.84% | - | - | -16.06% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 48.63% | 100.00% | 51.37% | - | - | - | 2.06 | -105.63% | - | - | 51.37% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 86.32% | 100.00% | 13.68% | - | - | - | 1.16 | -15.85% | - | - | 13.68% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 125.80% | 100.00% | -25.80% | - | - | - | 0.79 | 20.51% | - | - | -25.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.79% | 93.64% | 37.85% | - | - | - | 1.68 | -67.84% | - | - | 40.42% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.19% | 88.00% | -12.19% | - | - | - | 0.88 | 12.17% | - | - | -13.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 88.00% | -15.14% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.06% | 88.00% | 85.94% | - | - | - | 42.63 | -4163.09% | - | - | 97.65% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 5.77% | 100.00% | 94.23% | - | - | - | 17.32 | -1632.01% | - | - | 94.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 5.75% | 100.00% | 94.25% | - | - | - | 17.39 | -1639.27% | - | - | 94.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 14
|
- | - | - | - | - | - | 1.30% | 1.25% | 103.59% | 98.87% | -4.72% | - | - | - | 0.95 | 4.56% | - | - | -4.78% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 130.04% | 100.00% | -30.04% | - | - | - | 0.77 | 23.10% | - | - | -30.04% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 602.54% | 100.00% | -502.54% | - | - | - | 0.17 | 83.40% | - | - | -502.54% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 536.96% | 100.00% | -436.96% | - | - | - | 0.19 | 81.38% | - | - | -436.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 536.96% | 100.00% | -436.96% | - | - | - | 0.19 | 81.38% | - | - | -436.96% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 252.04% | 100.00% | -152.04% | - | - | - | 0.40 | 60.32% | - | - | -152.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 100.00% | -59.52% | - | - | - | 0.63 | 37.31% | - | - | -59.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 100.00% | -59.52% | - | - | - | 0.63 | 37.31% | - | - | -59.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 123.52% | 100.00% | -23.52% | - | - | - | 0.81 | 19.04% | - | - | -23.52% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA LATEX BLANCO TRADICIONAL INTERIOR E EXTERIOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLOR BLANCO LATEX PLUS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 205.63% | 100.00% | -105.63% | - | - | - | 0.49 | 51.37% | - | - | -105.63% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 202.96% | 100.00% | -102.96% | - | - | - | 0.49 | 50.73% | - | - | -102.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 129.91% | 100.00% | -29.91% | - | - | - | 0.77 | 23.02% | - | - | -29.91% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 128.07% | 100.00% | -28.07% | - | - | - | 0.78 | 21.92% | - | - | -28.07% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 124.15% | 100.00% | -24.15% | - | - | - | 0.81 | 19.45% | - | - | -24.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 115.87% | 100.00% | -15.87% | - | - | - | 0.86 | 13.70% | - | - | -15.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 88.63% | 100.00% | 11.37% | - | - | - | 1.13 | -12.83% | - | - | 11.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 117.87% | 100.00% | -17.87% | - | - | - | 0.85 | 15.16% | - | - | -17.87% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.44% | 100.00% | 12.56% | - | - | - | 1.14 | -14.36% | - | - | 12.56% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.44% | 100.00% | 12.56% | - | - | - | 1.14 | -14.36% | - | - | 12.56% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO CONTRAMARCO ENCHAPADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 74.94% | 100.00% | 25.06% | - | - | - | 1.33 | -33.43% | - | - | 25.06% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 80.35% | 100.00% | 19.65% | - | - | - | 1.24 | -24.45% | - | - | 19.65% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.65% | 100.00% | 54.35% | - | - | - | 2.19 | -119.05% | - | - | 54.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 100.00% | 0.11% | - | - | - | 1.00 | -0.11% | - | - | 0.11% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 100.00% | 19.28% | - | - | - | 1.24 | -23.89% | - | - | 19.28% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 100.00% | -48.15% | - | - | - | 0.67 | 32.50% | - | - | -48.15% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 100.00% | 57.12% | - | - | - | 2.33 | -133.18% | - | - | 57.12% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 101.26% | 100.00% | -1.26% | - | - | - | 0.99 | 1.25% | - | - | -1.26% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 126.44% | 100.00% | -26.44% | - | - | - | 0.79 | 20.91% | - | - | -26.44% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 163.43% | 100.00% | -63.43% | - | - | - | 0.61 | 38.81% | - | - | -63.43% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 397484.44% | 100.00% | -397384.44% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7005.79% | 100.00% | -6905.79% | - | - | - | 0.01 | 98.57% | - | - | -6905.79% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 335.34% | 100.00% | -235.34% | - | - | - | 0.30 | 70.18% | - | - | -235.34% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 319.78% | 100.00% | -219.78% | - | - | - | 0.31 | 68.73% | - | - | -219.78% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 159.86% | 100.00% | -59.86% | - | - | - | 0.63 | 37.44% | - | - | -59.86% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 138.35% | 100.00% | -38.35% | - | - | - | 0.72 | 27.72% | - | - | -38.35% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.14% | 100.00% | -20.14% | - | - | - | 0.83 | 16.76% | - | - | -20.14% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.13% | 100.00% | 41.87% | - | - | - | 1.72 | -72.03% | - | - | 41.87% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.51% | 100.00% | -154.51% | - | - | - | 0.39 | 60.71% | - | - | -154.51% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 218.91% | 100.00% | -118.91% | - | - | - | 0.46 | 54.32% | - | - | -118.91% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 327.47% | 100.00% | -227.47% | - | - | - | 0.31 | 69.46% | - | - | -227.47% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 88.06% | 100.00% | 11.94% | - | - | - | 1.14 | -13.56% | - | - | 11.94% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 88.06% | 100.00% | 11.94% | - | - | - | 1.14 | -13.56% | - | - | 11.94% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 69.02% | 100.00% | 30.98% | - | - | - | 1.45 | -44.89% | - | - | 30.98% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 122.84% | 100.00% | -22.84% | - | - | - | 0.81 | 18.59% | - | - | -22.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 145.45% | 100.00% | -45.45% | - | - | - | 0.69 | 31.25% | - | - | -45.45% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.43% | 100.00% | -102.43% | - | - | - | 0.49 | 50.60% | - | - | -102.43% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.43% | 100.00% | -102.43% | - | - | - | 0.49 | 50.60% | - | - | -102.43% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 118.12% | 100.00% | -18.12% | - | - | - | 0.85 | 15.34% | - | - | -18.12% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.93% | 100.00% | 39.07% | - | - | - | 1.64 | -64.13% | - | - | 39.07% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.59% | 100.00% | 12.41% | - | - | - | 1.14 | -14.17% | - | - | 12.41% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.26% | 100.00% | -27.26% | - | - | - | 0.79 | 21.42% | - | - | -27.26% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 109.54% | 100.00% | -9.54% | - | - | - | 0.91 | 8.71% | - | - | -9.54% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 109.54% | 100.00% | -9.54% | - | - | - | 0.91 | 8.71% | - | - | -9.54% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 324.26% | 100.00% | -224.26% | - | - | - | 0.31 | 69.16% | - | - | -224.26% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 91.23% | 100.00% | 8.77% | - | - | - | 1.10 | -9.61% | - | - | 8.77% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 119.46% | 100.00% | -19.46% | - | - | - | 0.84 | 16.29% | - | - | -19.46% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 119.46% | 100.00% | -19.46% | - | - | - | 0.84 | 16.29% | - | - | -19.46% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.47% | 100.00% | 54.53% | - | - | - | 2.20 | -119.95% | - | - | 54.53% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9826.77% | 100.00% | -9726.77% | - | - | - | 0.01 | 98.98% | - | - | -9726.77% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 6817.39% | 100.00% | -6717.39% | - | - | - | 0.01 | 98.53% | - | - | -6717.39% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 293.92% | 100.00% | -193.92% | - | - | - | 0.34 | 65.98% | - | - | -193.92% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 293.92% | 100.00% | -193.92% | - | - | - | 0.34 | 65.98% | - | - | -193.92% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.40% | 100.00% | -6.40% | - | - | - | 0.94 | 6.01% | - | - | -6.40% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 85.67% | 100.00% | 14.33% | - | - | - | 1.17 | -16.73% | - | - | 14.33% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1043.54% | 100.00% | -943.54% | - | - | - | 0.10 | 90.42% | - | - | -943.54% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 84.83% | 100.00% | 15.17% | - | - | - | 1.18 | -17.88% | - | - | 15.17% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 8.92% | 100.00% | 91.08% | - | - | - | 11.21 | -1020.79% | - | - | 91.08% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 35.70% | 100.00% | 64.30% | - | - | - | 2.80 | -180.08% | - | - | 64.30% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 80.75% | 100.00% | 19.25% | - | - | - | 1.24 | -23.84% | - | - | 19.25% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 113.12% | 100.00% | -13.12% | - | - | - | 0.88 | 11.60% | - | - | -13.12% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 203363.64% | 100.00% | -203263.64% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8201.97% | 100.00% | -8101.97% | - | - | - | 0.01 | 98.78% | - | - | -8101.97% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 367.79% | 100.00% | -267.79% | - | - | - | 0.27 | 72.81% | - | - | -267.79% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 130.56% | 100.00% | -30.56% | - | - | - | 0.77 | 23.41% | - | - | -30.56% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.84% | 100.00% | 11.16% | - | - | - | 1.13 | -12.56% | - | - | 11.16% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.27% | 100.00% | 28.73% | - | - | - | 1.40 | -40.32% | - | - | 28.73% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.23% | 100.00% | -136.23% | - | - | - | 0.42 | 57.67% | - | - | -136.23% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 398.55% | 100.00% | -298.55% | - | - | - | 0.25 | 74.91% | - | - | -298.55% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.62% | 100.00% | -83.62% | - | - | - | 0.54 | 45.54% | - | - | -83.62% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1065.62% | 100.00% | -965.62% | - | - | - | 0.09 | 90.62% | - | - | -965.62% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 97.82% | 100.00% | 2.18% | - | - | - | 1.02 | -2.23% | - | - | 2.18% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.87% | 100.00% | 43.13% | - | - | - | 1.76 | -75.83% | - | - | 43.13% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.88% | 100.00% | 54.12% | - | - | - | 2.18 | -117.95% | - | - | 54.12% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 58.46% | 93.64% | 35.18% | - | - | - | 1.60 | -60.18% | - | - | 37.57% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.92% | 88.00% | -12.92% | - | - | - | 0.87 | 12.80% | - | - | -14.68% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.94% | 88.00% | -15.94% | - | - | - | 0.85 | 15.34% | - | - | -18.12% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 10.63% | 100.00% | 89.37% | - | - | - | 9.41 | -840.61% | - | - | 89.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 10.75% | 100.00% | 89.25% | - | - | - | 9.30 | -829.97% | - | - | 89.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 13
|
- | - | - | - | - | - | 1.30% | 1.25% | 102.82% | 98.87% | -3.95% | - | - | - | 0.96 | 3.84% | - | - | -4.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 127.47% | 100.00% | -27.47% | - | - | - | 0.78 | 21.55% | - | - | -27.47% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 461.78% | 100.00% | -361.78% | - | - | - | 0.22 | 78.34% | - | - | -361.78% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 461.78% | 100.00% | -361.78% | - | - | - | 0.22 | 78.34% | - | - | -361.78% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 461.78% | 100.00% | -361.78% | - | - | - | 0.22 | 78.34% | - | - | -361.78% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 206.59% | 100.00% | -106.59% | - | - | - | 0.48 | 51.59% | - | - | -106.59% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 201.75% | 100.00% | -101.75% | - | - | - | 0.50 | 50.43% | - | - | -101.75% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 107.21% | 100.00% | -7.21% | - | - | - | 0.93 | 6.73% | - | - | -7.21% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 107.21% | 100.00% | -7.21% | - | - | - | 0.93 | 6.73% | - | - | -7.21% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 193.19% | 100.00% | -93.19% | - | - | - | 0.52 | 48.24% | - | - | -93.19% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 100.00% | 50.25% | - | - | - | 2.01 | -100.99% | - | - | 50.25% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA LATEX BLANCO TRADICIONAL INTERIOR E EXTERIOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLOR BLANCO LATEX PLUS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 148.90% | 100.00% | -48.90% | - | - | - | 0.67 | 32.84% | - | - | -48.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 189.89% | 100.00% | -89.89% | - | - | - | 0.53 | 47.34% | - | - | -89.89% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 156.79% | 100.00% | -56.79% | - | - | - | 0.64 | 36.22% | - | - | -56.79% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 156.79% | 100.00% | -56.79% | - | - | - | 0.64 | 36.22% | - | - | -56.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO CONTRAMARCO ENCHAPADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 127.12% | 100.00% | -27.12% | - | - | - | 0.79 | 21.34% | - | - | -27.12% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 127.12% | 100.00% | -27.12% | - | - | - | 0.79 | 21.34% | - | - | -27.12% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 159.52% | 100.00% | -59.52% | - | - | - | 0.63 | 37.31% | - | - | -59.52% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 64.59% | 100.00% | 35.41% | - | - | - | 1.55 | -54.81% | - | - | 35.41% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.65% | 100.00% | 54.35% | - | - | - | 2.19 | -119.05% | - | - | 54.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 100.00% | 0.11% | - | - | - | 1.00 | -0.11% | - | - | 0.11% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 100.00% | 19.28% | - | - | - | 1.24 | -23.89% | - | - | 19.28% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 100.00% | -48.15% | - | - | - | 0.67 | 32.50% | - | - | -48.15% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 100.00% | 57.12% | - | - | - | 2.33 | -133.18% | - | - | 57.12% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 103.21% | 100.00% | -3.21% | - | - | - | 0.97 | 3.11% | - | - | -3.21% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 144.52% | 100.00% | -44.52% | - | - | - | 0.69 | 30.80% | - | - | -44.52% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 192.67% | 100.00% | -92.67% | - | - | - | 0.52 | 48.10% | - | - | -92.67% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 148325.84% | 100.00% | -148225.84% | - | - | - | 0.00 | 99.93% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 243478.26% | 100.00% | -243378.26% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 956.64% | 100.00% | -856.64% | - | - | - | 0.10 | 89.55% | - | - | -856.64% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 59865.06% | 100.00% | -59765.06% | - | - | - | 0.00 | 99.83% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 253.99% | 100.00% | -153.99% | - | - | - | 0.39 | 60.63% | - | - | -153.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 236.45% | 100.00% | -136.45% | - | - | - | 0.42 | 57.71% | - | - | -136.45% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 117.66% | 100.00% | -17.66% | - | - | - | 0.85 | 15.01% | - | - | -17.66% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.16% | 100.00% | 45.84% | - | - | - | 1.85 | -84.64% | - | - | 45.84% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.59% | 100.00% | 12.41% | - | - | - | 1.14 | -14.17% | - | - | 12.41% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.26% | 100.00% | -27.26% | - | - | - | 0.79 | 21.42% | - | - | -27.26% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 103.64% | 100.00% | -3.64% | - | - | - | 0.96 | 3.51% | - | - | -3.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 103.64% | 100.00% | -3.64% | - | - | - | 0.96 | 3.51% | - | - | -3.64% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 123.91% | 100.00% | -23.91% | - | - | - | 0.81 | 19.30% | - | - | -23.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 148.41% | 100.00% | -48.41% | - | - | - | 0.67 | 32.62% | - | - | -48.41% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 335.34% | 100.00% | -235.34% | - | - | - | 0.30 | 70.18% | - | - | -235.34% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 160.27% | 100.00% | -60.27% | - | - | - | 0.62 | 37.61% | - | - | -60.27% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 132.02% | 100.00% | -32.02% | - | - | - | 0.76 | 24.25% | - | - | -32.02% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.14% | 100.00% | -20.14% | - | - | - | 0.83 | 16.76% | - | - | -20.14% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.89% | 100.00% | 45.11% | - | - | - | 1.82 | -82.17% | - | - | 45.11% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.51% | 100.00% | -154.51% | - | - | - | 0.39 | 60.71% | - | - | -154.51% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 200.34% | 100.00% | -100.34% | - | - | - | 0.50 | 50.09% | - | - | -100.34% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 327.47% | 100.00% | -227.47% | - | - | - | 0.31 | 69.46% | - | - | -227.47% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.24% | 100.00% | -0.24% | - | - | - | 1.00 | 0.24% | - | - | -0.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 100.24% | 100.00% | -0.24% | - | - | - | 1.00 | 0.24% | - | - | -0.24% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 72.47% | 100.00% | 27.53% | - | - | - | 1.38 | -37.99% | - | - | 27.53% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 116.89% | 100.00% | -16.89% | - | - | - | 0.86 | 14.45% | - | - | -16.89% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 158.17% | 100.00% | -58.17% | - | - | - | 0.63 | 36.78% | - | - | -58.17% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 158.17% | 100.00% | -58.17% | - | - | - | 0.63 | 36.78% | - | - | -58.17% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 49.81% | 100.00% | 50.19% | - | - | - | 2.01 | -100.78% | - | - | 50.19% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9426.09% | 100.00% | -9326.09% | - | - | - | 0.01 | 98.94% | - | - | -9326.09% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 6817.39% | 100.00% | -6717.39% | - | - | - | 0.01 | 98.53% | - | - | -6717.39% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 139.70% | 100.00% | -39.70% | - | - | - | 0.72 | 28.42% | - | - | -39.70% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 142.95% | 100.00% | -42.95% | - | - | - | 0.70 | 30.05% | - | - | -42.95% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 71.88 | -7088.00% | - | - | 98.61% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.53% | 100.00% | 29.47% | - | - | - | 1.42 | -41.78% | - | - | 29.47% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE ALUMINIO DE 1 3/4" X 3" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.79% | 100.00% | 41.21% | - | - | - | 1.70 | -70.11% | - | - | 41.21% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.79% | 100.00% | 41.21% | - | - | - | 1.70 | -70.11% | - | - | 41.21% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 20.93% | 100.00% | 79.07% | - | - | - | 4.78 | -377.84% | - | - | 79.07% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.28% | 100.00% | 85.72% | - | - | - | 7.00 | -600.17% | - | - | 85.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1949.42% | 100.00% | -1849.42% | - | - | - | 0.05 | 94.87% | - | - | -1849.42% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 62.09% | 100.00% | 37.91% | - | - | - | 1.61 | -61.05% | - | - | 37.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 78.13% | 100.00% | 21.87% | - | - | - | 1.28 | -27.99% | - | - | 21.87% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 639081.82% | 100.00% | -638981.82% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8201.97% | 100.00% | -8101.97% | - | - | - | 0.01 | 98.78% | - | - | -8101.97% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4788.06% | 100.00% | -4688.06% | - | - | - | 0.02 | 97.91% | - | - | -4688.06% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 232.38% | 100.00% | -132.38% | - | - | - | 0.43 | 56.97% | - | - | -132.38% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 155.97% | 100.00% | -55.97% | - | - | - | 0.64 | 35.89% | - | - | -55.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.84% | 100.00% | 11.16% | - | - | - | 1.13 | -12.56% | - | - | 11.16% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 76.26% | 100.00% | 23.74% | - | - | - | 1.31 | -31.12% | - | - | 23.74% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 577.11% | 100.00% | -477.11% | - | - | - | 0.17 | 82.67% | - | - | -477.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 487.17% | 100.00% | -387.17% | - | - | - | 0.21 | 79.47% | - | - | -387.17% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.62% | 100.00% | -83.62% | - | - | - | 0.54 | 45.54% | - | - | -83.62% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1051.57% | 100.00% | -951.57% | - | - | - | 0.10 | 90.49% | - | - | -951.57% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 7.22% | 100.00% | 92.78% | - | - | - | 13.84 | -1284.25% | - | - | 92.78% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.77% | 100.00% | 54.23% | - | - | - | 2.18 | -118.50% | - | - | 54.23% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.77% | 100.00% | 54.23% | - | - | - | 2.18 | -118.50% | - | - | 54.23% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.18% | 100.00% | 54.82% | - | - | - | 2.21 | -121.36% | - | - | 54.82% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 53.89% | 93.64% | 39.75% | - | - | - | 1.74 | -73.77% | - | - | 42.45% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.80% | 88.00% | -12.80% | - | - | - | 0.87 | 12.70% | - | - | -14.55% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.83% | 88.00% | -15.83% | - | - | - | 0.85 | 15.24% | - | - | -17.99% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.04% | 100.00% | 98.96% | - | - | - | 96.48 | -9547.76% | - | - | 98.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.87% | 100.00% | 99.13% | - | - | - | 114.90 | -11390.49% | - | - | 99.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 12
|
- | - | - | - | - | - | 1.30% | 1.25% | 100.94% | 98.87% | -2.07% | - | - | - | 0.98 | 2.05% | - | - | -2.09% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 122.92% | 100.00% | -22.92% | - | - | - | 0.81 | 18.65% | - | - | -22.92% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 508.24% | 100.00% | -408.24% | - | - | - | 0.20 | 80.32% | - | - | -408.24% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 467.84% | 100.00% | -367.84% | - | - | - | 0.21 | 78.62% | - | - | -367.84% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 467.84% | 100.00% | -367.84% | - | - | - | 0.21 | 78.62% | - | - | -367.84% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 208.51% | 100.00% | -108.51% | - | - | - | 0.48 | 52.04% | - | - | -108.51% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 202.96% | 100.00% | -102.96% | - | - | - | 0.49 | 50.73% | - | - | -102.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 176.57% | 100.00% | -76.57% | - | - | - | 0.57 | 43.37% | - | - | -76.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 100.00% | 50.25% | - | - | - | 2.01 | -100.99% | - | - | 50.25% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA LATEX BLANCO TRADICIONAL INTERIOR E EXTERIOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLOR BLANCO LATEX PLUS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 119.09% | 100.00% | -19.09% | - | - | - | 0.84 | 16.03% | - | - | -19.09% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 205.65% | 100.00% | -105.65% | - | - | - | 0.49 | 51.37% | - | - | -105.65% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 164.24% | 100.00% | -64.24% | - | - | - | 0.61 | 39.11% | - | - | -64.24% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 164.24% | 100.00% | -64.24% | - | - | - | 0.61 | 39.11% | - | - | -64.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO CONTRAMARCO ENCHAPADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 74.94% | 100.00% | 25.06% | - | - | - | 1.33 | -33.43% | - | - | 25.06% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.43% | 100.00% | -0.43% | - | - | - | 1.00 | 0.43% | - | - | -0.43% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 83.13% | 100.00% | 16.87% | - | - | - | 1.20 | -20.30% | - | - | 16.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.65% | 100.00% | 54.35% | - | - | - | 2.19 | -119.05% | - | - | 54.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 100.00% | 0.11% | - | - | - | 1.00 | -0.11% | - | - | 0.11% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 100.00% | 19.28% | - | - | - | 1.24 | -23.89% | - | - | 19.28% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 100.00% | -48.15% | - | - | - | 0.67 | 32.50% | - | - | -48.15% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 100.00% | 57.12% | - | - | - | 2.33 | -133.18% | - | - | 57.12% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 100.16% | 100.00% | -0.16% | - | - | - | 1.00 | 0.16% | - | - | -0.16% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 134.37% | 100.00% | -34.37% | - | - | - | 0.74 | 25.58% | - | - | -34.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 177.17% | 100.00% | -77.17% | - | - | - | 0.56 | 43.56% | - | - | -77.17% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 111483.15% | 100.00% | -111383.15% | - | - | - | 0.00 | 99.91% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182608.70% | 100.00% | -182508.70% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 958.54% | 100.00% | -858.54% | - | - | - | 0.10 | 89.57% | - | - | -858.54% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 59983.94% | 100.00% | -59883.94% | - | - | - | 0.00 | 99.83% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 219.98% | 100.00% | -119.98% | - | - | - | 0.45 | 54.54% | - | - | -119.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 117.66% | 100.00% | -17.66% | - | - | - | 0.85 | 15.01% | - | - | -17.66% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.16% | 100.00% | 45.84% | - | - | - | 1.85 | -84.64% | - | - | 45.84% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.59% | 100.00% | 12.41% | - | - | - | 1.14 | -14.17% | - | - | 12.41% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.26% | 100.00% | -27.26% | - | - | - | 0.79 | 21.42% | - | - | -27.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 98.66% | 100.00% | 1.34% | - | - | - | 1.01 | -1.36% | - | - | 1.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 98.66% | 100.00% | 1.34% | - | - | - | 1.01 | -1.36% | - | - | 1.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 123.20% | 100.00% | -23.20% | - | - | - | 0.81 | 18.83% | - | - | -23.20% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 149.16% | 100.00% | -49.16% | - | - | - | 0.67 | 32.96% | - | - | -49.16% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2437.44% | 100.00% | -2337.44% | - | - | - | 0.04 | 95.90% | - | - | -2337.44% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 160.27% | 100.00% | -60.27% | - | - | - | 0.62 | 37.61% | - | - | -60.27% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 132.02% | 100.00% | -32.02% | - | - | - | 0.76 | 24.25% | - | - | -32.02% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.14% | 100.00% | -20.14% | - | - | - | 0.83 | 16.76% | - | - | -20.14% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.89% | 100.00% | 45.11% | - | - | - | 1.82 | -82.17% | - | - | 45.11% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.51% | 100.00% | -154.51% | - | - | - | 0.39 | 60.71% | - | - | -154.51% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 200.34% | 100.00% | -100.34% | - | - | - | 0.50 | 50.09% | - | - | -100.34% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 327.47% | 100.00% | -227.47% | - | - | - | 0.31 | 69.46% | - | - | -227.47% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 97.76% | 100.00% | 2.24% | - | - | - | 1.02 | -2.29% | - | - | 2.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 97.76% | 100.00% | 2.24% | - | - | - | 1.02 | -2.29% | - | - | 2.24% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 72.47% | 100.00% | 27.53% | - | - | - | 1.38 | -37.99% | - | - | 27.53% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 83.83% | 100.00% | 16.17% | - | - | - | 1.19 | -19.29% | - | - | 16.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 118.91% | 100.00% | -18.91% | - | - | - | 0.84 | 15.90% | - | - | -18.91% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123667.27% | 100.00% | -123567.27% | - | - | - | 0.00 | 99.92% | - | - | 0.00% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14359.61% | 100.00% | -14259.61% | - | - | - | 0.01 | 99.30% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 687.84% | 100.00% | -587.84% | - | - | - | 0.15 | 85.46% | - | - | -587.84% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.98% | 100.00% | -133.98% | - | - | - | 0.43 | 57.26% | - | - | -133.98% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 137.07% | 100.00% | -37.07% | - | - | - | 0.73 | 27.04% | - | - | -37.07% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.84% | 100.00% | 11.16% | - | - | - | 1.13 | -12.56% | - | - | 11.16% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 74.40% | 100.00% | 25.60% | - | - | - | 1.34 | -34.41% | - | - | 25.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.14% | 100.00% | -192.14% | - | - | - | 0.34 | 65.77% | - | - | -192.14% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 398.55% | 100.00% | -298.55% | - | - | - | 0.25 | 74.91% | - | - | -298.55% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 201.20% | 100.00% | -101.20% | - | - | - | 0.50 | 50.30% | - | - | -101.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1184.61% | 100.00% | -1084.61% | - | - | - | 0.08 | 91.56% | - | - | -1084.61% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 101.47% | 100.00% | -1.47% | - | - | - | 0.99 | 1.45% | - | - | -1.47% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.88% | 100.00% | 54.12% | - | - | - | 2.18 | -117.95% | - | - | 54.12% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 81.07% | 100.00% | 18.93% | - | - | - | 1.23 | -23.36% | - | - | 18.93% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 93.68% | 100.00% | 6.32% | - | - | - | 1.07 | -6.74% | - | - | 6.32% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 15048.42% | 100.00% | -14948.42% | - | - | - | 0.01 | 99.34% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 6817.39% | 100.00% | -6717.39% | - | - | - | 0.01 | 98.53% | - | - | -6717.39% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 708.49% | 100.00% | -608.49% | - | - | - | 0.14 | 85.89% | - | - | -608.49% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 708.49% | 100.00% | -608.49% | - | - | - | 0.14 | 85.89% | - | - | -608.49% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 257.39% | 100.00% | -157.39% | - | - | - | 0.39 | 61.15% | - | - | -157.39% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 188.19% | 100.00% | -88.19% | - | - | - | 0.53 | 46.86% | - | - | -88.19% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2616.83% | 100.00% | -2516.83% | - | - | - | 0.04 | 96.18% | - | - | -2516.83% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 52.22% | 100.00% | 47.78% | - | - | - | 1.91 | -91.49% | - | - | 47.78% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4'X8'X1/4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 36.77% | 100.00% | 63.23% | - | - | - | 2.72 | -171.96% | - | - | 63.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.28% | 100.00% | 85.72% | - | - | - | 7.00 | -600.37% | - | - | 85.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 512.68% | 100.00% | -412.68% | - | - | - | 0.20 | 80.49% | - | - | -412.68% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.81% | 100.00% | 94.19% | - | - | - | 17.20 | -1620.30% | - | - | 94.19% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 73.84% | 100.00% | 26.16% | - | - | - | 1.35 | -35.42% | - | - | 26.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 73.84% | 100.00% | 26.16% | - | - | - | 1.35 | -35.42% | - | - | 26.16% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 60.30% | 93.64% | 33.34% | - | - | - | 1.55 | -55.28% | - | - | 35.60% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 102.14% | 88.00% | -14.14% | - | - | - | 0.86 | 13.85% | - | - | -16.07% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.21% | 88.00% | -17.21% | - | - | - | 0.84 | 16.36% | - | - | -19.56% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 13.17% | 100.00% | 86.83% | - | - | - | 7.59 | -659.22% | - | - | 86.83% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.46% | 100.00% | 86.54% | - | - | - | 7.43 | -642.75% | - | - | 86.54% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 13.16% | 100.00% | 86.84% | - | - | - | 7.60 | -659.73% | - | - | 86.84% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
URBANIZACION
|
- | - | - | - | - | - | 18.50% | 20.95% | 94.36% | 92.95% | -1.41% | - | - | - | 0.99 | 1.49% | - | - | -1.51% | - | 0.00% |
|
URBANIZACION
|
- | - | - | - | - | - | 18.50% | 20.95% | 94.36% | 92.95% | -1.41% | - | - | - | 0.99 | 1.49% | - | - | -1.51% | - | 0.00% |
|
OBRA GRIS
|
- | - | - | - | - | - | 0.29% | 0.28% | 266.76% | 100.00% | -166.76% | - | - | - | 0.37 | 62.51% | - | - | -166.76% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 300.24% | 100.00% | -200.24% | - | - | - | 0.33 | 66.69% | - | - | -200.24% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 300.24% | 100.00% | -200.24% | - | - | - | 0.33 | 66.69% | - | - | -200.24% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.11% | 0.11% | 198.72% | 100.00% | -98.72% | - | - | - | 0.50 | 49.68% | - | - | -98.72% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2644.25 | -264325.00% | - | - | 99.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.17% | 0.16% | 248.21% | 100.00% | -148.21% | - | - | - | 0.40 | 59.71% | - | - | -148.21% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 738.16% | 100.00% | -638.16% | - | - | - | 0.14 | 86.45% | - | - | -638.16% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1205.00 | -120400.00% | - | - | 99.92% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 695.53% | 100.00% | -595.53% | - | - | - | 0.14 | 85.62% | - | - | -595.53% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 423.16% | 100.00% | -323.16% | - | - | - | 0.24 | 76.37% | - | - | -323.16% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 125.38% | 100.00% | -25.38% | - | - | - | 0.80 | 20.24% | - | - | -25.38% | - | 0.00% |
|
PARALES DE 4" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REGLA DE 3"X2"X8'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 141.53 | -14053.00% | - | - | 99.29% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 335.90% | 100.00% | -235.90% | - | - | - | 0.30 | 70.23% | - | - | -235.90% | - | 0.00% |
|
TABLA 1" X 12" X 8´
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.01% | 0.01% | 268.07% | 100.00% | -168.07% | - | - | - | 0.37 | 62.70% | - | - | -168.07% | - | 0.00% |
|
PARALES DE 3" X 3" X 7'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 367.09% | 100.00% | -267.09% | - | - | - | 0.27 | 72.76% | - | - | -267.09% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 166.45% | 100.00% | -66.45% | - | - | - | 0.60 | 39.92% | - | - | -66.45% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.14% | 100.00% | 39.86% | - | - | - | 1.66 | -66.28% | - | - | 39.86% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.01% | 0.01% | 452.66% | 100.00% | -352.66% | - | - | - | 0.22 | 77.91% | - | - | -352.66% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 216.53% | 100.00% | -116.53% | - | - | - | 0.46 | 53.82% | - | - | -116.53% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 170.38 | -16938.00% | - | - | 99.41% | - | 0.00% |
|
ANTISOL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GEOTEXTIL NO TEJIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.06% | 0.05% | 123.76% | 100.00% | -23.76% | - | - | - | 0.81 | 19.20% | - | - | -23.76% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 115.58% | 100.00% | -15.58% | - | - | - | 0.87 | 13.48% | - | - | -15.58% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 166.84% | 100.00% | -66.84% | - | - | - | 0.60 | 40.06% | - | - | -66.84% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.02% | 129.43% | 100.00% | -29.43% | - | - | - | 0.77 | 22.74% | - | - | -29.43% | - | 0.00% |
|
ELECTROMALLA 6X6 3/3
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.10% | 100.00% | 31.90% | - | - | - | 1.47 | -46.85% | - | - | 31.90% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 17.19% | 100.00% | 82.81% | - | - | - | 5.82 | -481.82% | - | - | 82.81% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 51.67% | 100.00% | 48.33% | - | - | - | 1.94 | -93.55% | - | - | 48.33% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 92.55% | 100.00% | 7.45% | - | - | - | 1.08 | -8.05% | - | - | 7.45% | - | 0.00% |
|
BLOCK DE 14X19X19.5 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 14X19X39 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 14X19X39 - 100 KGS/CM2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3001.35 | -300035.00% | - | - | 99.97% | - | 0.00% |
|
BLOCK DE 9X19X39 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK "U" DE 14X19X39 - 100KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.55% | 100.00% | 19.45% | - | - | - | 1.24 | -24.14% | - | - | 19.45% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.06% | 0.05% | 27.91% | 100.00% | 72.09% | - | - | - | 3.58 | -258.35% | - | - | 72.09% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 10151.80 | -1015080.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO FLUIDO 4001 M3
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2069.98 | -206898.00% | - | - | 99.95% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.01% | 0.01% | 103.35% | 100.00% | -3.35% | - | - | - | 0.97 | 3.24% | - | - | -3.35% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 79.54 | -7854.00% | - | - | 98.74% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 79.54 | -7854.00% | - | - | 98.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA MADERA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCA DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO DE CONCRETO PERFORADO DE 42"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2316.83 | -231583.00% | - | - | 99.96% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2316.83 | -231583.00% | - | - | 99.96% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 41.66% | 100.00% | 58.34% | - | - | - | 2.40 | -140.06% | - | - | 58.34% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 41.66% | 100.00% | 58.34% | - | - | - | 2.40 | -140.06% | - | - | 58.34% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 720.19 | -71919.00% | - | - | 99.86% | - | 0.00% |
|
FLETES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 339.40 | -33840.00% | - | - | 99.71% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 339.40 | -33840.00% | - | - | 99.71% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 339.40 | -33840.00% | - | - | 99.71% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SEGUETA PARA SIERRA BANDA PORTÁTIL M-18 MILWAUKEE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PAVIMENTOS
|
- | - | - | - | - | - | 2.31% | 2.23% | 203.01% | 100.00% | -103.01% | - | - | - | 0.49 | 50.74% | - | - | -103.01% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 1.16% | 1.12% | 204.67% | 100.00% | -104.67% | - | - | - | 0.49 | 51.14% | - | - | -104.67% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 1.16% | 1.12% | 204.67% | 100.00% | -104.67% | - | - | - | 0.49 | 51.14% | - | - | -104.67% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 1.01% | 0.97% | 208.36% | 100.00% | -108.36% | - | - | - | 0.48 | 52.01% | - | - | -108.36% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.14% | 0.14% | 180.68% | 100.00% | -80.68% | - | - | - | 0.55 | 44.65% | - | - | -80.68% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.00% | 157.81% | 100.00% | -57.81% | - | - | - | 0.63 | 36.63% | - | - | -57.81% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 1.15% | 1.11% | 155.18% | 100.00% | -55.18% | - | - | - | 0.64 | 35.56% | - | - | -55.18% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 120.18% | 100.00% | -20.18% | - | - | - | 0.83 | 16.79% | - | - | -20.18% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 111.63% | 100.00% | -11.63% | - | - | - | 0.90 | 10.42% | - | - | -11.63% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.64 | -7964.00% | - | - | 98.76% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 105.51% | 100.00% | -5.51% | - | - | - | 0.95 | 5.22% | - | - | -5.51% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2199.34 | -219834.00% | - | - | 99.95% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 64.60% | 100.00% | 35.40% | - | - | - | 1.55 | -54.79% | - | - | 35.40% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 209.23 | -20823.00% | - | - | 99.52% | - | 0.00% |
|
ANTISOL BLANCO
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11266.22 | -1126522.00% | - | - | 99.99% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 1.04% | 1.00% | 28.84% | 100.00% | 71.16% | - | - | - | 3.47 | -246.75% | - | - | 71.16% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 1.04% | 1.00% | 0.00% | 100.00% | 100.00% | - | - | - | 313866.40 | -31386540.00% | - | - | 100.00% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE ALISADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE CORTE DE CISAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONMR600 MODULO DE ROTURA 600 TNM 1 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COSTANERA LEGITIMA DE 5"X6MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCA DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORTE DE SISA EN CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PREFABRICADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADOQUIN
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2175.00 | -217400.00% | - | - | 99.95% | - | 0.00% |
|
SELECTO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2175.00 | -217400.00% | - | - | 99.95% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 19089.74 | -1908874.00% | - | - | 99.99% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 19089.74 | -1908874.00% | - | - | 99.99% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TIRALINEAS DE PLASTICO 30M TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('GASTOS DE ADMINISTRACION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SERVICIOS BASICOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PROVISION PRESTACIONES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BANQUETA PERIMETRAL Y DE SENDEROS
|
- | - | - | - | - | - | 0.90% | 0.87% | 135.91% | 70.00% | -65.91% | - | - | - | 0.52 | 48.49% | - | - | -94.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.34% | 0.33% | 151.85% | 70.00% | -81.85% | - | - | - | 0.46 | 53.90% | - | - | -116.93% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.34% | 0.33% | 151.85% | 70.00% | -81.85% | - | - | - | 0.46 | 53.90% | - | - | -116.93% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 2706.98% | 70.00% | -2636.98% | - | - | - | 0.03 | 97.41% | - | - | -3767.11% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.33% | 0.32% | 55.61% | 70.00% | 14.39% | - | - | - | 1.26 | -25.87% | - | - | 20.55% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.54% | 0.52% | 127.02% | 70.00% | -57.02% | - | - | - | 0.55 | 44.89% | - | - | -81.46% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2293.94% | 70.00% | -2223.94% | - | - | - | 0.03 | 96.95% | - | - | -3177.06% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 83.54 | -8254.50% | - | - | 98.80% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.21% | 0.20% | 129.23% | 70.00% | -59.23% | - | - | - | 0.54 | 45.83% | - | - | -84.62% | - | 0.00% |
|
CONMR600 MODULO DE ROTURA 600 TNM 1 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.21% | 0.20% | 122.90% | 70.00% | -52.90% | - | - | - | 0.57 | 43.04% | - | - | -75.57% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.14% | 0.14% | 129.19% | 70.00% | -59.19% | - | - | - | 0.54 | 45.81% | - | - | -84.55% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.06% | 0.06% | 28.46% | 70.00% | 41.54% | - | - | - | 2.46 | -145.92% | - | - | 59.34% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELECTO
|
- | - | - | - | - | - | 0.06% | 0.06% | 0.00% | 70.00% | 70.00% | - | - | - | 12425.00 | -1242400.00% | - | - | 99.99% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.03% | 0.03% | 323.35% | 70.00% | -253.35% | - | - | - | 0.22 | 78.35% | - | - | -361.93% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 75.11% | 70.00% | -5.11% | - | - | - | 0.93 | 6.80% | - | - | -7.30% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.08% | 70.00% | 38.92% | - | - | - | 2.25 | -125.23% | - | - | 55.60% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 70.00% | 70.00% | - | - | - | 1454.27 | -145327.10% | - | - | 99.93% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.03% | 0.02% | 61.55% | 70.00% | 8.45% | - | - | - | 1.14 | -13.72% | - | - | 12.07% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.84% | 70.00% | 61.16% | - | - | - | 7.92 | -691.92% | - | - | 87.37% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 54.38% | 70.00% | 15.62% | - | - | - | 1.29 | -28.73% | - | - | 22.32% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 70.00% | 70.00% | - | - | - | 5979.83 | -597883.40% | - | - | 99.98% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 816.50 | -81550.10% | - | - | 99.88% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 816.50 | -81550.10% | - | - | 99.88% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 70.00% | 70.00% | - | - | - | 3553.10 | -355210.20% | - | - | 99.97% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 70.00% | 70.00% | - | - | - | 3553.10 | -355210.20% | - | - | 99.97% | - | 0.00% |
|
('PREFABRICADOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 0.00% | 70.00% | 70.00% | - | - | - | 20874.00 | -2087300.00% | - | - | 100.00% | - | 0.00% |
|
BORDILLO PREFABRICADO MITAD TRAPEZOIDAL DE 15X30X50
|
- | - | - | - | - | - | 0.10% | 0.10% | 0.00% | 70.00% | 70.00% | - | - | - | 20874.00 | -2087300.00% | - | - | 100.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CARRETA DE MANO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 70.00% | 70.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 70.00% | 70.00% | - | - | - | 4845.75 | -484475.00% | - | - | 99.98% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 70.00% | 70.00% | - | - | - | 4845.75 | -484475.00% | - | - | 99.98% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 70.00% | 70.00% | - | - | - | 4845.75 | -484475.00% | - | - | 99.98% | - | 0.00% |
|
MUROS DE CONTENCION
|
- | - | - | - | - | - | 1.79% | 2.36% | 129.69% | 90.00% | -39.69% | - | - | - | 0.69 | 30.60% | - | - | -44.10% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.53% | 0.54% | 323.13% | 90.00% | -233.13% | - | - | - | 0.28 | 72.15% | - | - | -259.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.53% | 0.54% | 323.13% | 90.00% | -233.13% | - | - | - | 0.28 | 72.15% | - | - | -259.03% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.01% | 7069.74% | 90.00% | -6979.74% | - | - | - | 0.01 | 98.73% | - | - | -7755.27% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.53% | 0.52% | 195.98% | 90.00% | -105.98% | - | - | - | 0.46 | 54.08% | - | - | -117.76% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.74% | 90.00% | 52.26% | - | - | - | 2.38 | -138.50% | - | - | 58.07% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 1.22% | 1.73% | 72.98% | 90.00% | 17.02% | - | - | - | 1.23 | -23.32% | - | - | 18.91% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.02% | 0.06% | 181.12% | 90.00% | -91.12% | - | - | - | 0.50 | 50.31% | - | - | -101.24% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.01% | 249.78% | 90.00% | -159.78% | - | - | - | 0.36 | 63.97% | - | - | -177.53% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.02% | 0.03% | 65.55% | 90.00% | 24.45% | - | - | - | 1.37 | -37.30% | - | - | 27.17% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.01% | 24.38% | 90.00% | 65.62% | - | - | - | 3.69 | -269.18% | - | - | 72.91% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.01% | 621.79% | 90.00% | -531.79% | - | - | - | 0.14 | 85.53% | - | - | -590.88% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.30% | 0.38% | 109.60% | 90.00% | -19.60% | - | - | - | 0.82 | 17.88% | - | - | -21.77% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.01% | 469.99% | 90.00% | -379.99% | - | - | - | 0.19 | 80.85% | - | - | -422.21% | - | 0.00% |
|
SERVICIO DE BOMBEO CONVENCIONAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 7.31% | 90.00% | 82.69% | - | - | - | 12.32 | -1131.90% | - | - | 91.88% | - | 0.00% |
|
SERVICIO DE COLOCACION CON PLUMA
|
- | - | - | - | - | - | 0.00% | 0.01% | 7.31% | 90.00% | 82.69% | - | - | - | 12.32 | -1131.90% | - | - | 91.88% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.90% | 90.00% | 69.10% | - | - | - | 4.31 | -330.71% | - | - | 76.78% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.01% | 112.60% | 90.00% | -22.60% | - | - | - | 0.80 | 20.07% | - | - | -25.12% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.01% | 3098.69% | 90.00% | -3008.69% | - | - | - | 0.03 | 97.10% | - | - | -3342.99% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.01% | 112.60% | 90.00% | -22.60% | - | - | - | 0.80 | 20.07% | - | - | -25.12% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.30% | 0.30% | 5.98% | 90.00% | 84.02% | - | - | - | 15.05 | -1404.69% | - | - | 93.35% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.15% | 0.20% | 102.50% | 90.00% | -12.50% | - | - | - | 0.88 | 12.19% | - | - | -13.89% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.04% | 0.05% | 36.03% | 90.00% | 53.97% | - | - | - | 2.50 | -149.77% | - | - | 59.96% | - | 0.00% |
|
CONMR600 MODULO DE ROTURA 600 TNM 1 1/2
|
- | - | - | - | - | - | 0.00% | 0.01% | 135.43% | 90.00% | -45.43% | - | - | - | 0.66 | 33.54% | - | - | -50.47% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 90.00% | 90.00% | - | - | - | 9003.62 | -900261.67% | - | - | 99.99% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.17% | 90.00% | 88.83% | - | - | - | 76.91 | -7590.78% | - | - | 98.70% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.09% | 0.10% | 178.80% | 90.00% | -88.80% | - | - | - | 0.50 | 49.66% | - | - | -98.66% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.31% | 0.48% | 94.19% | 90.00% | -4.19% | - | - | - | 0.96 | 4.45% | - | - | -4.66% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.01% | 71.84% | 90.00% | 18.16% | - | - | - | 1.25 | -25.27% | - | - | 20.17% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.04% | 90.00% | 88.96% | - | - | - | 86.53 | -8552.67% | - | - | 98.84% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.93% | 90.00% | 87.07% | - | - | - | 30.77 | -2976.50% | - | - | 96.75% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.02% | 0.03% | 44.00% | 90.00% | 46.00% | - | - | - | 2.05 | -104.55% | - | - | 51.11% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.01% | 86.16% | 90.00% | 3.84% | - | - | - | 1.04 | -4.46% | - | - | 4.27% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 26.25% | 90.00% | 63.75% | - | - | - | 3.43 | -242.92% | - | - | 70.84% | - | 0.00% |
|
ACERO DE 3/8 X 9 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 182.06% | 90.00% | -92.06% | - | - | - | 0.49 | 50.57% | - | - | -102.29% | - | 0.00% |
|
ACERO DE 1/2 X 9MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 66.86% | 90.00% | 23.14% | - | - | - | 1.35 | -34.62% | - | - | 25.71% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.02% | 0.03% | 22.37% | 90.00% | 67.63% | - | - | - | 4.02 | -302.40% | - | - | 75.15% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 786.93% | 90.00% | -696.93% | - | - | - | 0.11 | 88.56% | - | - | -774.37% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 154.22% | 90.00% | -64.22% | - | - | - | 0.58 | 41.64% | - | - | -71.35% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.26% | 0.26% | 91.03% | 90.00% | -1.03% | - | - | - | 0.99 | 1.13% | - | - | -1.14% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.63% | 90.00% | 69.37% | - | - | - | 4.36 | -336.35% | - | - | 77.08% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.01% | 23.64% | 90.00% | 66.36% | - | - | - | 3.81 | -280.78% | - | - | 73.74% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.01% | 15.52% | 90.00% | 74.48% | - | - | - | 5.80 | -480.02% | - | - | 82.76% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.86% | 90.00% | 89.14% | - | - | - | 104.09 | -10309.22% | - | - | 99.04% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 365.72% | 90.00% | -275.72% | - | - | - | 0.25 | 75.39% | - | - | -306.36% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.03% | 0.06% | 75.07% | 90.00% | 14.93% | - | - | - | 1.20 | -19.89% | - | - | 16.59% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.02% | 0.03% | 7.27% | 90.00% | 82.73% | - | - | - | 12.37 | -1137.31% | - | - | 91.92% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.01% | 173.54% | 90.00% | -83.54% | - | - | - | 0.52 | 48.14% | - | - | -92.82% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.01% | 0.02% | 141.25% | 90.00% | -51.25% | - | - | - | 0.64 | 36.28% | - | - | -56.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.06% | 21.29% | 90.00% | 68.71% | - | - | - | 4.23 | -322.78% | - | - | 76.35% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.01% | 29.02% | 90.00% | 60.98% | - | - | - | 3.10 | -210.11% | - | - | 67.75% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.17% | 90.00% | 89.83% | - | - | - | 538.39 | -53738.81% | - | - | 99.81% | - | 0.00% |
|
NYLON TRANSPARENTTE
|
- | - | - | - | - | - | 0.00% | 0.01% | 34.40% | 90.00% | 55.60% | - | - | - | 2.62 | -161.66% | - | - | 61.78% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.60% | 90.00% | 87.40% | - | - | - | 34.65 | -3364.78% | - | - | 97.11% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.01% | 59.44% | 90.00% | 30.56% | - | - | - | 1.51 | -51.42% | - | - | 33.96% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.11% | 90.00% | 87.89% | - | - | - | 42.73 | -4172.92% | - | - | 97.66% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 12.22% | 90.00% | 77.78% | - | - | - | 7.36 | -636.40% | - | - | 86.42% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.01% | 12.22% | 90.00% | 77.78% | - | - | - | 7.36 | -636.40% | - | - | 86.42% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.16% | 0.17% | 6.41% | 90.00% | 83.59% | - | - | - | 14.05 | -1304.90% | - | - | 92.88% | - | 0.00% |
|
BLOCK "U" DE 14X19X39 - 100KG/CM2
|
- | - | - | - | - | - | 0.16% | 0.16% | 0.00% | 90.00% | 90.00% | - | - | - | 45842.19 | -4584119.17% | - | - | 100.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.01% | 107.42% | 90.00% | -17.42% | - | - | - | 0.84 | 16.22% | - | - | -19.35% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.20% | 0.24% | 4.38% | 90.00% | 85.62% | - | - | - | 20.54 | -1954.07% | - | - | 95.13% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.01% | 30.83% | 90.00% | 59.17% | - | - | - | 2.92 | -191.90% | - | - | 65.74% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.01% | 19.50% | 90.00% | 70.50% | - | - | - | 4.61 | -361.48% | - | - | 78.33% | - | 0.00% |
|
EMULSION ASFALTICA
|
- | - | - | - | - | - | 0.00% | 0.01% | 51.08% | 90.00% | 38.92% | - | - | - | 1.76 | -76.20% | - | - | 43.25% | - | 0.00% |
|
SIKATOP SEAL 107, KIT 16.3 KG
|
- | - | - | - | - | - | 0.20% | 0.21% | 0.00% | 90.00% | 90.00% | - | - | - | 58569.36 | -5856836.17% | - | - | 100.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.97% | 90.00% | 88.03% | - | - | - | 45.80 | -4479.86% | - | - | 97.82% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.97% | 90.00% | 88.03% | - | - | - | 45.80 | -4479.86% | - | - | 97.82% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 3336.09 | -333509.17% | - | - | 99.97% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 3336.09 | -333509.17% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 90.00% | 90.00% | - | - | - | 12938.73 | -1293773.17% | - | - | 99.99% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 90.00% | 90.00% | - | - | - | 12938.73 | -1293773.17% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.03% | 0.05% | 60.41% | 90.00% | 29.59% | - | - | - | 1.49 | -48.98% | - | - | 32.88% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.03% | 0.05% | 60.41% | 90.00% | 29.59% | - | - | - | 1.49 | -48.98% | - | - | 32.88% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 90.00% | 90.00% | - | - | - | 11734.25 | -1173325.27% | - | - | 99.99% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.01% | 304.24% | 90.00% | -214.24% | - | - | - | 0.30 | 70.42% | - | - | -238.05% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.15% | 90.00% | 52.85% | - | - | - | 2.42 | -142.27% | - | - | 58.72% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.15% | 90.00% | 52.85% | - | - | - | 2.42 | -142.27% | - | - | 58.72% | - | 0.00% |
|
ALQUILER DE MAQUINARIA
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.15% | 90.00% | 52.85% | - | - | - | 2.42 | -142.27% | - | - | 58.72% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.02% | 1.07% | 90.00% | 88.93% | - | - | - | 84.08 | -8308.43% | - | - | 98.81% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.21% | 90.00% | 87.79% | - | - | - | 40.65 | -3965.01% | - | - | 97.54% | - | 0.00% |
|
TIRALINEAS DE PLASTICO 30M TRUPER
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.21% | 90.00% | 87.79% | - | - | - | 40.65 | -3965.01% | - | - | 97.54% | - | 0.00% |
|
('EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 3106.41 | -310541.17% | - | - | 99.97% | - | 0.00% |
|
ANDAMIOS
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 3106.41 | -310541.17% | - | - | 99.97% | - | 0.00% |
|
INFRAESTRUCTURA ELECTRICA Y ESPECIALES
|
- | - | - | - | - | - | 1.25% | 1.34% | 119.90% | 90.00% | -29.90% | - | - | - | 0.75 | 24.94% | - | - | -33.22% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.88% | 90.00% | -152.88% | - | - | - | 0.37 | 62.94% | - | - | -169.86% | - | 0.00% |
|
('MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.88% | 90.00% | -152.88% | - | - | - | 0.37 | 62.94% | - | - | -169.86% | - | 0.00% |
|
EXTRACCION EXCAVACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.88% | 90.00% | -152.88% | - | - | - | 0.37 | 62.94% | - | - | -169.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.03% | 0.15% | 232.68% | 90.00% | -142.68% | - | - | - | 0.39 | 61.32% | - | - | -158.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.03% | 887.44% | 90.00% | -797.44% | - | - | - | 0.10 | 89.86% | - | - | -886.05% | - | 0.00% |
|
PEGAMENTO PVC GALON
|
- | - | - | - | - | - | 0.00% | 0.00% | 87.90% | 90.00% | 2.10% | - | - | - | 1.02 | -2.38% | - | - | 2.33% | - | 0.00% |
|
ESPUMA EXPANSIVA SISTA 500 ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 45.95% | 90.00% | 44.05% | - | - | - | 1.96 | -95.85% | - | - | 48.94% | - | 0.00% |
|
TUBO DE 4" (250 PSI) PVC AP
|
- | - | - | - | - | - | 0.00% | 0.00% | 2982.67% | 90.00% | -2892.67% | - | - | - | 0.03 | 96.98% | - | - | -3214.08% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.07% | 90.00% | 84.93% | - | - | - | 17.74 | -1673.94% | - | - | 94.36% | - | 0.00% |
|
TUBO DE 4" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.89% | 90.00% | -103.89% | - | - | - | 0.46 | 53.58% | - | - | -115.44% | - | 0.00% |
|
CAJA TIPO H
|
- | - | - | - | - | - | 0.00% | 0.00% | 2845.14% | 90.00% | -2755.14% | - | - | - | 0.03 | 96.84% | - | - | -3061.26% | - | 0.00% |
|
CAJA TIPO VII PARA ESPECIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 929.87% | 90.00% | -839.87% | - | - | - | 0.10 | 90.32% | - | - | -933.19% | - | 0.00% |
|
TAPON HEMBRA DE 4" LISO PVC
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.02% | 90.00% | 80.98% | - | - | - | 9.98 | -897.65% | - | - | 89.98% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.03% | 152.07% | 90.00% | -62.07% | - | - | - | 0.59 | 40.82% | - | - | -68.96% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 633.54% | 90.00% | -543.54% | - | - | - | 0.14 | 85.79% | - | - | -603.94% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 128.73% | 90.00% | -38.73% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
TUBO PVC GRIS DE 1" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 195.24% | 90.00% | -105.24% | - | - | - | 0.46 | 53.90% | - | - | -116.94% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.24% | 90.00% | 19.76% | - | - | - | 1.28 | -28.14% | - | - | 21.96% | - | 0.00% |
|
COPLA PVC GRIS DE 1" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 23.65% | 90.00% | 66.35% | - | - | - | 3.81 | -280.54% | - | - | 73.72% | - | 0.00% |
|
VUELTA PVC GRIS DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.40% | 90.00% | 89.60% | - | - | - | 222.33 | -22133.42% | - | - | 99.55% | - | 0.00% |
|
MORDAZA
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.66% | 90.00% | 77.34% | - | - | - | 7.11 | -610.66% | - | - | 85.93% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 52.89% | 90.00% | 37.11% | - | - | - | 1.70 | -70.15% | - | - | 41.23% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 52.89% | 90.00% | 37.11% | - | - | - | 1.70 | -70.15% | - | - | 41.23% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.32% | 90.00% | 43.68% | - | - | - | 1.94 | -94.30% | - | - | 48.53% | - | 0.00% |
|
PIEDRIN DE 1 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.32% | 90.00% | 43.68% | - | - | - | 1.94 | -94.30% | - | - | 48.53% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.03% | 6.09% | 90.00% | 83.91% | - | - | - | 14.79 | -1378.78% | - | - | 93.24% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.68% | 90.00% | 89.32% | - | - | - | 131.45 | -13044.76% | - | - | 99.24% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.87% | 90.00% | 87.13% | - | - | - | 31.40 | -3040.31% | - | - | 96.82% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.00% | 90.00% | 86.00% | - | - | - | 22.51 | -2150.78% | - | - | 95.56% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 24.33% | 90.00% | 65.67% | - | - | - | 3.70 | -269.93% | - | - | 72.97% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.18% | 90.00% | 77.82% | - | - | - | 7.39 | -638.86% | - | - | 86.47% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.76% | 90.00% | 89.24% | - | - | - | 118.62 | -11762.34% | - | - | 99.16% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.82% | 90.00% | 89.18% | - | - | - | 110.33 | -10932.65% | - | - | 99.09% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 3.06% | 90.00% | 86.94% | - | - | - | 29.45 | -2845.38% | - | - | 96.60% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.07% | 90.00% | 87.93% | - | - | - | 43.55 | -4255.43% | - | - | 97.70% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1.67% | 90.00% | 88.33% | - | - | - | 54.04 | -5303.96% | - | - | 98.15% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.47% | 90.00% | 87.53% | - | - | - | 36.48 | -3547.67% | - | - | 97.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 90.00% | 90.00% | - | - | - | 10201.27 | -1020026.55% | - | - | 99.99% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 90.00% | 90.00% | - | - | - | 10201.27 | -1020026.55% | - | - | 99.99% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 140.19% | 90.00% | -50.19% | - | - | - | 0.64 | 35.80% | - | - | -55.77% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 140.19% | 90.00% | -50.19% | - | - | - | 0.64 | 35.80% | - | - | -55.77% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 140.19% | 90.00% | -50.19% | - | - | - | 0.64 | 35.80% | - | - | -55.77% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 1.21% | 1.18% | 105.35% | 90.00% | -15.35% | - | - | - | 0.85 | 14.57% | - | - | -17.05% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 1.21% | 1.18% | 105.35% | 90.00% | -15.35% | - | - | - | 0.85 | 14.57% | - | - | -17.05% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 1.10% | 1.07% | 84.49% | 90.00% | 5.51% | - | - | - | 1.07 | -6.52% | - | - | 6.12% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.11% | 0.11% | 308.86% | 90.00% | -218.86% | - | - | - | 0.29 | 70.86% | - | - | -243.18% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.39% | 90.00% | -11.39% | - | - | - | 0.89 | 11.24% | - | - | -12.66% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.39% | 90.00% | -11.39% | - | - | - | 0.89 | 11.24% | - | - | -12.66% | - | 0.00% |
|
FLETES
|
- | - | - | - | - | - | 0.00% | 0.00% | 101.39% | 90.00% | -11.39% | - | - | - | 0.89 | 11.24% | - | - | -12.66% | - | 0.00% |
|
ACABADOS E INSTALACIONES
|
- | - | - | - | - | - | 0.99% | 1.00% | 69.13% | 69.00% | -0.13% | - | - | - | 1.00 | 0.19% | - | - | -0.19% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.91% | 0.88% | 74.80% | 69.00% | -5.80% | - | - | - | 0.92 | 7.76% | - | - | -8.41% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.91% | 0.88% | 74.80% | 69.00% | -5.80% | - | - | - | 0.92 | 7.76% | - | - | -8.41% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.86% | 0.83% | 78.22% | 69.00% | -9.22% | - | - | - | 0.88 | 11.79% | - | - | -13.36% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.05% | 0.04% | 10.80% | 69.00% | 58.20% | - | - | - | 6.39 | -538.88% | - | - | 84.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.12% | 27.65% | 69.00% | 41.35% | - | - | - | 2.50 | -149.56% | - | - | 59.93% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.91% | 69.00% | -118.91% | - | - | - | 0.37 | 63.28% | - | - | -172.33% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 83.78% | 69.00% | -14.78% | - | - | - | 0.82 | 17.64% | - | - | -21.42% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.52% | 69.00% | 55.48% | - | - | - | 5.10 | -410.44% | - | - | 80.41% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 385.43% | 69.00% | -316.43% | - | - | - | 0.18 | 82.10% | - | - | -458.59% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.00% | 0.00% | 176.54% | 69.00% | -107.54% | - | - | - | 0.39 | 60.91% | - | - | -155.85% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 258.83 | -25783.04% | - | - | 99.61% | - | 0.00% |
|
NIVELADOR PEGACERAMICO DE 40 KG.
|
- | - | - | - | - | - | 0.00% | 0.00% | 663.25% | 69.00% | -594.25% | - | - | - | 0.10 | 89.60% | - | - | -861.24% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 97.13% | 69.00% | -28.13% | - | - | - | 0.71 | 28.96% | - | - | -40.77% | - | 0.00% |
|
FELPA SIN RODILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 139.43 | -13842.59% | - | - | 99.28% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 411.40% | 69.00% | -342.40% | - | - | - | 0.17 | 83.23% | - | - | -496.23% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 30.92% | 69.00% | 38.08% | - | - | - | 2.23 | -123.17% | - | - | 55.19% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 141.68 | -14067.53% | - | - | 99.29% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.42% | 69.00% | 22.58% | - | - | - | 1.49 | -48.63% | - | - | 32.72% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.75% | 69.00% | -19.75% | - | - | - | 0.78 | 22.25% | - | - | -28.62% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 169.55% | 69.00% | -100.55% | - | - | - | 0.41 | 59.30% | - | - | -145.73% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 7.94% | 69.00% | 61.06% | - | - | - | 8.69 | -769.12% | - | - | 88.49% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 77.25% | 69.00% | -8.25% | - | - | - | 0.89 | 10.67% | - | - | -11.95% | - | 0.00% |
|
LLAVE DE DUCHA TIPO SAYCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 43.22% | 69.00% | 25.78% | - | - | - | 1.60 | -59.64% | - | - | 37.36% | - | 0.00% |
|
PEGAMENTO PVC 1/4
|
- | - | - | - | - | - | 0.00% | 0.00% | 94.75% | 69.00% | -25.75% | - | - | - | 0.73 | 27.18% | - | - | -37.32% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 85.65% | 69.00% | -16.65% | - | - | - | 0.81 | 19.44% | - | - | -24.14% | - | 0.00% |
|
REPOSADERA METALICA 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 47.17% | 69.00% | 21.83% | - | - | - | 1.46 | -46.28% | - | - | 31.64% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.42% | 69.00% | 1.58% | - | - | - | 1.02 | -2.34% | - | - | 2.29% | - | 0.00% |
|
TUBO DE 4" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.00% | 241.13% | 69.00% | -172.13% | - | - | - | 0.29 | 71.38% | - | - | -249.46% | - | 0.00% |
|
CHAPETA CROMADA DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 145.26 | -14426.33% | - | - | 99.31% | - | 0.00% |
|
REGADERA GRIFERINA DE DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 127.17% | 69.00% | -58.17% | - | - | - | 0.54 | 45.74% | - | - | -84.30% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 47.32% | 69.00% | 21.68% | - | - | - | 1.46 | -45.80% | - | - | 31.41% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.18% | 69.00% | 10.82% | - | - | - | 1.19 | -18.59% | - | - | 15.68% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.86% | 69.00% | 14.14% | - | - | - | 1.26 | -25.78% | - | - | 20.50% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 34.81% | 69.00% | 34.19% | - | - | - | 1.98 | -98.20% | - | - | 49.55% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 10.77% | 69.00% | 58.23% | - | - | - | 6.41 | -540.57% | - | - | 84.39% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 253.66 | -25266.23% | - | - | 99.61% | - | 0.00% |
|
BANDEJA PARA PINTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 139.63 | -13863.29% | - | - | 99.28% | - | 0.00% |
|
MANERAL PARA PINTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 139.96 | -13895.72% | - | - | 99.29% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 13.95% | 69.00% | 55.05% | - | - | - | 4.95 | -394.68% | - | - | 79.79% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 41.87% | 69.00% | 27.13% | - | - | - | 1.65 | -64.78% | - | - | 39.31% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 299.21% | 69.00% | -230.21% | - | - | - | 0.23 | 76.94% | - | - | -333.64% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.89% | 69.00% | 28.11% | - | - | - | 1.69 | -68.74% | - | - | 40.74% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.89% | 69.00% | 28.11% | - | - | - | 1.69 | -68.74% | - | - | 40.74% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 37.02% | 69.00% | 31.98% | - | - | - | 1.86 | -86.39% | - | - | 46.35% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 69.00% | 69.00% | - | - | - | 1146.80 | -114579.83% | - | - | 99.91% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 66.72% | 69.00% | 2.28% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.85% | 69.00% | 60.15% | - | - | - | 7.80 | -680.05% | - | - | 87.18% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.01% | 0.01% | 38.60% | 69.00% | 30.40% | - | - | - | 1.79 | -78.76% | - | - | 44.06% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 146.68 | -14568.47% | - | - | 99.32% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 146.68 | -14568.47% | - | - | 99.32% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.41% | 69.00% | 68.59% | - | - | - | 169.06 | -16806.42% | - | - | 99.41% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 248.88 | -24788.06% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 349.30 | -34830.32% | - | - | 99.71% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.32% | 69.00% | 63.68% | - | - | - | 12.97 | -1196.75% | - | - | 92.29% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 172.95 | -17195.30% | - | - | 99.42% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 214.21 | -21320.81% | - | - | 99.53% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 680.21 | -67920.65% | - | - | 99.85% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 270.34 | -26933.96% | - | - | 99.63% | - | 0.00% |
|
ANTISOL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 270.34 | -26933.96% | - | - | 99.63% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 1004.83 | -100383.08% | - | - | 99.90% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 1004.83 | -100383.08% | - | - | 99.90% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 69.00% | 69.00% | - | - | - | 1165.12 | -116411.99% | - | - | 99.91% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 264.48 | -26348.15% | - | - | 99.62% | - | 0.00% |
|
SELECTO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 588.78 | -58778.15% | - | - | 99.83% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 311.86 | -31085.69% | - | - | 99.68% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 69.00% | 69.00% | - | - | - | 2600.22 | -259921.88% | - | - | 99.96% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 69.00% | 69.00% | - | - | - | 2116.92 | -211591.76% | - | - | 99.95% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 483.30 | -48230.12% | - | - | 99.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 69.00% | 69.00% | - | - | - | 7748.59 | -774759.41% | - | - | 99.99% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 69.00% | 69.00% | - | - | - | 7748.59 | -774759.41% | - | - | 99.99% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.47% | 69.00% | 41.53% | - | - | - | 2.51 | -151.20% | - | - | 60.19% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.47% | 69.00% | 41.53% | - | - | - | 2.51 | -151.20% | - | - | 60.19% | - | 0.00% |
|
SEGUETA PARA SIERRA BANDA PORTÁTIL M-18 MILWAUKEE
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.47% | 69.00% | 41.53% | - | - | - | 2.51 | -151.20% | - | - | 60.19% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 201.74 | -20073.98% | - | - | 99.50% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 201.74 | -20073.98% | - | - | 99.50% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 69.00% | 69.00% | - | - | - | 201.74 | -20073.98% | - | - | 99.50% | - | 0.00% |
|
INFRAESTRUCTURA HIDROSANITARIA
|
- | - | - | - | - | - | 4.75% | 4.92% | 70.41% | 90.00% | 19.59% | - | - | - | 1.28 | -27.83% | - | - | 21.77% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 485.90% | 90.00% | -395.90% | - | - | - | 0.19 | 81.48% | - | - | -439.89% | - | 0.00% |
|
('MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 485.90% | 90.00% | -395.90% | - | - | - | 0.19 | 81.48% | - | - | -439.89% | - | 0.00% |
|
EXTRACCION EXCAVACION
|
- | - | - | - | - | - | 0.00% | 0.01% | 485.90% | 90.00% | -395.90% | - | - | - | 0.19 | 81.48% | - | - | -439.89% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 4.21% | 4.09% | 71.02% | 90.00% | 18.98% | - | - | - | 1.27 | -26.72% | - | - | 21.09% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 1.86% | 1.80% | 83.63% | 90.00% | 6.37% | - | - | - | 1.08 | -7.61% | - | - | 7.07% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 1.86% | 1.80% | 83.63% | 90.00% | 6.37% | - | - | - | 1.08 | -7.61% | - | - | 7.07% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 2.35% | 2.29% | 61.09% | 90.00% | 28.91% | - | - | - | 1.47 | -47.33% | - | - | 32.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.01% | 9915.52% | 90.00% | -9825.52% | - | - | - | 0.01 | 99.09% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 1.75% | 1.70% | 32.91% | 90.00% | 57.09% | - | - | - | 2.73 | -173.50% | - | - | 63.44% | - | 0.00% |
|
POZO DE ABSORCION
|
- | - | - | - | - | - | 0.59% | 0.58% | 38.36% | 90.00% | 51.64% | - | - | - | 2.35 | -134.63% | - | - | 57.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.54% | 0.80% | 65.74% | 90.00% | 24.26% | - | - | - | 1.37 | -36.90% | - | - | 26.96% | - | 0.00% |
|
('PREFABRICADOS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 2390.92% | 90.00% | -2300.92% | - | - | - | 0.04 | 96.24% | - | - | -2556.58% | - | 0.00% |
|
TAPADERA DE HIERRO FUNDIDA DE 60 CM. MARCA MASELLI
|
- | - | - | - | - | - | 0.00% | 0.01% | 2390.92% | 90.00% | -2300.92% | - | - | - | 0.04 | 96.24% | - | - | -2556.58% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 134.10% | 90.00% | -44.10% | - | - | - | 0.67 | 32.88% | - | - | -49.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 14.77% | 90.00% | 75.23% | - | - | - | 6.09 | -509.46% | - | - | 83.59% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.02% | 0.02% | 171.74% | 90.00% | -81.74% | - | - | - | 0.52 | 47.60% | - | - | -90.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.01% | 0.03% | 78.74% | 90.00% | 11.26% | - | - | - | 1.14 | -14.30% | - | - | 12.51% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 82.97% | 90.00% | 7.03% | - | - | - | 1.08 | -8.47% | - | - | 7.81% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.01% | 78.17% | 90.00% | 11.83% | - | - | - | 1.15 | -15.13% | - | - | 13.14% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.01% | 46.05% | 90.00% | 43.95% | - | - | - | 1.95 | -95.45% | - | - | 48.84% | - | 0.00% |
|
PIEDRA BOLA
|
- | - | - | - | - | - | 0.00% | 0.01% | 113.12% | 90.00% | -23.12% | - | - | - | 0.80 | 20.44% | - | - | -25.69% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.28% | 0.34% | 74.92% | 90.00% | 15.08% | - | - | - | 1.20 | -20.12% | - | - | 16.75% | - | 0.00% |
|
TUBO DE CONCRETO DE 42"
|
- | - | - | - | - | - | 0.11% | 0.11% | 0.00% | 90.00% | 90.00% | - | - | - | 31450.37 | -3144937.06% | - | - | 100.00% | - | 0.00% |
|
PEGAMENTO PVC 1/4
|
- | - | - | - | - | - | 0.00% | 0.01% | 19.54% | 90.00% | 70.46% | - | - | - | 4.61 | -360.62% | - | - | 78.29% | - | 0.00% |
|
TUBO DE CONCRETO DE 16"
|
- | - | - | - | - | - | 0.04% | 0.04% | 41.74% | 90.00% | 48.26% | - | - | - | 2.16 | -115.61% | - | - | 53.62% | - | 0.00% |
|
TUBO DE 2" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.30% | 90.00% | 69.70% | - | - | - | 4.43 | -343.36% | - | - | 77.44% | - | 0.00% |
|
TUBO DE 4" (80 PSI) PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.01% | 1170.97% | 90.00% | -1080.97% | - | - | - | 0.08 | 92.31% | - | - | -1201.08% | - | 0.00% |
|
TUBO DE CONCRETO DE 30"
|
- | - | - | - | - | - | 0.00% | 0.01% | 812.40% | 90.00% | -722.40% | - | - | - | 0.11 | 88.92% | - | - | -802.67% | - | 0.00% |
|
TUBO DE CONCRETO PERFORADO DE 42"
|
- | - | - | - | - | - | 0.00% | 0.01% | 1693.70% | 90.00% | -1603.70% | - | - | - | 0.05 | 94.69% | - | - | -1781.89% | - | 0.00% |
|
TUBO DE CONCRETO DE 36"
|
- | - | - | - | - | - | 0.13% | 0.14% | 0.00% | 90.00% | 90.00% | - | - | - | 38200.37 | -3819937.06% | - | - | 100.00% | - | 0.00% |
|
UNION DE 4" PVC DRENAJE
|
- | - | - | - | - | - | 0.00% | 0.01% | 30.85% | 90.00% | 59.15% | - | - | - | 2.92 | -191.73% | - | - | 65.72% | - | 0.00% |
|
CODO DE 4" X 45 PVC DRENAJE PG
|
- | - | - | - | - | - | 0.00% | 0.01% | 23.40% | 90.00% | 66.60% | - | - | - | 3.85 | -284.70% | - | - | 74.01% | - | 0.00% |
|
CODO DE 4" X 90 PVC DRENAJE PG
|
- | - | - | - | - | - | 0.00% | 0.01% | 26.99% | 90.00% | 63.01% | - | - | - | 3.33 | -233.40% | - | - | 70.01% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 40.13% | 90.00% | 49.87% | - | - | - | 2.24 | -124.26% | - | - | 55.41% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 2218.06 | -221705.56% | - | - | 99.95% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.01% | 90.99% | 90.00% | -0.99% | - | - | - | 0.99 | 1.09% | - | - | -1.10% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.08% | 0.14% | 37.64% | 90.00% | 52.36% | - | - | - | 2.39 | -139.14% | - | - | 58.18% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.01% | 59.44% | 90.00% | 30.56% | - | - | - | 1.51 | -51.41% | - | - | 33.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.33% | 90.00% | 89.67% | - | - | - | 272.02 | -27101.91% | - | - | 99.63% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 73.63% | 90.00% | 16.37% | - | - | - | 1.22 | -22.23% | - | - | 18.19% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 3333.00 | -333200.26% | - | - | 99.97% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 90.00% | 90.00% | - | - | - | 7126.47 | -712546.66% | - | - | 99.99% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.03% | 0.04% | 85.68% | 90.00% | 4.32% | - | - | - | 1.05 | -5.04% | - | - | 4.80% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.25% | 90.00% | 89.75% | - | - | - | 355.77 | -35476.64% | - | - | 99.72% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.01% | 0.01% | 1.00% | 90.00% | 89.00% | - | - | - | 89.78 | -8878.18% | - | - | 98.89% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.99% | 90.00% | 87.01% | - | - | - | 30.08 | -2907.51% | - | - | 96.67% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.01% | 155.27% | 90.00% | -65.27% | - | - | - | 0.58 | 42.04% | - | - | -72.52% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 12.73% | 90.00% | 77.27% | - | - | - | 7.07 | -607.22% | - | - | 85.86% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.01% | 12.73% | 90.00% | 77.27% | - | - | - | 7.07 | -607.22% | - | - | 85.86% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.02% | 9.79% | 90.00% | 80.21% | - | - | - | 9.20 | -819.73% | - | - | 89.13% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.01% | 24.04% | 90.00% | 65.96% | - | - | - | 3.74 | -274.41% | - | - | 73.29% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.01% | 4.91% | 90.00% | 85.09% | - | - | - | 18.32 | -1732.47% | - | - | 94.54% | - | 0.00% |
|
COPLA PVC GRIS DE 1" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.41% | 90.00% | 89.59% | - | - | - | 221.01 | -22000.64% | - | - | 99.55% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.02% | 0.05% | 8.21% | 90.00% | 81.79% | - | - | - | 10.96 | -995.73% | - | - | 90.87% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.01% | 33.72% | 90.00% | 56.28% | - | - | - | 2.67 | -166.92% | - | - | 62.54% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 90.00% | 90.00% | - | - | - | 7958.43 | -795742.66% | - | - | 99.99% | - | 0.00% |
|
REGLA DE 3"X2"X8'
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 2099.57 | -209857.06% | - | - | 99.95% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.01% | 29.91% | 90.00% | 60.09% | - | - | - | 3.01 | -200.93% | - | - | 66.77% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 5.76% | 90.00% | 84.24% | - | - | - | 15.63 | -1462.83% | - | - | 93.60% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.01% | 5.76% | 90.00% | 84.24% | - | - | - | 15.63 | -1462.83% | - | - | 93.60% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.02% | 2.58% | 90.00% | 87.42% | - | - | - | 34.89 | -3389.40% | - | - | 97.13% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.00% | 90.00% | 89.00% | - | - | - | 89.72 | -8871.66% | - | - | 98.89% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.04% | 90.00% | 87.96% | - | - | - | 44.05 | -4304.56% | - | - | 97.73% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.28% | 90.00% | 89.72% | - | - | - | 324.14 | -32314.27% | - | - | 99.69% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.01% | 6.99% | 90.00% | 83.01% | - | - | - | 12.87 | -1187.04% | - | - | 92.23% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 1828.15 | -182714.86% | - | - | 99.95% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 90.00% | 90.00% | - | - | - | 1828.15 | -182714.86% | - | - | 99.95% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 90.00% | 90.00% | - | - | - | 13646.44 | -1364544.46% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 5003 M3
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 90.00% | 90.00% | - | - | - | 13646.44 | -1364544.46% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 0.00% | 90.00% | 90.00% | - | - | - | 25729.75 | -2572874.56% | - | - | 100.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.09% | 0.09% | 0.00% | 90.00% | 90.00% | - | - | - | 25729.75 | -2572874.56% | - | - | 100.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.53% | 90.00% | 52.47% | - | - | - | 2.40 | -139.79% | - | - | 58.30% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.53% | 90.00% | 52.47% | - | - | - | 2.40 | -139.79% | - | - | 58.30% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.01% | 37.53% | 90.00% | 52.47% | - | - | - | 2.40 | -139.79% | - | - | 58.30% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 90.00% | 90.00% | - | - | - | 4572.59 | -457159.06% | - | - | 99.98% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 90.00% | 90.00% | - | - | - | 4572.59 | -457159.06% | - | - | 99.98% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 90.00% | 90.00% | - | - | - | 4572.59 | -457159.06% | - | - | 99.98% | - | 0.00% |
|
CISTERNA Y CUARTO DE BOMBAS
|
- | - | - | - | - | - | 1.64% | 2.01% | 61.51% | 100.00% | 38.49% | - | - | - | 1.63 | -62.59% | - | - | 38.49% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.04% | 0.08% | 199.36% | 100.00% | -99.36% | - | - | - | 0.50 | 49.84% | - | - | -99.36% | - | 0.00% |
|
('MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 1104.35% | 100.00% | -1004.35% | - | - | - | 0.09 | 90.94% | - | - | -1004.35% | - | 0.00% |
|
EXTRACCION EXCAVACION
|
- | - | - | - | - | - | 0.00% | 0.01% | 1104.35% | 100.00% | -1004.35% | - | - | - | 0.09 | 90.94% | - | - | -1004.35% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.04% | 0.07% | 75.88% | 100.00% | 24.12% | - | - | - | 1.32 | -31.78% | - | - | 24.12% | - | 0.00% |
|
HERRAMIENTAS Y EQUIPO
|
- | - | - | - | - | - | 0.00% | 0.01% | 556.20% | 100.00% | -456.20% | - | - | - | 0.18 | 82.02% | - | - | -456.20% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 4741.65 | -474065.38% | - | - | 99.98% | - | 0.00% |
|
ALQUILER FORMALETA DE METAL Y ACCESORIOS
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 13312.72 | -1331172.38% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.77% | 1.06% | 62.80% | 100.00% | 37.20% | - | - | - | 1.59 | -59.25% | - | - | 37.20% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.24% | 0.26% | 124.60% | 100.00% | -24.60% | - | - | - | 0.80 | 19.75% | - | - | -24.60% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 15492.77 | -1549177.38% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.01% | 500.35% | 100.00% | -400.35% | - | - | - | 0.20 | 80.01% | - | - | -400.35% | - | 0.00% |
|
BAJA PERMEABILIDAD 400 PSI 3/8
|
- | - | - | - | - | - | 0.00% | 0.01% | 3124.41% | 100.00% | -3024.41% | - | - | - | 0.03 | 96.80% | - | - | -3024.41% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4001 M3
|
- | - | - | - | - | - | 0.19% | 0.20% | 0.00% | 100.00% | 100.00% | - | - | - | 61779.23 | -6177823.38% | - | - | 100.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.23% | 0.29% | 73.19% | 100.00% | 26.81% | - | - | - | 1.37 | -36.63% | - | - | 26.81% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.40% | 100.00% | 79.60% | - | - | - | 4.90 | -390.23% | - | - | 79.60% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.01% | 0.02% | 25.12% | 100.00% | 74.88% | - | - | - | 3.98 | -298.01% | - | - | 74.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.01% | 14.67% | 100.00% | 85.33% | - | - | - | 6.82 | -581.67% | - | - | 85.33% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.20% | 0.20% | 81.12% | 100.00% | 18.88% | - | - | - | 1.23 | -23.28% | - | - | 18.88% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.02% | 0.02% | 171.05% | 100.00% | -71.05% | - | - | - | 0.58 | 41.54% | - | - | -71.05% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 7.96% | 100.00% | 92.04% | - | - | - | 12.57 | -1156.66% | - | - | 92.04% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.01% | 19.71% | 100.00% | 80.29% | - | - | - | 5.07 | -407.44% | - | - | 80.29% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.01% | 7.79% | 100.00% | 92.21% | - | - | - | 12.84 | -1183.58% | - | - | 92.21% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.09% | 0.12% | 65.90% | 100.00% | 34.10% | - | - | - | 1.52 | -51.74% | - | - | 34.10% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.01% | 279.17% | 100.00% | -179.17% | - | - | - | 0.36 | 64.18% | - | - | -179.17% | - | 0.00% |
|
TABLON DE 2" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.01% | 249.58% | 100.00% | -149.58% | - | - | - | 0.40 | 59.93% | - | - | -149.58% | - | 0.00% |
|
REGLA DE 2" X 2" X 10'
|
- | - | - | - | - | - | 0.05% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 18163.19 | -1816219.38% | - | - | 99.99% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.04% | 0.04% | 70.68% | 100.00% | 29.32% | - | - | - | 1.41 | -41.48% | - | - | 29.32% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.02% | 0.06% | 48.41% | 100.00% | 51.59% | - | - | - | 2.07 | -106.56% | - | - | 51.59% | - | 0.00% |
|
LEVANTA MUROS 50 KG
|
- | - | - | - | - | - | 0.00% | 0.01% | 7.41% | 100.00% | 92.59% | - | - | - | 13.50 | -1250.24% | - | - | 92.59% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.01% | 4.95% | 100.00% | 95.05% | - | - | - | 20.21 | -1921.34% | - | - | 95.05% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.01% | 11.18% | 100.00% | 88.82% | - | - | - | 8.94 | -794.44% | - | - | 88.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.02% | 0.03% | 97.14% | 100.00% | 2.86% | - | - | - | 1.03 | -2.94% | - | - | 2.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.03% | 39.46% | 100.00% | 60.54% | - | - | - | 2.53 | -153.41% | - | - | 60.54% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2867.81 | -286681.38% | - | - | 99.97% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.01% | 66.61% | 100.00% | 33.39% | - | - | - | 1.50 | -50.12% | - | - | 33.39% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.01% | 49.88% | 100.00% | 50.12% | - | - | - | 2.00 | -100.50% | - | - | 50.12% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.02% | 16.42% | 100.00% | 83.58% | - | - | - | 6.09 | -508.83% | - | - | 83.58% | - | 0.00% |
|
BLOCK "U" DE 14X19X39 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.01% | 2.24% | 100.00% | 97.76% | - | - | - | 44.64 | -4363.81% | - | - | 97.76% | - | 0.00% |
|
BLOCK DE 14X19X39 - 66KG/CM2
|
- | - | - | - | - | - | 0.00% | 0.01% | 30.61% | 100.00% | 69.39% | - | - | - | 3.27 | -226.69% | - | - | 69.39% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 8.22% | 100.00% | 91.78% | - | - | - | 12.17 | -1116.88% | - | - | 91.78% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.01% | 8.22% | 100.00% | 91.78% | - | - | - | 12.17 | -1116.88% | - | - | 91.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.19% | 100.00% | 99.81% | - | - | - | 540.22 | -53922.23% | - | - | 99.81% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.19% | 100.00% | 99.81% | - | - | - | 540.22 | -53922.23% | - | - | 99.81% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.10% | 100.00% | 99.90% | - | - | - | 960.40 | -95939.52% | - | - | 99.90% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.10% | 100.00% | 99.90% | - | - | - | 960.40 | -95939.52% | - | - | 99.90% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2853.39 | -285239.38% | - | - | 99.96% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2853.39 | -285239.38% | - | - | 99.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12710.63 | -1270963.38% | - | - | 99.99% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.03% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12710.63 | -1270963.38% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.16% | 0.20% | 0.00% | 100.00% | 100.00% | - | - | - | 63136.65 | -6313564.91% | - | - | 100.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3339.08 | -333808.38% | - | - | 99.97% | - | 0.00% |
|
AQUASTOP
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 4947.14 | -494614.38% | - | - | 99.98% | - | 0.00% |
|
EMULSION ASFALTICA
|
- | - | - | - | - | - | 0.01% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6251.97 | -625097.38% | - | - | 99.98% | - | 0.00% |
|
SIKATOP SEAL 107, KIT 16.3 KG
|
- | - | - | - | - | - | 0.09% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 30645.27 | -3064427.38% | - | - | 100.00% | - | 0.00% |
|
SIKAGARD 62, KIT 22 KG
|
- | - | - | - | - | - | 0.05% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 17953.17 | -1795217.38% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.76% | 0.78% | 50.34% | 100.00% | 49.66% | - | - | - | 1.99 | -98.66% | - | - | 49.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.75% | 0.76% | 52.00% | 100.00% | 48.00% | - | - | - | 1.92 | -92.31% | - | - | 48.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.01% | 933.28% | 100.00% | -833.28% | - | - | - | 0.11 | 89.29% | - | - | -833.28% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.67% | 0.66% | 47.02% | 100.00% | 52.98% | - | - | - | 2.13 | -112.66% | - | - | 52.98% | - | 0.00% |
|
SUBCONTRATO DE ESCALONES
|
- | - | - | - | - | - | 0.04% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 14952.37 | -1495137.38% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 13635.54 | -1363454.38% | - | - | 99.99% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 7852.37 | -785137.38% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO TAPADERA HIERRO FUNDIDO 0.40CM
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 7852.37 | -785137.38% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.06% | 0.08% | 27.44% | 100.00% | 72.56% | - | - | - | 3.64 | -264.37% | - | - | 72.56% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.06% | 0.08% | 27.44% | 100.00% | 72.56% | - | - | - | 3.64 | -264.37% | - | - | 72.56% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.06% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21939.57 | -2193857.38% | - | - | 100.00% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.01% | 238.54% | 100.00% | -138.54% | - | - | - | 0.42 | 58.08% | - | - | -138.54% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.54% | 100.00% | 79.46% | - | - | - | 4.87 | -386.84% | - | - | 79.46% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.54% | 100.00% | 79.46% | - | - | - | 4.87 | -386.84% | - | - | 79.46% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.01% | 20.54% | 100.00% | 79.46% | - | - | - | 4.87 | -386.84% | - | - | 79.46% | - | 0.00% |
|
MOVIMIENTO DE TIERRAS
|
- | - | - | - | - | - | 4.53% | 5.90% | 55.14% | 100.00% | 44.86% | - | - | - | 1.81 | -81.36% | - | - | 44.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 4.40% | 4.82% | 95.96% | 100.00% | 4.04% | - | - | - | 1.04 | -4.21% | - | - | 4.04% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 4.40% | 4.63% | 108.69% | 100.00% | -8.69% | - | - | - | 0.92 | 8.00% | - | - | -8.69% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 4.33% | 4.38% | 109.13% | 100.00% | -9.13% | - | - | - | 0.92 | 8.37% | - | - | -9.13% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.06% | 0.25% | 101.07% | 100.00% | -1.07% | - | - | - | 0.99 | 1.06% | - | - | -1.07% | - | 0.00% |
|
('SUB CONTRATO MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.00% | 0.19% | -214.47% | 100.00% | 314.47% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO SERVICIOS DE TOPOGRAFIA
|
- | - | - | - | - | - | 0.00% | 0.19% | -214.47% | 100.00% | 314.47% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.19% | -138.25% | 100.00% | 238.25% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.19% | -138.25% | 100.00% | 238.25% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
VIAJES DE SELECTO
|
- | - | - | - | - | - | 0.00% | 0.19% | -138.25% | 100.00% | 238.25% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.19% | -226.89% | 100.00% | 326.89% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.19% | -226.89% | 100.00% | 326.89% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.19% | -226.89% | 100.00% | 326.89% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.13% | 0.32% | -142.20% | 100.00% | 242.20% | - | - | - | 98966.51 | -9896550.62% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.13% | 0.32% | -142.20% | 100.00% | 242.20% | - | - | - | 98966.51 | -9896550.62% | - | - | 100.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.13% | 0.32% | -142.20% | 100.00% | 242.20% | - | - | - | 98966.51 | -9896550.62% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.38% | -61.12% | 100.00% | 161.12% | - | - | - | 119137.53 | -11913653.25% | - | - | 100.00% | - | 0.00% |
|
('MOVIMIENTO DE TIERRA',)
|
- | - | - | - | - | - | 0.00% | 0.38% | -61.12% | 100.00% | 161.12% | - | - | - | 119137.53 | -11913653.25% | - | - | 100.00% | - | 0.00% |
|
EXTRACCION EXCAVACION
|
- | - | - | - | - | - | 0.00% | 0.19% | -203.46% | 100.00% | 303.46% | - | - | - | 59568.77 | -5956776.62% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO MOVIMIENTO DE TIERRA
|
- | - | - | - | - | - | 0.00% | 0.19% | 81.21% | 100.00% | 18.79% | - | - | - | 1.23 | -23.14% | - | - | 18.79% | - | 0.00% |
|
SE?ALIZACION VIAL
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.05% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.05% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SEÑALIZACION VIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SEGURIDAD INDUSTRIAL',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CERCA PLASTICA LIMITACION NARANJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 24
|
- | - | - | - | - | - | 1.30% | 1.25% | 100.03% | 100.00% | -0.03% | - | - | - | 1.00 | 0.03% | - | - | -0.03% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 128.74% | 100.00% | -28.74% | - | - | - | 0.78 | 22.32% | - | - | -28.74% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 252.18% | 100.00% | -152.18% | - | - | - | 0.40 | 60.35% | - | - | -152.18% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 410.18% | 100.00% | -310.18% | - | - | - | 0.24 | 75.62% | - | - | -310.18% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1082466.67% | 100.00% | -1082366.67% | - | - | - | 0.00 | 99.99% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 573.61% | 100.00% | -473.61% | - | - | - | 0.17 | 82.57% | - | - | -473.61% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.02% | 100.00% | -39.02% | - | - | - | 0.72 | 28.07% | - | - | -39.02% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO FLUIDO 3003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.94% | 100.00% | -7.94% | - | - | - | 0.93 | 7.35% | - | - | -7.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 387.24% | 100.00% | -287.24% | - | - | - | 0.26 | 74.18% | - | - | -287.24% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 164.95% | 100.00% | -64.95% | - | - | - | 0.61 | 39.37% | - | - | -64.95% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 137.99% | 100.00% | -37.99% | - | - | - | 0.72 | 27.53% | - | - | -37.99% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.33% | 100.00% | 59.67% | - | - | - | 2.48 | -147.94% | - | - | 59.67% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 333.15% | 100.00% | -233.15% | - | - | - | 0.30 | 69.98% | - | - | -233.15% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 256.54% | 100.00% | -156.54% | - | - | - | 0.39 | 61.02% | - | - | -156.54% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 276.19% | 100.00% | -176.19% | - | - | - | 0.36 | 63.79% | - | - | -176.19% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 278.20% | 100.00% | -178.20% | - | - | - | 0.36 | 64.06% | - | - | -178.20% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.67% | 100.00% | 24.33% | - | - | - | 1.32 | -32.16% | - | - | 24.33% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.67% | 100.00% | 24.33% | - | - | - | 1.32 | -32.16% | - | - | 24.33% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 64.71% | 100.00% | 35.29% | - | - | - | 1.55 | -54.55% | - | - | 35.29% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 105.24% | 100.00% | -5.24% | - | - | - | 0.95 | 4.98% | - | - | -5.24% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 149.26% | 100.00% | -49.26% | - | - | - | 0.67 | 33.00% | - | - | -49.26% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 218.44% | 100.00% | -118.44% | - | - | - | 0.46 | 54.22% | - | - | -118.44% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE BOMBEO CONVENCIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION CON PLUMA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 109.17% | 100.00% | -9.17% | - | - | - | 0.92 | 8.40% | - | - | -9.17% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.39% | 100.00% | 53.61% | - | - | - | 2.16 | -115.56% | - | - | 53.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.99% | 100.00% | 4.01% | - | - | - | 1.04 | -4.17% | - | - | 4.01% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.00% | 100.00% | 35.00% | - | - | - | 1.54 | -53.86% | - | - | 35.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.00% | 100.00% | 35.00% | - | - | - | 1.54 | -53.86% | - | - | 35.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 77.57% | 100.00% | 22.43% | - | - | - | 1.29 | -28.92% | - | - | 22.43% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 104.10% | 100.00% | -4.10% | - | - | - | 0.96 | 3.93% | - | - | -4.10% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 104.10% | 100.00% | -4.10% | - | - | - | 0.96 | 3.93% | - | - | -4.10% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 34.49% | 100.00% | 65.51% | - | - | - | 2.90 | -189.92% | - | - | 65.51% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2074.17% | 100.00% | -1974.17% | - | - | - | 0.05 | 95.18% | - | - | -1974.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.15% | 100.00% | -135.15% | - | - | - | 0.43 | 57.47% | - | - | -135.15% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.15% | 100.00% | -135.15% | - | - | - | 0.43 | 57.47% | - | - | -135.15% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.35% | 100.00% | -27.35% | - | - | - | 0.79 | 21.48% | - | - | -27.35% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 215.05% | 100.00% | -115.05% | - | - | - | 0.47 | 53.50% | - | - | -115.05% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 116.33% | 100.00% | -16.33% | - | - | - | 0.86 | 14.03% | - | - | -16.33% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 71.88 | -7088.00% | - | - | 98.61% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.57% | 100.00% | 95.43% | - | - | - | 21.88 | -2087.82% | - | - | 95.43% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.45% | 100.00% | 97.55% | - | - | - | 40.89 | -3989.44% | - | - | 97.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 73.61% | 100.00% | 26.39% | - | - | - | 1.36 | -35.86% | - | - | 26.39% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 101.41% | 100.00% | -1.41% | - | - | - | 0.99 | 1.39% | - | - | -1.41% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 67756.36% | 100.00% | -67656.36% | - | - | - | 0.00 | 99.85% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5172.41% | 100.00% | -5072.41% | - | - | - | 0.02 | 98.07% | - | - | -5072.41% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.31% | 100.00% | -23.31% | - | - | - | 0.81 | 18.91% | - | - | -23.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 121.61% | 100.00% | -21.61% | - | - | - | 0.82 | 17.77% | - | - | -21.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.12% | 100.00% | 11.88% | - | - | - | 1.13 | -13.48% | - | - | 11.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.42% | 100.00% | 27.58% | - | - | - | 1.38 | -38.08% | - | - | 27.58% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 19.39% | 100.00% | 80.61% | - | - | - | 5.16 | -415.73% | - | - | 80.61% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 169.41% | 100.00% | -69.41% | - | - | - | 0.59 | 40.97% | - | - | -69.41% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.27% | 100.00% | -109.27% | - | - | - | 0.48 | 52.21% | - | - | -109.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 97.73% | 100.00% | 2.27% | - | - | - | 1.02 | -2.32% | - | - | 2.27% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 184.69% | 100.00% | -84.69% | - | - | - | 0.54 | 45.86% | - | - | -84.69% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 741.64% | 100.00% | -641.64% | - | - | - | 0.13 | 86.52% | - | - | -641.64% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 96.41% | 100.00% | 3.59% | - | - | - | 1.04 | -3.73% | - | - | 3.59% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 54.60% | 100.00% | 45.40% | - | - | - | 1.83 | -83.16% | - | - | 45.40% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO M004 PARA VIVIENDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.82% | 100.00% | 56.18% | - | - | - | 2.28 | -128.20% | - | - | 56.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.82% | 100.00% | 56.18% | - | - | - | 2.28 | -128.20% | - | - | 56.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.18% | 100.00% | 54.82% | - | - | - | 2.21 | -121.36% | - | - | 54.82% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 83.36% | 100.00% | 16.64% | - | - | - | 1.20 | -19.96% | - | - | 16.64% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 456.68% | 100.00% | -356.68% | - | - | - | 0.22 | 78.10% | - | - | -356.68% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 427.92% | 100.00% | -327.92% | - | - | - | 0.23 | 76.63% | - | - | -327.92% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 427.92% | 100.00% | -327.92% | - | - | - | 0.23 | 76.63% | - | - | -327.92% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SQUEEGEE LIMPIADOR DE VIDRIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 109.67% | 100.00% | -9.67% | - | - | - | 0.91 | 8.81% | - | - | -9.67% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.88% | 100.00% | 5.12% | - | - | - | 1.05 | -5.39% | - | - | 5.12% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.35% | 100.00% | 99.65% | - | - | - | 289.12 | -28811.52% | - | - | 99.65% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.35% | 100.00% | 99.65% | - | - | - | 289.12 | -28811.52% | - | - | 99.65% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.05% | 100.00% | -4.05% | - | - | - | 0.96 | 3.89% | - | - | -4.05% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.05% | 100.00% | -4.05% | - | - | - | 0.96 | 3.89% | - | - | -4.05% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.05% | 100.00% | -4.05% | - | - | - | 0.96 | 3.89% | - | - | -4.05% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.05% | 100.00% | -4.05% | - | - | - | 0.96 | 3.89% | - | - | -4.05% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 99.36% | 100.00% | 0.64% | - | - | - | 1.01 | -0.64% | - | - | 0.64% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 128.96% | 100.00% | -28.96% | - | - | - | 0.78 | 22.46% | - | - | -28.96% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.72% | 100.00% | -7.72% | - | - | - | 0.93 | 7.17% | - | - | -7.72% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.72% | 100.00% | -7.72% | - | - | - | 0.93 | 7.17% | - | - | -7.72% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 83.64% | 100.00% | 16.36% | - | - | - | 1.20 | -19.57% | - | - | 16.36% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 83.45% | 100.00% | 16.55% | - | - | - | 1.20 | -19.84% | - | - | 16.55% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.86% | 100.00% | -17.86% | - | - | - | 0.85 | 15.16% | - | - | -17.86% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 93.49% | 100.00% | 6.51% | - | - | - | 1.07 | -6.96% | - | - | 6.51% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 52.42% | 100.00% | 47.58% | - | - | - | 1.91 | -90.77% | - | - | 47.58% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 10.74% | 100.00% | 89.26% | - | - | - | 9.31 | -830.72% | - | - | 89.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 30.96% | 100.00% | 69.04% | - | - | - | 3.23 | -223.01% | - | - | 69.04% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 26.85% | 100.00% | 73.15% | - | - | - | 3.72 | -272.39% | - | - | 73.15% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.22% | 100.00% | 37.78% | - | - | - | 1.61 | -60.71% | - | - | 37.78% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.11% | 100.00% | 44.89% | - | - | - | 1.81 | -81.47% | - | - | 44.89% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.38% | 100.00% | 95.62% | - | - | - | 22.81 | -2181.49% | - | - | 95.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.34% | 100.00% | 95.66% | - | - | - | 23.02 | -2202.22% | - | - | 95.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 9
|
- | - | - | - | - | - | 1.30% | 1.25% | 96.32% | 96.48% | 0.16% | - | - | - | 1.00 | -0.17% | - | - | 0.17% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 127.03% | 93.05% | -33.98% | - | - | - | 0.73 | 26.75% | - | - | -36.52% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 642.10% | 100.00% | -542.10% | - | - | - | 0.16 | 84.43% | - | - | -542.10% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 627.16% | 100.00% | -527.16% | - | - | - | 0.16 | 84.06% | - | - | -527.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 627.16% | 100.00% | -527.16% | - | - | - | 0.16 | 84.06% | - | - | -527.16% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 331.96% | 100.00% | -231.96% | - | - | - | 0.30 | 69.88% | - | - | -231.96% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 205.27% | 100.00% | -105.27% | - | - | - | 0.49 | 51.28% | - | - | -105.27% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 202.96% | 100.00% | -102.96% | - | - | - | 0.49 | 50.73% | - | - | -102.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 151.98% | 100.00% | -51.98% | - | - | - | 0.66 | 34.20% | - | - | -51.98% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 117.69% | 100.00% | -17.69% | - | - | - | 0.85 | 15.03% | - | - | -17.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.71% | 100.00% | -72.71% | - | - | - | 0.58 | 42.10% | - | - | -72.71% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 152.45% | 100.00% | -52.45% | - | - | - | 0.66 | 34.40% | - | - | -52.45% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 152.45% | 100.00% | -52.45% | - | - | - | 0.66 | 34.40% | - | - | -52.45% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 88.46% | 100.00% | 11.54% | - | - | - | 1.13 | -13.04% | - | - | 11.54% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 88.46% | 100.00% | 11.54% | - | - | - | 1.13 | -13.04% | - | - | 11.54% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1950.66 | -194966.00% | - | - | 99.95% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 106.66% | 100.00% | -6.66% | - | - | - | 0.94 | 6.24% | - | - | -6.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.05% | 100.00% | 18.95% | - | - | - | 1.23 | -23.38% | - | - | 18.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 55.07% | 100.00% | 44.93% | - | - | - | 1.82 | -81.60% | - | - | 44.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 27.52% | 100.00% | 72.48% | - | - | - | 3.63 | -263.31% | - | - | 72.48% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 79.31% | 100.00% | 20.69% | - | - | - | 1.26 | -26.09% | - | - | 20.69% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 75.20% | 100.00% | 24.80% | - | - | - | 1.33 | -32.97% | - | - | 24.80% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1350.00 | -134900.00% | - | - | 99.93% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.95% | 100.00% | -154.95% | - | - | - | 0.39 | 60.78% | - | - | -154.95% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 406.92% | 100.00% | -306.92% | - | - | - | 0.25 | 75.43% | - | - | -306.92% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 257.12% | 0.00% | -257.12% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL LATEX BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA MOUNTAIN FULL WEATHER CUBETA MATE COLOR BLANCO DE LINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA PROCOAT CUBETA MATE COLOR BLANCO DE LINEA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 0.00% | -159.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 159.52% | 0.00% | -159.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 123.52% | 0.00% | -123.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 90.18% | 100.00% | 9.82% | - | - | - | 1.11 | -10.89% | - | - | 9.82% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 145.62% | 100.00% | -45.62% | - | - | - | 0.69 | 31.33% | - | - | -45.62% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 195.27% | 100.00% | -95.27% | - | - | - | 0.51 | 48.79% | - | - | -95.27% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 195.27% | 100.00% | -95.27% | - | - | - | 0.51 | 48.79% | - | - | -95.27% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 64.97% | 100.00% | 35.03% | - | - | - | 1.54 | -53.92% | - | - | 35.03% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6524.98% | 100.00% | -6424.98% | - | - | - | 0.02 | 98.47% | - | - | -6424.98% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 162.20% | 100.00% | -62.20% | - | - | - | 0.62 | 38.35% | - | - | -62.20% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 43.51% | 100.00% | 56.49% | - | - | - | 2.30 | -129.85% | - | - | 56.49% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4920.52% | 100.00% | -4820.52% | - | - | - | 0.02 | 97.97% | - | - | -4820.52% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 52.37% | 100.00% | 47.63% | - | - | - | 1.91 | -90.95% | - | - | 47.63% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 22.61% | 100.00% | 77.39% | - | - | - | 4.42 | -342.37% | - | - | 77.39% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.93% | 100.00% | 91.07% | - | - | - | 11.20 | -1020.21% | - | - | 91.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1982.45% | 100.00% | -1882.45% | - | - | - | 0.05 | 94.96% | - | - | -1882.45% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1025.07% | 100.00% | -925.07% | - | - | - | 0.10 | 90.24% | - | - | -925.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.36% | 100.00% | 83.64% | - | - | - | 6.11 | -511.08% | - | - | 83.64% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 5/8 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 72.55% | 100.00% | 27.45% | - | - | - | 1.38 | -37.83% | - | - | 27.45% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 102.33% | 100.00% | -2.33% | - | - | - | 0.98 | 2.27% | - | - | -2.33% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 102.33% | 100.00% | -2.33% | - | - | - | 0.98 | 2.27% | - | - | -2.33% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 50.13% | 100.00% | 49.87% | - | - | - | 1.99 | -99.48% | - | - | 49.87% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 99.17% | 100.00% | 0.83% | - | - | - | 1.01 | -0.84% | - | - | 0.83% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.06% | 100.00% | -20.06% | - | - | - | 0.83 | 16.71% | - | - | -20.06% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.53% | 100.00% | 73.47% | - | - | - | 3.77 | -276.87% | - | - | 73.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 16308.96 | -1630796.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 72.46% | 100.00% | 27.54% | - | - | - | 1.38 | -38.01% | - | - | 27.54% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 99.88% | 100.00% | 0.12% | - | - | - | 1.00 | -0.12% | - | - | 0.12% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7828.41% | 100.00% | -7728.41% | - | - | - | 0.01 | 98.72% | - | - | -7728.41% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 239.35% | 100.00% | -139.35% | - | - | - | 0.42 | 58.22% | - | - | -139.35% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 126.09% | 100.00% | -26.09% | - | - | - | 0.79 | 20.69% | - | - | -26.09% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.15% | 100.00% | 10.85% | - | - | - | 1.12 | -12.17% | - | - | 10.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.33% | 100.00% | 27.67% | - | - | - | 1.38 | -38.26% | - | - | 27.67% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.29% | 100.00% | -136.29% | - | - | - | 0.42 | 57.68% | - | - | -136.29% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 354.24% | 100.00% | -254.24% | - | - | - | 0.28 | 71.77% | - | - | -254.24% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.82% | 100.00% | -83.82% | - | - | - | 0.54 | 45.60% | - | - | -83.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 903.31% | 100.00% | -803.31% | - | - | - | 0.11 | 88.93% | - | - | -803.31% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 90.19% | 100.00% | 9.81% | - | - | - | 1.11 | -10.88% | - | - | 9.81% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 76.13% | 100.00% | 23.87% | - | - | - | 1.31 | -31.35% | - | - | 23.87% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 63.98% | 100.00% | 36.02% | - | - | - | 1.56 | -56.31% | - | - | 36.02% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.15% | 100.00% | 19.85% | - | - | - | 1.25 | -24.76% | - | - | 19.85% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.15% | 100.00% | 19.85% | - | - | - | 1.25 | -24.76% | - | - | 19.85% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.01% | 100.00% | 43.99% | - | - | - | 1.79 | -78.55% | - | - | 43.99% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.58% | 100.00% | -6.58% | - | - | - | 0.94 | 6.17% | - | - | -6.58% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.93% | 100.00% | 39.07% | - | - | - | 1.64 | -64.13% | - | - | 39.07% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.38% | 100.00% | 1.62% | - | - | - | 1.02 | -1.64% | - | - | 1.62% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.44% | - | - | 16.97% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 17.55% | 100.00% | 82.45% | - | - | - | 5.70 | -469.87% | - | - | 82.45% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 53.14% | 93.64% | 40.50% | - | - | - | 1.76 | -76.23% | - | - | 43.26% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 88.00% | -12.13% | - | - | - | 0.88 | 12.12% | - | - | -13.79% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 88.00% | -15.14% | - | - | - | 0.85 | 14.68% | - | - | -17.20% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 100.00% | 99.81% | - | - | - | 521.99 | -52099.20% | - | - | 99.81% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 39
|
- | - | - | - | - | - | 1.30% | 1.30% | 91.91% | 92.43% | 0.52% | - | - | - | 1.01 | -0.57% | - | - | 0.56% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.46% | 124.28% | 85.84% | -38.44% | - | - | - | 0.69 | 30.93% | - | - | -44.78% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 207.00% | 100.00% | -107.00% | - | - | - | 0.48 | 51.69% | - | - | -107.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 205.55% | 100.00% | -105.55% | - | - | - | 0.49 | 51.35% | - | - | -105.55% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 111.01% | 100.00% | -11.01% | - | - | - | 0.90 | 9.92% | - | - | -11.01% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 103.04% | 100.00% | -3.04% | - | - | - | 0.97 | 2.95% | - | - | -3.04% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 156.70% | 100.00% | -56.70% | - | - | - | 0.64 | 36.19% | - | - | -56.70% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 156.70% | 100.00% | -56.70% | - | - | - | 0.64 | 36.19% | - | - | -56.70% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 156.70% | 100.00% | -56.70% | - | - | - | 0.64 | 36.19% | - | - | -56.70% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 149.06% | 100.00% | -49.06% | - | - | - | 0.67 | 32.91% | - | - | -49.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 193.23% | 100.00% | -93.23% | - | - | - | 0.52 | 48.25% | - | - | -93.23% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 125.60% | 100.00% | -25.60% | - | - | - | 0.80 | 20.38% | - | - | -25.60% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 125.60% | 100.00% | -25.60% | - | - | - | 0.80 | 20.38% | - | - | -25.60% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 60.53% | 100.00% | 39.47% | - | - | - | 1.65 | -65.21% | - | - | 39.47% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 59.63% | 100.00% | 40.37% | - | - | - | 1.68 | -67.71% | - | - | 40.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 59.63% | 100.00% | 40.37% | - | - | - | 1.68 | -67.71% | - | - | 40.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 41.63% | 100.00% | 58.37% | - | - | - | 2.40 | -140.22% | - | - | 58.37% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.03% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.03% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.03% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.03% | 56.10% | 100.00% | 43.90% | - | - | - | 1.78 | -78.27% | - | - | 43.90% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 431.40% | 0.00% | -431.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 431.40% | 0.00% | -431.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 431.40% | 0.00% | -431.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 19.35% | 0.00% | -19.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 55.75% | 0.00% | -55.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 51.64% | 0.00% | -51.64% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 83.81% | 100.00% | 16.19% | - | - | - | 1.19 | -19.31% | - | - | 16.19% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 99.94% | 100.00% | 0.06% | - | - | - | 1.00 | -0.06% | - | - | 0.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 116.18% | 100.00% | -16.18% | - | - | - | 0.86 | 13.93% | - | - | -16.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 116.18% | 100.00% | -16.18% | - | - | - | 0.86 | 13.93% | - | - | -16.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 194800.19% | 100.00% | -194700.19% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3668.67 | -366767.13% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 54685.07% | 100.00% | -54585.07% | - | - | - | 0.00 | 99.82% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1520.08 | -151908.13% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24634.10 | -2463310.13% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 74.52% | 100.00% | 25.48% | - | - | - | 1.34 | -34.19% | - | - | 25.48% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1216.00% | 100.00% | -1116.00% | - | - | - | 0.08 | 91.78% | - | - | -1116.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1216.00% | 100.00% | -1116.00% | - | - | - | 0.08 | 91.78% | - | - | -1116.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 261.40% | 100.00% | -161.40% | - | - | - | 0.38 | 61.74% | - | - | -161.40% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 37.36 | -3636.13% | - | - | 97.32% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 963.94% | 100.00% | -863.94% | - | - | - | 0.10 | 89.63% | - | - | -863.94% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 205.55% | 100.00% | -105.55% | - | - | - | 0.49 | 51.35% | - | - | -105.55% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 97.49 | -9649.13% | - | - | 98.97% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 79.08% | 100.00% | 20.92% | - | - | - | 1.26 | -26.45% | - | - | 20.92% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4617.51% | 100.00% | -4517.51% | - | - | - | 0.02 | 97.83% | - | - | -4517.51% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 50.65% | 100.00% | 49.35% | - | - | - | 1.97 | -97.45% | - | - | 49.35% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.90% | 100.00% | 83.10% | - | - | - | 5.92 | -491.78% | - | - | 83.10% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.14 | -2414.13% | - | - | 96.02% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 3858.49% | 100.00% | -3758.49% | - | - | - | 0.03 | 97.41% | - | - | -3758.49% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1100.59% | 100.00% | -1000.59% | - | - | - | 0.09 | 90.91% | - | - | -1000.59% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 141.57% | 100.00% | -41.57% | - | - | - | 0.71 | 29.36% | - | - | -41.57% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 113.29% | 100.00% | -13.29% | - | - | - | 0.88 | 11.73% | - | - | -13.29% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 415.91% | 100.00% | -315.91% | - | - | - | 0.24 | 75.96% | - | - | -315.91% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1743.99 | -174299.13% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7.21% | 100.00% | 92.79% | - | - | - | 13.86 | -1286.46% | - | - | 92.79% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.98% | 100.00% | 62.02% | - | - | - | 2.63 | -163.28% | - | - | 62.02% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 876.76 | -87576.13% | - | - | 99.89% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 441.97% | 100.00% | -341.97% | - | - | - | 0.23 | 77.37% | - | - | -341.97% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 20.48 | -1948.13% | - | - | 95.12% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.73 | -2273.13% | - | - | 95.79% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.73 | -2273.13% | - | - | 95.79% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 53.73 | -5273.26% | - | - | 98.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 33.08 | -3208.13% | - | - | 96.98% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 20.65 | -1965.13% | - | - | 95.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 694.69 | -69369.13% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 694.69 | -69369.13% | - | - | 99.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1679.88 | -167888.13% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1679.88 | -167888.13% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9309.46 | -930846.26% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 94.57 | -9357.13% | - | - | 98.94% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9214.89 | -921389.13% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 169.88 | -16888.13% | - | - | 99.41% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 169.88 | -16888.13% | - | - | 99.41% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 169.88 | -16888.13% | - | - | 99.41% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 99.63% | 100.00% | 0.37% | - | - | - | 1.00 | -0.37% | - | - | 0.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 154.89% | 100.00% | -54.89% | - | - | - | 0.65 | 35.44% | - | - | -54.89% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16551.11% | 100.00% | -16451.11% | - | - | - | 0.01 | 99.40% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 367.20% | 100.00% | -267.20% | - | - | - | 0.27 | 72.77% | - | - | -267.20% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 630.74% | 100.00% | -530.74% | - | - | - | 0.16 | 84.15% | - | - | -530.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 178.75% | 100.00% | -78.75% | - | - | - | 0.56 | 44.06% | - | - | -78.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 38.39% | 100.00% | 61.61% | - | - | - | 2.60 | -160.47% | - | - | 61.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 38.39% | 100.00% | 61.61% | - | - | - | 2.60 | -160.47% | - | - | 61.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 78.63% | 100.00% | 21.37% | - | - | - | 1.27 | -27.18% | - | - | 21.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 147.19% | 100.00% | -47.19% | - | - | - | 0.68 | 32.06% | - | - | -47.19% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 213.89% | 100.00% | -113.89% | - | - | - | 0.47 | 53.25% | - | - | -113.89% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 111.91% | 100.00% | -11.91% | - | - | - | 0.89 | 10.64% | - | - | -11.91% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.14% | - | - | 29.15% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.34% | 100.00% | -0.34% | - | - | - | 1.00 | 0.34% | - | - | -0.34% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 92.79% | 100.00% | 7.21% | - | - | - | 1.08 | -7.77% | - | - | 7.21% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 6.80% | 100.00% | 93.20% | - | - | - | 14.70 | -1369.75% | - | - | 93.20% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 6.80% | 100.00% | 93.20% | - | - | - | 14.70 | -1369.75% | - | - | 93.20% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 60.59% | 100.00% | 39.41% | - | - | - | 1.65 | -65.04% | - | - | 39.41% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 110.60% | 100.00% | -10.60% | - | - | - | 0.90 | 9.58% | - | - | -10.60% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 51525.45% | 100.00% | -51425.45% | - | - | - | 0.00 | 99.81% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 134.51% | 100.00% | -34.51% | - | - | - | 0.74 | 25.66% | - | - | -34.51% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.05% | 100.00% | 27.95% | - | - | - | 1.39 | -38.80% | - | - | 27.95% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 287.01% | 100.00% | -187.01% | - | - | - | 0.35 | 65.16% | - | - | -187.01% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 267.12% | 100.00% | -167.12% | - | - | - | 0.37 | 62.56% | - | - | -167.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 168.34% | 100.00% | -68.34% | - | - | - | 0.59 | 40.59% | - | - | -68.34% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 888.13% | 100.00% | -788.13% | - | - | - | 0.11 | 88.74% | - | - | -788.13% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 122.34% | 100.00% | -22.34% | - | - | - | 0.82 | 18.26% | - | - | -22.34% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.24% | 50.38% | 86.05% | 35.67% | - | - | - | 1.71 | -70.82% | - | - | 41.46% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 97.96% | 88.00% | -9.96% | - | - | - | 0.90 | 10.17% | - | - | -11.32% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.89% | 88.00% | -13.89% | - | - | - | 0.86 | 13.63% | - | - | -15.78% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.05% | 88.00% | -147.05% | - | - | - | 0.37 | 62.56% | - | - | -167.10% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.42% | 88.00% | -154.42% | - | - | - | 0.36 | 63.70% | - | - | -175.48% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 227.68% | 88.00% | -139.68% | - | - | - | 0.39 | 61.35% | - | - | -158.72% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 98.86% | 88.00% | -10.86% | - | - | - | 0.89 | 10.99% | - | - | -12.35% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.12% | 98.86% | 88.00% | -10.86% | - | - | - | 0.89 | 10.99% | - | - | -12.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1310.26 | -130925.84% | - | - | 99.92% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1310.26 | -130925.84% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1310.26 | -130925.84% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.12% | 0.15% | 84.00% | 83.85% | - | - | - | 564.28 | -56328.10% | - | - | 99.82% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.57% | 84.00% | 82.43% | - | - | - | 53.52 | -5251.75% | - | - | 98.13% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.33% | 84.00% | 79.67% | - | - | - | 19.39 | -1838.81% | - | - | 94.84% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.33% | 84.00% | 79.67% | - | - | - | 19.39 | -1838.81% | - | - | 94.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 84.00% | 84.00% | - | - | - | 1858.35 | -185734.60% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.01% | 0.00% | 84.00% | 84.00% | - | - | - | 1858.35 | -185734.60% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 0.00% | 84.00% | 84.00% | - | - | - | 27811.07 | -2781007.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 0.00% | 84.00% | 84.00% | - | - | - | 27811.07 | -2781007.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.11% | 0.00% | 84.00% | 84.00% | - | - | - | 27811.07 | -2781007.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 11
|
- | - | - | - | - | - | 1.30% | 1.25% | 97.48% | 98.87% | 1.39% | - | - | - | 1.01 | -1.43% | - | - | 1.41% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 116.32% | 100.00% | -16.32% | - | - | - | 0.86 | 14.03% | - | - | -16.32% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 355.66% | 100.00% | -255.66% | - | - | - | 0.28 | 71.88% | - | - | -255.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 355.66% | 100.00% | -255.66% | - | - | - | 0.28 | 71.88% | - | - | -255.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 355.66% | 100.00% | -255.66% | - | - | - | 0.28 | 71.88% | - | - | -255.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 203.84% | 100.00% | -103.84% | - | - | - | 0.49 | 50.94% | - | - | -103.84% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 202.96% | 100.00% | -102.96% | - | - | - | 0.49 | 50.73% | - | - | -102.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 108.42% | 100.00% | -8.42% | - | - | - | 0.92 | 7.77% | - | - | -8.42% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 174.57% | 100.00% | -74.57% | - | - | - | 0.57 | 42.72% | - | - | -74.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 85.75% | 100.00% | 14.25% | - | - | - | 1.17 | -16.62% | - | - | 14.25% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 49.75% | 100.00% | 50.25% | - | - | - | 2.01 | -100.99% | - | - | 50.25% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA MOUNTAIN FULL WEATHER CUBETA MATE COLOR BLANCO DE LINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA PROCOAT CUBETA MATE COLOR BLANCO DE LINEA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 111.69% | 100.00% | -11.69% | - | - | - | 0.90 | 10.47% | - | - | -11.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 184.33% | 100.00% | -84.33% | - | - | - | 0.54 | 45.75% | - | - | -84.33% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 158.97% | 100.00% | -58.97% | - | - | - | 0.63 | 37.10% | - | - | -58.97% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 158.97% | 100.00% | -58.97% | - | - | - | 0.63 | 37.10% | - | - | -58.97% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO CONTRAMARCO ENCHAPADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 73.10% | 100.00% | 26.90% | - | - | - | 1.37 | -36.80% | - | - | 26.90% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 74.94% | 100.00% | 25.06% | - | - | - | 1.33 | -33.43% | - | - | 25.06% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.59% | 100.00% | 10.41% | - | - | - | 1.12 | -11.63% | - | - | 10.41% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 81.14% | 100.00% | 18.86% | - | - | - | 1.23 | -23.25% | - | - | 18.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 77.78% | 100.00% | 22.22% | - | - | - | 1.29 | -28.56% | - | - | 22.22% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 77.78% | 100.00% | 22.22% | - | - | - | 1.29 | -28.56% | - | - | 22.22% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 77.78% | 100.00% | 22.22% | - | - | - | 1.29 | -28.56% | - | - | 22.22% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 77.78% | 100.00% | 22.22% | - | - | - | 1.29 | -28.56% | - | - | 22.22% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.65% | 100.00% | 54.35% | - | - | - | 2.19 | -119.05% | - | - | 54.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 100.00% | 0.11% | - | - | - | 1.00 | -0.11% | - | - | 0.11% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 100.00% | 19.28% | - | - | - | 1.24 | -23.89% | - | - | 19.28% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 100.00% | -48.15% | - | - | - | 0.67 | 32.50% | - | - | -48.15% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 100.00% | 57.12% | - | - | - | 2.33 | -133.18% | - | - | 57.12% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 97.68% | 100.00% | 2.32% | - | - | - | 1.02 | -2.38% | - | - | 2.32% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 130.72% | 100.00% | -30.72% | - | - | - | 0.76 | 23.50% | - | - | -30.72% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 193.84% | 100.00% | -93.84% | - | - | - | 0.52 | 48.41% | - | - | -93.84% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 148325.84% | 100.00% | -148225.84% | - | - | - | 0.00 | 99.93% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 243478.26% | 100.00% | -243378.26% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 717.48% | 100.00% | -617.48% | - | - | - | 0.14 | 86.06% | - | - | -617.48% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 44898.80% | 100.00% | -44798.80% | - | - | - | 0.00 | 99.78% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 236.18% | 100.00% | -136.18% | - | - | - | 0.42 | 57.66% | - | - | -136.18% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 192.31% | 100.00% | -92.31% | - | - | - | 0.52 | 48.00% | - | - | -92.31% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 139.49% | 100.00% | -39.49% | - | - | - | 0.72 | 28.31% | - | - | -39.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 54.16% | 100.00% | 45.84% | - | - | - | 1.85 | -84.64% | - | - | 45.84% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 132.31% | 100.00% | -32.31% | - | - | - | 0.76 | 24.42% | - | - | -32.31% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 92.67% | 100.00% | 7.33% | - | - | - | 1.08 | -7.91% | - | - | 7.33% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.54% | 100.00% | 62.46% | - | - | - | 2.66 | -166.39% | - | - | 62.46% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.14% | - | - | 29.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.14% | - | - | 29.15% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 124.34% | 100.00% | -24.34% | - | - | - | 0.80 | 19.58% | - | - | -24.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 137.68% | 100.00% | -37.68% | - | - | - | 0.73 | 27.37% | - | - | -37.68% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 422.75% | 100.00% | -322.75% | - | - | - | 0.24 | 76.35% | - | - | -322.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 160.27% | 100.00% | -60.27% | - | - | - | 0.62 | 37.61% | - | - | -60.27% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 100.34% | 100.00% | -0.34% | - | - | - | 1.00 | 0.34% | - | - | -0.34% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 120.06% | 100.00% | -20.06% | - | - | - | 0.83 | 16.71% | - | - | -20.06% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.66% | 100.00% | 57.34% | - | - | - | 2.34 | -134.39% | - | - | 57.34% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.03% | 100.00% | -43.03% | - | - | - | 0.70 | 30.09% | - | - | -43.03% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 113.93% | 100.00% | -13.93% | - | - | - | 0.88 | 12.23% | - | - | -13.93% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 113.93% | 100.00% | -13.93% | - | - | - | 0.88 | 12.23% | - | - | -13.93% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 72.47% | 100.00% | 27.53% | - | - | - | 1.38 | -37.99% | - | - | 27.53% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 80.43% | 100.00% | 19.57% | - | - | - | 1.24 | -24.33% | - | - | 19.57% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 112.52% | 100.00% | -12.52% | - | - | - | 0.89 | 11.13% | - | - | -12.52% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14634.65% | 100.00% | -14534.65% | - | - | - | 0.01 | 99.32% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2064.97% | 100.00% | -1964.97% | - | - | - | 0.05 | 95.16% | - | - | -1964.97% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.98% | 100.00% | -133.98% | - | - | - | 0.43 | 57.26% | - | - | -133.98% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 134.15% | 100.00% | -34.15% | - | - | - | 0.75 | 25.46% | - | - | -34.15% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 73.72% | 100.00% | 26.28% | - | - | - | 1.36 | -35.64% | - | - | 26.28% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 125.31% | 100.00% | -25.31% | - | - | - | 0.80 | 20.20% | - | - | -25.31% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.03% | 100.00% | 10.97% | - | - | - | 1.12 | -12.33% | - | - | 10.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.24% | 100.00% | 28.76% | - | - | - | 1.40 | -40.37% | - | - | 28.76% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 213.45% | 100.00% | -113.45% | - | - | - | 0.47 | 53.15% | - | - | -113.45% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 309.93% | 100.00% | -209.93% | - | - | - | 0.32 | 67.73% | - | - | -209.93% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.80% | 100.00% | -83.80% | - | - | - | 0.54 | 45.59% | - | - | -83.80% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1013.44% | 100.00% | -913.44% | - | - | - | 0.10 | 90.13% | - | - | -913.44% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 101.47% | 100.00% | -1.47% | - | - | - | 0.99 | 1.45% | - | - | -1.47% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.84% | 100.00% | 54.16% | - | - | - | 2.18 | -118.13% | - | - | 54.16% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.88% | 100.00% | 54.12% | - | - | - | 2.18 | -117.95% | - | - | 54.12% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 76.34% | 100.00% | 23.66% | - | - | - | 1.31 | -30.99% | - | - | 23.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.17% | 100.00% | 19.83% | - | - | - | 1.25 | -24.74% | - | - | 19.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 80.17% | 100.00% | 19.83% | - | - | - | 1.25 | -24.74% | - | - | 19.83% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.70% | 100.00% | 29.30% | - | - | - | 1.41 | -41.44% | - | - | 29.30% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1713.55% | 100.00% | -1613.55% | - | - | - | 0.06 | 94.16% | - | - | -1613.55% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 711.58% | 100.00% | -611.58% | - | - | - | 0.14 | 85.95% | - | - | -611.58% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 263.51% | 100.00% | -163.51% | - | - | - | 0.38 | 62.05% | - | - | -163.51% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 205.78% | 100.00% | -105.78% | - | - | - | 0.49 | 51.40% | - | - | -105.78% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2616.83% | 100.00% | -2516.83% | - | - | - | 0.04 | 96.18% | - | - | -2516.83% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 28.10% | 100.00% | 71.90% | - | - | - | 3.56 | -255.82% | - | - | 71.90% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 27.52% | 100.00% | 72.48% | - | - | - | 3.63 | -263.44% | - | - | 72.48% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.93% | 100.00% | 91.07% | - | - | - | 11.20 | -1020.21% | - | - | 91.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 2592.46% | 100.00% | -2492.46% | - | - | - | 0.04 | 96.14% | - | - | -2492.46% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 60.31% | 93.64% | 33.33% | - | - | - | 1.55 | -55.26% | - | - | 35.59% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.43% | 88.00% | -13.43% | - | - | - | 0.87 | 13.24% | - | - | -15.26% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 104.29% | 88.00% | -16.29% | - | - | - | 0.84 | 15.62% | - | - | -18.51% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.19% | 88.00% | 81.81% | - | - | - | 14.21 | -1321.46% | - | - | 92.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 13.99% | 100.00% | 86.01% | - | - | - | 7.15 | -614.90% | - | - | 86.01% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 14.21% | 100.00% | 85.79% | - | - | - | 7.04 | -603.71% | - | - | 85.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 5
|
- | - | - | - | - | - | 1.30% | 1.25% | 96.12% | 98.52% | 2.40% | - | - | - | 1.02 | -2.50% | - | - | 2.44% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 97.56% | 93.64% | -3.92% | - | - | - | 0.96 | 4.02% | - | - | -4.19% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.38% | 88.00% | -13.38% | - | - | - | 0.87 | 13.19% | - | - | -15.20% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 104.29% | 88.00% | -16.29% | - | - | - | 0.84 | 15.62% | - | - | -18.51% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.28% | 88.00% | 83.72% | - | - | - | 20.57 | -1956.57% | - | - | 95.14% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 1" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 93.26% | 100.00% | 6.74% | - | - | - | 1.07 | -7.22% | - | - | 6.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 95.86% | 100.00% | 4.14% | - | - | - | 1.04 | -4.32% | - | - | 4.14% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 100.00% | 14.19% | - | - | - | 1.17 | -16.54% | - | - | 14.19% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 85.81% | 100.00% | 14.19% | - | - | - | 1.17 | -16.54% | - | - | 14.19% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 100.00% | 93.42% | - | - | - | 15.20 | -1420.37% | - | - | 93.42% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 103.05% | 98.98% | -4.07% | - | - | - | 0.96 | 3.95% | - | - | -4.11% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 162.82% | 100.00% | -62.82% | - | - | - | 0.61 | 38.58% | - | - | -62.82% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 134.93% | 100.00% | -34.93% | - | - | - | 0.74 | 25.89% | - | - | -34.93% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 134.93% | 100.00% | -34.93% | - | - | - | 0.74 | 25.89% | - | - | -34.93% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 98.93% | 100.00% | 1.07% | - | - | - | 1.01 | -1.08% | - | - | 1.07% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE EXTRA WHITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXCELLO WEATHER PERFECT LATEX MATE BASE DEEP
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 150.29% | 100.00% | -50.29% | - | - | - | 0.67 | 33.46% | - | - | -50.29% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 150.29% | 100.00% | -50.29% | - | - | - | 0.67 | 33.46% | - | - | -50.29% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 130.31% | 100.00% | -30.31% | - | - | - | 0.77 | 23.26% | - | - | -30.31% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.15% | 100.00% | -53.15% | - | - | - | 0.65 | 34.71% | - | - | -53.15% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 153.15% | 100.00% | -53.15% | - | - | - | 0.65 | 34.71% | - | - | -53.15% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA PLOMO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.30% | 100.00% | 12.70% | - | - | - | 1.15 | -14.54% | - | - | 12.70% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 51.04% | 100.00% | 48.96% | - | - | - | 1.96 | -95.94% | - | - | 48.96% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 51.04% | 100.00% | 48.96% | - | - | - | 1.96 | -95.94% | - | - | 48.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 121.57% | 100.00% | -21.57% | - | - | - | 0.82 | 17.74% | - | - | -21.57% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 103.69% | 100.00% | -3.69% | - | - | - | 0.96 | 3.56% | - | - | -3.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.81% | 100.00% | -2.81% | - | - | - | 0.97 | 2.73% | - | - | -2.81% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.81% | 100.00% | -2.81% | - | - | - | 0.97 | 2.73% | - | - | -2.81% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.37% | 100.00% | -2.37% | - | - | - | 0.98 | 2.32% | - | - | -2.37% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 20.87% | 100.00% | 79.13% | - | - | - | 4.79 | -379.11% | - | - | 79.13% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 60.14% | 100.00% | 39.86% | - | - | - | 1.66 | -66.28% | - | - | 39.86% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 56.04% | 100.00% | 43.96% | - | - | - | 1.78 | -78.46% | - | - | 43.96% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.61% | 100.00% | 93.39% | - | - | - | 15.13 | -1412.61% | - | - | 93.39% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 525.19% | 0.00% | -525.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 520.50% | 0.00% | -520.50% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 520.50% | 0.00% | -520.50% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 90.59% | 100.00% | 9.41% | - | - | - | 1.10 | -10.39% | - | - | 9.41% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 116.90% | 100.00% | -16.90% | - | - | - | 0.86 | 14.46% | - | - | -16.90% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 164.43% | 100.00% | -64.43% | - | - | - | 0.61 | 39.19% | - | - | -64.43% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 260.47% | 100.00% | -160.47% | - | - | - | 0.38 | 61.61% | - | - | -160.47% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 242.92% | 100.00% | -142.92% | - | - | - | 0.41 | 58.83% | - | - | -142.92% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 105.69% | 100.00% | -5.69% | - | - | - | 0.95 | 5.38% | - | - | -5.69% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 56.78% | 100.00% | 43.22% | - | - | - | 1.76 | -76.12% | - | - | 43.22% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.33% | 100.00% | 1.67% | - | - | - | 1.02 | -1.70% | - | - | 1.67% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.56% | 100.00% | 18.44% | - | - | - | 1.23 | -22.61% | - | - | 18.44% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 842.97 | -84197.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.78% | 100.00% | 26.22% | - | - | - | 1.36 | -35.53% | - | - | 26.22% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.78% | 100.00% | 26.22% | - | - | - | 1.36 | -35.53% | - | - | 26.22% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 108.09% | 100.00% | -8.09% | - | - | - | 0.93 | 7.48% | - | - | -8.09% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 106.50% | 100.00% | -6.50% | - | - | - | 0.94 | 6.10% | - | - | -6.50% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 111.00% | 100.00% | -11.00% | - | - | - | 0.90 | 9.91% | - | - | -11.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13413.41% | 100.00% | -13313.41% | - | - | - | 0.01 | 99.25% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1167.62% | 100.00% | -1067.62% | - | - | - | 0.09 | 91.44% | - | - | -1067.62% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 149.53% | 100.00% | -49.53% | - | - | - | 0.67 | 33.12% | - | - | -49.53% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 148.83% | 100.00% | -48.83% | - | - | - | 0.67 | 32.81% | - | - | -48.83% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 34.81% | 100.00% | 65.19% | - | - | - | 2.87 | -187.30% | - | - | 65.19% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 54.61% | 100.00% | 45.39% | - | - | - | 1.83 | -83.13% | - | - | 45.39% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.77% | 100.00% | 74.23% | - | - | - | 3.88 | -288.01% | - | - | 74.23% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1825.21 | -182421.00% | - | - | 99.95% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 187.77% | 100.00% | -87.77% | - | - | - | 0.53 | 46.74% | - | - | -87.77% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL DE 2 1/2"X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.80% | 100.00% | -5.80% | - | - | - | 0.95 | 5.48% | - | - | -5.80% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 105.80% | 100.00% | -5.80% | - | - | - | 0.95 | 5.48% | - | - | -5.80% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 67.29% | 100.00% | 32.71% | - | - | - | 1.49 | -48.60% | - | - | 32.71% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 85.50% | 100.00% | 14.50% | - | - | - | 1.17 | -16.96% | - | - | 14.50% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 97.49% | 100.00% | 2.51% | - | - | - | 1.03 | -2.57% | - | - | 2.51% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 97.49% | 100.00% | 2.51% | - | - | - | 1.03 | -2.57% | - | - | 2.51% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 66.47% | 100.00% | 33.53% | - | - | - | 1.50 | -50.45% | - | - | 33.53% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 330.44% | 100.00% | -230.44% | - | - | - | 0.30 | 69.74% | - | - | -230.44% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 194.81% | 100.00% | -94.81% | - | - | - | 0.51 | 48.67% | - | - | -94.81% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4595.45% | 100.00% | -4495.45% | - | - | - | 0.02 | 97.82% | - | - | -4495.45% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 52.37% | 100.00% | 47.63% | - | - | - | 1.91 | -90.95% | - | - | 47.63% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 48.79% | 100.00% | 51.21% | - | - | - | 2.05 | -104.95% | - | - | 51.21% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.53% | 100.00% | 46.47% | - | - | - | 1.87 | -86.83% | - | - | 46.47% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1523.76% | 100.00% | -1423.76% | - | - | - | 0.07 | 93.44% | - | - | -1423.76% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 202.91% | 100.00% | -102.91% | - | - | - | 0.49 | 50.72% | - | - | -102.91% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 869.44 | -86844.00% | - | - | 99.88% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 72.39% | 100.00% | 27.61% | - | - | - | 1.38 | -38.15% | - | - | 27.61% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 99.75% | 100.00% | 0.25% | - | - | - | 1.00 | -0.25% | - | - | 0.25% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6157.64% | 100.00% | -6057.64% | - | - | - | 0.02 | 98.38% | - | - | -6057.64% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 233.98% | 100.00% | -133.98% | - | - | - | 0.43 | 57.26% | - | - | -133.98% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 124.56% | 100.00% | -24.56% | - | - | - | 0.80 | 19.72% | - | - | -24.56% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.15% | 100.00% | 10.85% | - | - | - | 1.12 | -12.17% | - | - | 10.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.15% | 100.00% | 27.85% | - | - | - | 1.39 | -38.61% | - | - | 27.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 236.23% | 100.00% | -136.23% | - | - | - | 0.42 | 57.67% | - | - | -136.23% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 353.84% | 100.00% | -253.84% | - | - | - | 0.28 | 71.74% | - | - | -253.84% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 183.78% | 100.00% | -83.78% | - | - | - | 0.54 | 45.59% | - | - | -83.78% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 839.13% | 100.00% | -739.13% | - | - | - | 0.12 | 88.08% | - | - | -739.13% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 92.39% | 100.00% | 7.61% | - | - | - | 1.08 | -8.24% | - | - | 7.61% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.08% | 100.00% | 56.92% | - | - | - | 2.32 | -132.15% | - | - | 56.92% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
CASA # 40
|
- | - | - | - | - | - | 1.30% | 1.25% | 87.26% | 92.37% | 5.11% | - | - | - | 1.06 | -5.86% | - | - | 5.54% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 123.83% | 85.01% | -38.82% | - | - | - | 0.69 | 31.35% | - | - | -45.66% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.06% | 100.00% | -135.06% | - | - | - | 0.43 | 57.46% | - | - | -135.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.06% | 100.00% | -135.06% | - | - | - | 0.43 | 57.46% | - | - | -135.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 235.06% | 100.00% | -135.06% | - | - | - | 0.43 | 57.46% | - | - | -135.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 203.37% | 100.00% | -103.37% | - | - | - | 0.49 | 50.83% | - | - | -103.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 201.82% | 100.00% | -101.82% | - | - | - | 0.50 | 50.45% | - | - | -101.82% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 107.28% | 100.00% | -7.28% | - | - | - | 0.93 | 6.79% | - | - | -7.28% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 107.28% | 100.00% | -7.28% | - | - | - | 0.93 | 6.79% | - | - | -7.28% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 150.50% | 100.00% | -50.50% | - | - | - | 0.66 | 33.56% | - | - | -50.50% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 231.49% | 100.00% | -131.49% | - | - | - | 0.43 | 56.80% | - | - | -131.49% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 107.47% | 100.00% | -7.47% | - | - | - | 0.93 | 6.95% | - | - | -7.47% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 107.47% | 100.00% | -7.47% | - | - | - | 0.93 | 6.95% | - | - | -7.47% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 87.08% | 100.00% | 12.92% | - | - | - | 1.15 | -14.84% | - | - | 12.92% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.33% | 100.00% | 67.67% | - | - | - | 3.09 | -209.29% | - | - | 67.67% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 97.46% | 100.00% | 2.54% | - | - | - | 1.03 | -2.61% | - | - | 2.54% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 50.47% | 100.00% | 49.53% | - | - | - | 1.98 | -98.15% | - | - | 49.53% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 50.04% | 100.00% | 49.96% | - | - | - | 2.00 | -99.83% | - | - | 49.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 50.04% | 100.00% | 49.96% | - | - | - | 2.00 | -99.83% | - | - | 49.96% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 50.04% | 100.00% | 49.96% | - | - | - | 2.00 | -99.83% | - | - | 49.96% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 46.84% | 100.00% | 53.16% | - | - | - | 2.14 | -113.51% | - | - | 53.16% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 40.18% | 100.00% | 59.82% | - | - | - | 2.49 | -148.89% | - | - | 59.82% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 295.93% | 0.00% | -295.93% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPONJA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 293.46% | 0.00% | -293.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 293.46% | 0.00% | -293.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 73.05% | 100.00% | 26.95% | - | - | - | 1.37 | -36.88% | - | - | 26.95% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 111.29% | 100.00% | -11.29% | - | - | - | 0.90 | 10.14% | - | - | -11.29% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 159.81% | 100.00% | -59.81% | - | - | - | 0.63 | 37.43% | - | - | -59.81% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 301.09% | 100.00% | -201.09% | - | - | - | 0.33 | 66.79% | - | - | -201.09% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 190.37% | 100.00% | -90.37% | - | - | - | 0.53 | 47.47% | - | - | -90.37% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO M004 PARA VIVIENDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 58.56% | 100.00% | 41.44% | - | - | - | 1.71 | -70.77% | - | - | 41.44% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 58.56% | 100.00% | 41.44% | - | - | - | 1.71 | -70.77% | - | - | 41.44% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 89.18% | 100.00% | 10.82% | - | - | - | 1.12 | -12.13% | - | - | 10.82% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 115.18% | 100.00% | -15.18% | - | - | - | 0.87 | 13.18% | - | - | -15.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 115.18% | 100.00% | -15.18% | - | - | - | 0.87 | 13.18% | - | - | -15.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 47.07% | 100.00% | 52.93% | - | - | - | 2.12 | -112.43% | - | - | 52.93% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4445.18% | 100.00% | -4345.18% | - | - | - | 0.02 | 97.75% | - | - | -4345.18% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 168.27% | 100.00% | -68.27% | - | - | - | 0.59 | 40.57% | - | - | -68.27% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3840.61% | 100.00% | -3740.61% | - | - | - | 0.03 | 97.40% | - | - | -3740.61% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.09% | 100.00% | 20.91% | - | - | - | 1.26 | -26.44% | - | - | 20.91% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 54.96% | 100.00% | 45.04% | - | - | - | 1.82 | -81.96% | - | - | 45.04% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.52% | 100.00% | 46.48% | - | - | - | 1.87 | -86.86% | - | - | 46.48% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1980.90% | 100.00% | -1880.90% | - | - | - | 0.05 | 94.95% | - | - | -1880.90% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 306.63% | 100.00% | -206.63% | - | - | - | 0.33 | 67.39% | - | - | -206.63% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.70% | 100.00% | -446.70% | - | - | - | 0.18 | 81.71% | - | - | -446.70% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 80.55% | 100.00% | 19.45% | - | - | - | 1.24 | -24.15% | - | - | 19.45% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 152.57% | 100.00% | -52.57% | - | - | - | 0.66 | 34.46% | - | - | -52.57% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 213.89% | 100.00% | -113.89% | - | - | - | 0.47 | 53.25% | - | - | -113.89% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 124.59% | 100.00% | -24.59% | - | - | - | 0.80 | 19.74% | - | - | -24.59% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.14% | - | - | 29.15% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.17% | 100.00% | 6.83% | - | - | - | 1.07 | -7.33% | - | - | 6.83% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 92.80% | 100.00% | 7.20% | - | - | - | 1.08 | -7.76% | - | - | 7.20% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 27.29% | 100.00% | 72.71% | - | - | - | 3.66 | -266.49% | - | - | 72.71% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 48.00% | 100.00% | 52.00% | - | - | - | 2.08 | -108.34% | - | - | 52.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27083.64% | 100.00% | -26983.64% | - | - | - | 0.00 | 99.63% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 264.70% | 100.00% | -164.70% | - | - | - | 0.38 | 62.22% | - | - | -164.70% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 133.71% | 100.00% | -33.71% | - | - | - | 0.75 | 25.21% | - | - | -33.71% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 124.56% | 100.00% | -24.56% | - | - | - | 0.80 | 19.72% | - | - | -24.56% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 284.53% | 100.00% | -184.53% | - | - | - | 0.35 | 64.85% | - | - | -184.53% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 267.12% | 100.00% | -167.12% | - | - | - | 0.37 | 62.56% | - | - | -167.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.75% | 100.00% | -44.75% | - | - | - | 0.69 | 30.92% | - | - | -44.75% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 889.54% | 100.00% | -789.54% | - | - | - | 0.11 | 88.76% | - | - | -789.54% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 100.00% | 100.00% | - | - | - | 19933.17 | -1993217.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.40% | 86.12% | 31.72% | - | - | - | 1.58 | -58.30% | - | - | 36.83% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 102.55% | 88.00% | -14.55% | - | - | - | 0.86 | 14.19% | - | - | -16.53% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 105.40% | 88.00% | -17.40% | - | - | - | 0.83 | 16.51% | - | - | -19.78% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7.31% | 88.00% | 80.69% | - | - | - | 12.03 | -1103.33% | - | - | 91.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.17% | 84.00% | 83.83% | - | - | - | 506.12 | -50511.66% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 84.00% | 78.30% | - | - | - | 14.74 | -1374.13% | - | - | 93.22% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 28
|
- | - | - | - | - | - | 1.30% | 1.25% | 92.83% | 100.00% | 7.17% | - | - | - | 1.08 | -7.72% | - | - | 7.17% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 105.49% | 100.00% | -5.49% | - | - | - | 0.95 | 5.20% | - | - | -5.49% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 133.16% | 100.00% | -33.16% | - | - | - | 0.75 | 24.90% | - | - | -33.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 174.25% | 100.00% | -74.25% | - | - | - | 0.57 | 42.61% | - | - | -74.25% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 218.44% | 100.00% | -118.44% | - | - | - | 0.46 | 54.22% | - | - | -118.44% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE BOMBEO CONVENCIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION CON PLUMA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 167.06% | 100.00% | -67.06% | - | - | - | 0.60 | 40.14% | - | - | -67.06% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.09% | 100.00% | -23.09% | - | - | - | 0.81 | 18.76% | - | - | -23.09% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.95% | 100.00% | 74.05% | - | - | - | 3.85 | -285.35% | - | - | 74.05% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 6104.82% | 100.00% | -6004.82% | - | - | - | 0.02 | 98.36% | - | - | -6004.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.09% | 100.00% | -19.09% | - | - | - | 0.84 | 16.03% | - | - | -19.09% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.24% | 100.00% | 32.76% | - | - | - | 1.49 | -48.71% | - | - | 32.76% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.12% | 100.00% | 12.88% | - | - | - | 1.15 | -14.78% | - | - | 12.88% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.14% | 100.00% | -27.14% | - | - | - | 0.79 | 21.34% | - | - | -27.14% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 4" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 99.34% | 100.00% | 0.66% | - | - | - | 1.01 | -0.66% | - | - | 0.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 99.34% | 100.00% | 0.66% | - | - | - | 1.01 | -0.66% | - | - | 0.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 115.68% | 100.00% | -15.68% | - | - | - | 0.86 | 13.55% | - | - | -15.68% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 159.63% | 100.00% | -59.63% | - | - | - | 0.63 | 37.36% | - | - | -59.63% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 159.63% | 100.00% | -59.63% | - | - | - | 0.63 | 37.36% | - | - | -59.63% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 44.18% | 100.00% | 55.82% | - | - | - | 2.26 | -126.36% | - | - | 55.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1038.19% | 100.00% | -938.19% | - | - | - | 0.10 | 90.37% | - | - | -938.19% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 184.37% | 100.00% | -84.37% | - | - | - | 0.54 | 45.76% | - | - | -84.37% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 89.02% | 100.00% | 10.98% | - | - | - | 1.12 | -12.33% | - | - | 10.98% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1152.21% | 100.00% | -1052.21% | - | - | - | 0.09 | 91.32% | - | - | -1052.21% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.43% | 100.00% | -10.43% | - | - | - | 0.91 | 9.45% | - | - | -10.43% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 100.00% | 7.18% | - | - | - | 1.08 | -7.74% | - | - | 7.18% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 100.00% | 7.18% | - | - | - | 1.08 | -7.74% | - | - | 7.18% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 6.61% | 100.00% | 93.39% | - | - | - | 15.14 | -1413.71% | - | - | 93.39% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.28% | 100.00% | 85.72% | - | - | - | 7.00 | -600.17% | - | - | 85.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 681.89% | 100.00% | -581.89% | - | - | - | 0.15 | 85.33% | - | - | -581.89% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 113.56% | 100.00% | -13.56% | - | - | - | 0.88 | 11.94% | - | - | -13.56% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 146.07% | 100.00% | -46.07% | - | - | - | 0.68 | 31.54% | - | - | -46.07% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 342666.67% | 100.00% | -342566.67% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7527.53% | 100.00% | -7427.53% | - | - | - | 0.01 | 98.67% | - | - | -7427.53% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 520.69% | 100.00% | -420.69% | - | - | - | 0.19 | 80.79% | - | - | -420.69% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 150.71% | 100.00% | -50.71% | - | - | - | 0.66 | 33.65% | - | - | -50.71% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.26% | 100.00% | -36.26% | - | - | - | 0.73 | 26.61% | - | - | -36.26% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.11% | 100.00% | 53.89% | - | - | - | 2.17 | -116.88% | - | - | 53.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.62% | 100.00% | -154.62% | - | - | - | 0.39 | 60.73% | - | - | -154.62% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 247.30% | 100.00% | -147.30% | - | - | - | 0.40 | 59.56% | - | - | -147.30% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 373.47% | 100.00% | -273.47% | - | - | - | 0.27 | 73.22% | - | - | -273.47% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 134.82% | 100.00% | -34.82% | - | - | - | 0.74 | 25.83% | - | - | -34.82% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 69.51% | 100.00% | 30.49% | - | - | - | 1.44 | -43.86% | - | - | 30.49% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 81.93% | 100.00% | 18.07% | - | - | - | 1.22 | -22.06% | - | - | 18.07% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 115.73% | 100.00% | -15.73% | - | - | - | 0.86 | 13.60% | - | - | -15.73% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 51515.93% | 100.00% | -51415.93% | - | - | - | 0.00 | 99.81% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EPOXICO EBOND 580 MV
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.31% | 100.00% | -23.31% | - | - | - | 0.81 | 18.91% | - | - | -23.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 111.76% | 100.00% | -11.76% | - | - | - | 0.89 | 10.52% | - | - | -11.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.09% | 100.00% | 26.91% | - | - | - | 1.37 | -36.82% | - | - | 26.91% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 92.27% | 100.00% | 7.73% | - | - | - | 1.08 | -8.38% | - | - | 7.73% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.12% | 100.00% | 11.88% | - | - | - | 1.13 | -13.48% | - | - | 11.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.61% | 100.00% | 38.39% | - | - | - | 1.62 | -62.32% | - | - | 38.39% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 158.71% | 100.00% | -58.71% | - | - | - | 0.63 | 36.99% | - | - | -58.71% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 177.89% | 100.00% | -77.89% | - | - | - | 0.56 | 43.79% | - | - | -77.89% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 107.57% | 100.00% | -7.57% | - | - | - | 0.93 | 7.04% | - | - | -7.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 329.15% | 100.00% | -229.15% | - | - | - | 0.30 | 69.62% | - | - | -229.15% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.38% | 100.00% | 54.62% | - | - | - | 2.20 | -120.36% | - | - | 54.62% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 45.38% | 100.00% | 54.62% | - | - | - | 2.20 | -120.36% | - | - | 54.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 92.67% | 100.00% | 7.33% | - | - | - | 1.08 | -7.92% | - | - | 7.33% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 642.86% | 100.00% | -542.86% | - | - | - | 0.16 | 84.44% | - | - | -542.86% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 631.10% | 100.00% | -531.10% | - | - | - | 0.16 | 84.15% | - | - | -531.10% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 631.10% | 100.00% | -531.10% | - | - | - | 0.16 | 84.15% | - | - | -531.10% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 120.96% | 100.00% | -20.96% | - | - | - | 0.83 | 17.33% | - | - | -20.96% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 178.25% | 100.00% | -78.25% | - | - | - | 0.56 | 43.90% | - | - | -78.25% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 178.25% | 100.00% | -78.25% | - | - | - | 0.56 | 43.90% | - | - | -78.25% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 178.25% | 100.00% | -78.25% | - | - | - | 0.56 | 43.90% | - | - | -78.25% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 90.53% | 100.00% | 9.47% | - | - | - | 1.10 | -10.46% | - | - | 9.47% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 90.53% | 100.00% | 9.47% | - | - | - | 1.10 | -10.46% | - | - | 9.47% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.23% | 100.00% | 15.77% | - | - | - | 1.19 | -18.72% | - | - | 15.77% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 105.15% | 100.00% | -5.15% | - | - | - | 0.95 | 4.89% | - | - | -5.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 92.92% | 100.00% | 7.08% | - | - | - | 1.08 | -7.62% | - | - | 7.08% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 69.49% | 100.00% | 30.51% | - | - | - | 1.44 | -43.91% | - | - | 30.51% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 69.49% | 100.00% | 30.51% | - | - | - | 1.44 | -43.91% | - | - | 30.51% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 29.53% | 100.00% | 70.47% | - | - | - | 3.39 | -238.68% | - | - | 70.47% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.96% | 100.00% | 20.04% | - | - | - | 1.25 | -25.06% | - | - | 20.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 47.69% | 100.00% | 52.31% | - | - | - | 2.10 | -109.71% | - | - | 52.31% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 132.90% | 100.00% | -32.90% | - | - | - | 0.75 | 24.76% | - | - | -32.90% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 129.63% | 100.00% | -29.63% | - | - | - | 0.77 | 22.86% | - | - | -29.63% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 2.39% | 100.00% | 97.61% | - | - | - | 41.81 | -4080.85% | - | - | 97.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 2.39% | 100.00% | 97.61% | - | - | - | 41.81 | -4080.85% | - | - | 97.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.91% | 100.00% | 53.09% | - | - | - | 2.13 | -113.18% | - | - | 53.09% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 35.25% | 100.00% | 64.75% | - | - | - | 2.84 | -183.67% | - | - | 64.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 59.06% | 100.00% | 40.94% | - | - | - | 1.69 | -69.31% | - | - | 40.94% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 12.79% | 100.00% | 87.21% | - | - | - | 7.82 | -681.64% | - | - | 87.21% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 12.92% | 100.00% | 87.08% | - | - | - | 7.74 | -673.70% | - | - | 87.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.42% | 100.00% | 91.58% | - | - | - | 11.88 | -1087.76% | - | - | 91.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIPLE CORRIDO DE 1/2" X 1" HG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA HG DE 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 26
|
- | - | - | - | - | - | 1.30% | 1.26% | 90.77% | 100.00% | 9.23% | - | - | - | 1.10 | -10.17% | - | - | 9.23% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 100.46% | 100.00% | -0.46% | - | - | - | 1.00 | 0.46% | - | - | -0.46% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 123.95% | 100.00% | -23.95% | - | - | - | 0.81 | 19.33% | - | - | -23.95% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 149.34% | 100.00% | -49.34% | - | - | - | 0.67 | 33.04% | - | - | -49.34% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 64060.67% | 100.00% | -63960.67% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.49% | 100.00% | -107.49% | - | - | - | 0.48 | 51.81% | - | - | -107.49% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 109.17% | 100.00% | -9.17% | - | - | - | 0.92 | 8.40% | - | - | -9.17% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.39% | 100.00% | 53.61% | - | - | - | 2.16 | -115.56% | - | - | 53.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.99% | 100.00% | 4.01% | - | - | - | 1.04 | -4.17% | - | - | 4.01% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 107.53% | 100.00% | -7.53% | - | - | - | 0.93 | 7.00% | - | - | -7.53% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 107.53% | 100.00% | -7.53% | - | - | - | 0.93 | 7.00% | - | - | -7.53% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182.55% | 100.00% | -82.55% | - | - | - | 0.55 | 45.22% | - | - | -82.55% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 111.34% | 100.00% | -11.34% | - | - | - | 0.90 | 10.18% | - | - | -11.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 145.64% | 100.00% | -45.64% | - | - | - | 0.69 | 31.34% | - | - | -45.64% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 307866.67% | 100.00% | -307766.67% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2522.52% | 100.00% | -2422.52% | - | - | - | 0.04 | 96.04% | - | - | -2422.52% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 387.24% | 100.00% | -287.24% | - | - | - | 0.26 | 74.18% | - | - | -287.24% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 150.79% | 100.00% | -50.79% | - | - | - | 0.66 | 33.68% | - | - | -50.79% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.26% | 100.00% | -36.26% | - | - | - | 0.73 | 26.61% | - | - | -36.26% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.19% | 100.00% | 59.81% | - | - | - | 2.49 | -148.84% | - | - | 59.81% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 252.73% | 100.00% | -152.73% | - | - | - | 0.40 | 60.43% | - | - | -152.73% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 255.78% | 100.00% | -155.78% | - | - | - | 0.39 | 60.90% | - | - | -155.78% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 280.76% | 100.00% | -180.76% | - | - | - | 0.36 | 64.38% | - | - | -180.76% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 147.55% | 100.00% | -47.55% | - | - | - | 0.68 | 32.23% | - | - | -47.55% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 122.83% | 100.00% | -22.83% | - | - | - | 0.81 | 18.58% | - | - | -22.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 94.87% | 100.00% | 5.13% | - | - | - | 1.05 | -5.40% | - | - | 5.13% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 139.37% | 100.00% | -39.37% | - | - | - | 0.72 | 28.25% | - | - | -39.37% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 21789.09% | 100.00% | -21689.09% | - | - | - | 0.00 | 99.54% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 20231.86% | 100.00% | -20131.86% | - | - | - | 0.00 | 99.51% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 392.41% | 100.00% | -292.41% | - | - | - | 0.25 | 74.52% | - | - | -292.41% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 1465.47% | 100.00% | -1365.47% | - | - | - | 0.07 | 93.18% | - | - | -1365.47% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 308.99% | 100.00% | -208.99% | - | - | - | 0.32 | 67.64% | - | - | -208.99% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 186.93% | 100.00% | -86.93% | - | - | - | 0.53 | 46.50% | - | - | -86.93% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 180.94% | 100.00% | -80.94% | - | - | - | 0.55 | 44.73% | - | - | -80.94% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.34% | 100.00% | 11.66% | - | - | - | 1.13 | -13.19% | - | - | 11.66% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.69% | 100.00% | 90.31% | - | - | - | 10.31 | -931.47% | - | - | 90.31% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 185.93% | 100.00% | -85.93% | - | - | - | 0.54 | 46.21% | - | - | -85.93% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.27% | 100.00% | -109.27% | - | - | - | 0.48 | 52.21% | - | - | -109.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 407.89% | 100.00% | -307.89% | - | - | - | 0.25 | 75.48% | - | - | -307.89% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 227.84% | 100.00% | -127.84% | - | - | - | 0.44 | 56.11% | - | - | -127.84% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 619.67% | 100.00% | -519.67% | - | - | - | 0.16 | 83.86% | - | - | -519.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 99.24% | 100.00% | 0.76% | - | - | - | 1.01 | -0.77% | - | - | 0.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.98% | 100.00% | 56.02% | - | - | - | 2.27 | -127.40% | - | - | 56.02% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.98% | 100.00% | 56.02% | - | - | - | 2.27 | -127.40% | - | - | 56.02% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 46.59% | 100.00% | 53.41% | - | - | - | 2.15 | -114.65% | - | - | 53.41% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FLETES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 85.20% | 100.00% | 14.80% | - | - | - | 1.17 | -17.37% | - | - | 14.80% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.43% | 100.00% | -2.43% | - | - | - | 0.98 | 2.37% | - | - | -2.43% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.43% | 100.00% | -2.43% | - | - | - | 0.98 | 2.37% | - | - | -2.43% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 57.51% | 100.00% | 42.49% | - | - | - | 1.74 | -73.89% | - | - | 42.49% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2546.80% | 100.00% | -2446.80% | - | - | - | 0.04 | 96.07% | - | - | -2446.80% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 262.37% | 100.00% | -162.37% | - | - | - | 0.38 | 61.89% | - | - | -162.37% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 262.37% | 100.00% | -162.37% | - | - | - | 0.38 | 61.89% | - | - | -162.37% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 257.87% | 100.00% | -157.87% | - | - | - | 0.39 | 61.22% | - | - | -157.87% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 1146.93% | 100.00% | -1046.93% | - | - | - | 0.09 | 91.28% | - | - | -1046.93% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 145.78% | 100.00% | -45.78% | - | - | - | 0.69 | 31.40% | - | - | -45.78% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 730.48% | 100.00% | -630.48% | - | - | - | 0.14 | 86.31% | - | - | -630.48% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.82% | 100.00% | 94.18% | - | - | - | 17.17 | -1617.24% | - | - | 94.18% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCA DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULAS METALICAS DE 4" MANGO PLASTICO MARCA PUMA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 3.17% | 100.00% | 96.83% | - | - | - | 31.51 | -3050.57% | - | - | 96.83% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.44% | 93.13% | 100.00% | 6.87% | - | - | - | 1.07 | -7.38% | - | - | 6.87% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 509.44% | 100.00% | -409.44% | - | - | - | 0.20 | 80.37% | - | - | -409.44% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 405.23% | 100.00% | -305.23% | - | - | - | 0.25 | 75.32% | - | - | -305.23% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 405.23% | 100.00% | -305.23% | - | - | - | 0.25 | 75.32% | - | - | -305.23% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCALERA DE ALUMINIO 2 BANDAS 5 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 5 TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 137.15% | 100.00% | -37.15% | - | - | - | 0.73 | 27.09% | - | - | -37.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 183.62% | 100.00% | -83.62% | - | - | - | 0.54 | 45.54% | - | - | -83.62% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 168.70% | 100.00% | -68.70% | - | - | - | 0.59 | 40.72% | - | - | -68.70% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 168.70% | 100.00% | -68.70% | - | - | - | 0.59 | 40.72% | - | - | -68.70% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 112.46% | 100.00% | -12.46% | - | - | - | 0.89 | 11.08% | - | - | -12.46% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 107.84% | 100.00% | -7.84% | - | - | - | 0.93 | 7.27% | - | - | -7.84% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.23% | 100.00% | 15.77% | - | - | - | 1.19 | -18.72% | - | - | 15.77% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 112.50% | 100.00% | -12.50% | - | - | - | 0.89 | 11.11% | - | - | -12.50% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 52.42% | 100.00% | 47.58% | - | - | - | 1.91 | -90.77% | - | - | 47.58% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA LATEX BLANCO TRADICIONAL INTERIOR E EXTERIOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLOR BLANCO LATEX PLUS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 100.51% | 100.00% | -0.51% | - | - | - | 0.99 | 0.51% | - | - | -0.51% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.09% | 100.00% | -0.09% | - | - | - | 1.00 | 0.09% | - | - | -0.09% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.09% | 100.00% | -0.09% | - | - | - | 1.00 | 0.09% | - | - | -0.09% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.09% | 100.00% | -0.09% | - | - | - | 1.00 | 0.09% | - | - | -0.09% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.09% | 100.00% | -0.09% | - | - | - | 1.00 | 0.09% | - | - | -0.09% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 49.29% | 100.00% | 50.71% | - | - | - | 2.03 | -102.90% | - | - | 50.71% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.33% | 100.00% | -36.33% | - | - | - | 0.73 | 26.65% | - | - | -36.33% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 132.22% | 100.00% | -32.22% | - | - | - | 0.76 | 24.37% | - | - | -32.22% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.22% | 100.00% | 37.78% | - | - | - | 1.61 | -60.71% | - | - | 37.78% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 129.63% | 100.00% | -29.63% | - | - | - | 0.77 | 22.86% | - | - | -29.63% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 3.02% | 100.00% | 96.98% | - | - | - | 33.10 | -3209.88% | - | - | 96.98% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 3.02% | 100.00% | 96.98% | - | - | - | 33.10 | -3209.88% | - | - | 96.98% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 36.26% | 100.00% | 63.74% | - | - | - | 2.76 | -175.82% | - | - | 63.74% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 60.02% | 100.00% | 39.98% | - | - | - | 1.67 | -66.62% | - | - | 39.98% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 14.82% | 100.00% | 85.18% | - | - | - | 6.75 | -574.63% | - | - | 85.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 15.10% | 100.00% | 84.90% | - | - | - | 6.62 | -562.40% | - | - | 84.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 38
|
- | - | - | - | - | - | 1.30% | 1.25% | 80.04% | 89.85% | 9.81% | - | - | - | 1.12 | -12.25% | - | - | 10.91% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 84.28% | 77.70% | -6.58% | - | - | - | 0.92 | 7.80% | - | - | -8.46% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 149.92% | 100.00% | -49.92% | - | - | - | 0.67 | 33.30% | - | - | -49.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 149.92% | 100.00% | -49.92% | - | - | - | 0.67 | 33.30% | - | - | -49.92% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 55.38% | 100.00% | 44.62% | - | - | - | 1.81 | -80.56% | - | - | 44.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 53.46% | 100.00% | 46.54% | - | - | - | 1.87 | -87.05% | - | - | 46.54% | - | 0.00% |
|
SUBCONTRATO SERVICIOS MATERIALES Y MANO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 123.18% | 100.00% | -23.18% | - | - | - | 0.81 | 18.82% | - | - | -23.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 184.72% | 100.00% | -84.72% | - | - | - | 0.54 | 45.87% | - | - | -84.72% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.29% | 100.00% | -63.29% | - | - | - | 0.61 | 38.76% | - | - | -63.29% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 163.29% | 100.00% | -63.29% | - | - | - | 0.61 | 38.76% | - | - | -63.29% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 90.49% | 100.00% | 9.51% | - | - | - | 1.11 | -10.51% | - | - | 9.51% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 90.49% | 100.00% | 9.51% | - | - | - | 1.11 | -10.51% | - | - | 9.51% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.68% | 100.00% | 14.32% | - | - | - | 1.17 | -16.72% | - | - | 14.32% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 100.00% | 29.61% | - | - | - | 1.42 | -42.07% | - | - | 29.61% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 100.00% | 29.61% | - | - | - | 1.42 | -42.07% | - | - | 29.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 100.00% | 29.61% | - | - | - | 1.42 | -42.07% | - | - | 29.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 100.00% | 29.61% | - | - | - | 1.42 | -42.07% | - | - | 29.61% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 41.96% | 100.00% | 58.04% | - | - | - | 2.38 | -138.34% | - | - | 58.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 41.96% | 100.00% | 58.04% | - | - | - | 2.38 | -138.34% | - | - | 58.04% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 41.96% | 100.00% | 58.04% | - | - | - | 2.38 | -138.34% | - | - | 58.04% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 41.96% | 100.00% | 58.04% | - | - | - | 2.38 | -138.34% | - | - | 58.04% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 16.40% | 100.00% | 83.60% | - | - | - | 6.10 | -509.62% | - | - | 83.60% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 16.40% | 100.00% | 83.60% | - | - | - | 6.10 | -509.62% | - | - | 83.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO SERVICIOS MATERIALES Y MANO DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.77% | 0.00% | -72.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.77% | 0.00% | -72.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.77% | 0.00% | -72.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 19.53% | 0.00% | -19.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 56.26% | 0.00% | -56.26% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 52.15% | 0.00% | -52.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 36.00% | 0.00% | -36.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 86.34% | 100.00% | 13.66% | - | - | - | 1.16 | -15.83% | - | - | 13.66% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 115.04% | 100.00% | -15.04% | - | - | - | 0.87 | 13.08% | - | - | -15.04% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 176.00% | 100.00% | -76.00% | - | - | - | 0.57 | 43.18% | - | - | -76.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 349342.22% | 100.00% | -349242.22% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 423.44% | 100.00% | -323.44% | - | - | - | 0.24 | 76.38% | - | - | -323.44% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 203.75% | 100.00% | -103.75% | - | - | - | 0.49 | 50.92% | - | - | -103.75% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.29% | 100.00% | -39.29% | - | - | - | 0.72 | 28.20% | - | - | -39.29% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 47.71% | 100.00% | 52.29% | - | - | - | 2.10 | -109.58% | - | - | 52.29% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 47.71% | 100.00% | 52.29% | - | - | - | 2.10 | -109.58% | - | - | 52.29% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 95.79% | 100.00% | 4.21% | - | - | - | 1.04 | -4.40% | - | - | 4.21% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 182.24% | 100.00% | -82.24% | - | - | - | 0.55 | 45.13% | - | - | -82.24% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 213.89% | 100.00% | -113.89% | - | - | - | 0.47 | 53.25% | - | - | -113.89% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 194.44% | 100.00% | -94.44% | - | - | - | 0.51 | 48.57% | - | - | -94.44% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.15% | - | - | 29.15% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 206.05% | 100.00% | -106.05% | - | - | - | 0.49 | 51.47% | - | - | -106.05% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 157.72% | 100.00% | -57.72% | - | - | - | 0.63 | 36.60% | - | - | -57.72% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 80.91% | 100.00% | 19.09% | - | - | - | 1.24 | -23.60% | - | - | 19.09% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.61% | 100.00% | 1.39% | - | - | - | 1.01 | -1.41% | - | - | 1.39% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.61% | 100.00% | 1.39% | - | - | - | 1.01 | -1.41% | - | - | 1.39% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 52.40% | 100.00% | 47.60% | - | - | - | 1.91 | -90.83% | - | - | 47.60% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 213.58% | 100.00% | -113.58% | - | - | - | 0.47 | 53.18% | - | - | -113.58% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 116.84% | 100.00% | -16.84% | - | - | - | 0.86 | 14.41% | - | - | -16.84% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4257.33% | 100.00% | -4157.33% | - | - | - | 0.02 | 97.65% | - | - | -4157.33% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 100.00% | 38.12% | - | - | - | 1.62 | -61.61% | - | - | 38.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 56.63% | 100.00% | 43.37% | - | - | - | 1.77 | -76.60% | - | - | 43.37% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.52% | 100.00% | 46.48% | - | - | - | 1.87 | -86.86% | - | - | 46.48% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1980.90% | 100.00% | -1880.90% | - | - | - | 0.05 | 94.95% | - | - | -1880.90% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 856.20% | 100.00% | -756.20% | - | - | - | 0.12 | 88.32% | - | - | -756.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.70% | 100.00% | -446.70% | - | - | - | 0.18 | 81.71% | - | - | -446.70% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.09% | 100.00% | 62.91% | - | - | - | 2.70 | -169.63% | - | - | 62.91% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.32% | 100.00% | 85.68% | - | - | - | 6.98 | -598.31% | - | - | 85.68% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 63.65% | 100.00% | 36.35% | - | - | - | 1.57 | -57.10% | - | - | 36.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 116.35% | 100.00% | -16.35% | - | - | - | 0.86 | 14.05% | - | - | -16.35% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 57250.91% | 100.00% | -57150.91% | - | - | - | 0.00 | 99.83% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4926.11% | 100.00% | -4826.11% | - | - | - | 0.02 | 97.97% | - | - | -4826.11% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.74% | 100.00% | -142.74% | - | - | - | 0.41 | 58.80% | - | - | -142.74% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 1''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 144.87% | 100.00% | -44.87% | - | - | - | 0.69 | 30.97% | - | - | -44.87% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.96% | 100.00% | -6.96% | - | - | - | 0.93 | 6.51% | - | - | -6.96% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 84.73% | 100.00% | 15.27% | - | - | - | 1.18 | -18.02% | - | - | 15.27% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 270.43% | 100.00% | -170.43% | - | - | - | 0.37 | 63.02% | - | - | -170.43% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 265.57% | 100.00% | -165.57% | - | - | - | 0.38 | 62.35% | - | - | -165.57% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 219.83% | 100.00% | -119.83% | - | - | - | 0.45 | 54.51% | - | - | -119.83% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 879.09% | 100.00% | -779.09% | - | - | - | 0.11 | 88.62% | - | - | -779.09% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.87% | 86.12% | 31.25% | - | - | - | 1.57 | -56.96% | - | - | 36.29% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 103.43% | 88.00% | -15.43% | - | - | - | 0.85 | 14.91% | - | - | -17.53% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 106.47% | 88.00% | -18.47% | - | - | - | 0.83 | 17.34% | - | - | -20.98% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 88.00% | -12.00% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.06% | 88.00% | 85.94% | - | - | - | 42.65 | -4165.01% | - | - | 97.66% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.17% | 84.00% | 83.83% | - | - | - | 506.12 | -50511.66% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 84.00% | 78.30% | - | - | - | 14.74 | -1374.13% | - | - | 93.22% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 29
|
- | - | - | - | - | - | 1.30% | 1.25% | 88.86% | 100.00% | 11.14% | - | - | - | 1.13 | -12.54% | - | - | 11.14% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 104.10% | 100.00% | -4.10% | - | - | - | 0.96 | 3.94% | - | - | -4.10% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 144.79% | 100.00% | -44.79% | - | - | - | 0.69 | 30.93% | - | - | -44.79% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.37% | 100.00% | -88.37% | - | - | - | 0.53 | 46.91% | - | - | -88.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 188.37% | 100.00% | -88.37% | - | - | - | 0.53 | 46.91% | - | - | -88.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 74.16% | 100.00% | 25.84% | - | - | - | 1.35 | -34.84% | - | - | 25.84% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6170.50% | 100.00% | -6070.50% | - | - | - | 0.02 | 98.38% | - | - | -6070.50% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 12444.44% | 100.00% | -12344.44% | - | - | - | 0.01 | 99.20% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4346.63% | 100.00% | -4246.63% | - | - | - | 0.02 | 97.70% | - | - | -4246.63% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 100.00% | -2172.46% | - | - | - | 0.04 | 95.60% | - | - | -2172.46% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 232.04% | 100.00% | -132.04% | - | - | - | 0.43 | 56.90% | - | - | -132.04% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 232.04% | 100.00% | -132.04% | - | - | - | 0.43 | 56.90% | - | - | -132.04% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 205.43% | 100.00% | -105.43% | - | - | - | 0.49 | 51.32% | - | - | -105.43% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 113.31% | 100.00% | -13.31% | - | - | - | 0.88 | 11.74% | - | - | -13.31% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 4058.65% | 100.00% | -3958.65% | - | - | - | 0.02 | 97.54% | - | - | -3958.65% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.34% | 100.00% | 12.66% | - | - | - | 1.14 | -14.50% | - | - | 12.66% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.64% | 100.00% | 95.36% | - | - | - | 21.57 | -2056.88% | - | - | 95.36% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 3.86% | 100.00% | 96.14% | - | - | - | 25.89 | -2488.83% | - | - | 96.14% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 683.29% | 100.00% | -583.29% | - | - | - | 0.15 | 85.36% | - | - | -583.29% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 104.83% | 100.00% | -4.83% | - | - | - | 0.95 | 4.61% | - | - | -4.83% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 129.66% | 100.00% | -29.66% | - | - | - | 0.77 | 22.87% | - | - | -29.66% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 166533.33% | 100.00% | -166433.33% | - | - | - | 0.00 | 99.94% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 7527.53% | 100.00% | -7427.53% | - | - | - | 0.01 | 98.67% | - | - | -7427.53% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 319.88% | 100.00% | -219.88% | - | - | - | 0.31 | 68.74% | - | - | -219.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 134.82% | 100.00% | -34.82% | - | - | - | 0.74 | 25.83% | - | - | -34.82% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 93.05% | 100.00% | 6.95% | - | - | - | 1.07 | -7.47% | - | - | 6.95% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 128.58% | 100.00% | -28.58% | - | - | - | 0.78 | 22.23% | - | - | -28.58% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 94.33% | 100.00% | 5.67% | - | - | - | 1.06 | -6.01% | - | - | 5.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 39.56% | 100.00% | 60.44% | - | - | - | 2.53 | -152.81% | - | - | 60.44% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.03% | 100.00% | -154.03% | - | - | - | 0.39 | 60.63% | - | - | -154.03% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 255.94% | 100.00% | -155.94% | - | - | - | 0.39 | 60.93% | - | - | -155.94% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 371.35% | 100.00% | -271.35% | - | - | - | 0.27 | 73.07% | - | - | -271.35% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 100.85% | 100.00% | -0.85% | - | - | - | 0.99 | 0.84% | - | - | -0.85% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 132.12% | 100.00% | -32.12% | - | - | - | 0.76 | 24.31% | - | - | -32.12% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.07% | 100.00% | -72.07% | - | - | - | 0.58 | 41.88% | - | - | -72.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 118.28% | 100.00% | -18.28% | - | - | - | 0.85 | 15.46% | - | - | -18.28% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.24% | 100.00% | 32.76% | - | - | - | 1.49 | -48.71% | - | - | 32.76% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.12% | 100.00% | 12.88% | - | - | - | 1.15 | -14.78% | - | - | 12.88% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.14% | 100.00% | -27.14% | - | - | - | 0.79 | 21.34% | - | - | -27.14% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 75.04% | 100.00% | 24.96% | - | - | - | 1.33 | -33.26% | - | - | 24.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 75.04% | 100.00% | 24.96% | - | - | - | 1.33 | -33.26% | - | - | 24.96% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 155.64% | 100.00% | -55.64% | - | - | - | 0.64 | 35.75% | - | - | -55.64% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 74.49% | 100.00% | 25.51% | - | - | - | 1.34 | -34.25% | - | - | 25.51% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 105.68% | 100.00% | -5.68% | - | - | - | 0.95 | 5.37% | - | - | -5.68% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2778.33% | 100.00% | -2678.33% | - | - | - | 0.04 | 96.40% | - | - | -2678.33% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 147.88% | 100.00% | -47.88% | - | - | - | 0.68 | 32.38% | - | - | -47.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 92.80% | 100.00% | 7.20% | - | - | - | 1.08 | -7.76% | - | - | 7.20% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 74.42% | 100.00% | 25.58% | - | - | - | 1.34 | -34.36% | - | - | 25.58% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 360.94% | 100.00% | -260.94% | - | - | - | 0.28 | 72.29% | - | - | -260.94% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 69.76% | 100.00% | 30.24% | - | - | - | 1.43 | -43.36% | - | - | 30.24% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 709.59% | 100.00% | -609.59% | - | - | - | 0.14 | 85.91% | - | - | -609.59% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 230.20% | 100.00% | -130.20% | - | - | - | 0.43 | 56.56% | - | - | -130.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 841.30% | 100.00% | -741.30% | - | - | - | 0.12 | 88.11% | - | - | -741.30% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.31% | 100.00% | -23.31% | - | - | - | 0.81 | 18.91% | - | - | -23.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 91.89% | 100.00% | 8.11% | - | - | - | 1.09 | -8.83% | - | - | 8.11% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.09% | 100.00% | 26.91% | - | - | - | 1.37 | -36.82% | - | - | 26.91% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.72% | 100.00% | 59.28% | - | - | - | 2.46 | -145.56% | - | - | 59.28% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.72% | 100.00% | 59.28% | - | - | - | 2.46 | -145.56% | - | - | 59.28% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 16.94% | 100.00% | 83.06% | - | - | - | 5.90 | -490.29% | - | - | 83.06% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 81.99% | 100.00% | 18.01% | - | - | - | 1.22 | -21.97% | - | - | 18.01% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 521.84% | 100.00% | -421.84% | - | - | - | 0.19 | 80.84% | - | - | -421.84% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 495.58% | 100.00% | -395.58% | - | - | - | 0.20 | 79.82% | - | - | -395.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 495.58% | 100.00% | -395.58% | - | - | - | 0.20 | 79.82% | - | - | -395.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIQUIDO ATRAPA POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 132.50% | 100.00% | -32.50% | - | - | - | 0.75 | 24.53% | - | - | -32.50% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 150.12% | 100.00% | -50.12% | - | - | - | 0.67 | 33.39% | - | - | -50.12% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 150.12% | 100.00% | -50.12% | - | - | - | 0.67 | 33.39% | - | - | -50.12% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 150.12% | 100.00% | -50.12% | - | - | - | 0.67 | 33.39% | - | - | -50.12% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 123.14% | 100.00% | -23.14% | - | - | - | 0.81 | 18.79% | - | - | -23.14% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 117.34% | 100.00% | -17.34% | - | - | - | 0.85 | 14.78% | - | - | -17.34% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.37% | 100.00% | -3.37% | - | - | - | 0.97 | 3.26% | - | - | -3.37% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.23% | 100.00% | 15.77% | - | - | - | 1.19 | -18.72% | - | - | 15.77% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 100.26% | 100.00% | -0.26% | - | - | - | 1.00 | 0.26% | - | - | -0.26% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.14% | 100.00% | -0.14% | - | - | - | 1.00 | 0.14% | - | - | -0.14% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.72% | 100.00% | 19.28% | - | - | - | 1.24 | -23.89% | - | - | 19.28% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 29.53% | 100.00% | 70.47% | - | - | - | 3.39 | -238.68% | - | - | 70.47% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 52.58% | 100.00% | 47.42% | - | - | - | 1.90 | -90.18% | - | - | 47.42% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 46.64% | 100.00% | 53.36% | - | - | - | 2.14 | -114.42% | - | - | 53.36% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 131.54% | 100.00% | -31.54% | - | - | - | 0.76 | 23.98% | - | - | -31.54% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.43% | 100.00% | -27.43% | - | - | - | 0.78 | 21.53% | - | - | -27.43% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 129.63% | 100.00% | -29.63% | - | - | - | 0.77 | 22.86% | - | - | -29.63% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.51% | 100.00% | 98.49% | - | - | - | 66.20 | -6519.75% | - | - | 98.49% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.51% | 100.00% | 98.49% | - | - | - | 66.20 | -6519.75% | - | - | 98.49% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 32.17% | 100.00% | 67.83% | - | - | - | 3.11 | -210.81% | - | - | 67.83% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 31.86% | 100.00% | 68.14% | - | - | - | 3.14 | -213.85% | - | - | 68.14% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 31.86% | 100.00% | 68.14% | - | - | - | 3.14 | -213.85% | - | - | 68.14% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 31.86% | 100.00% | 68.14% | - | - | - | 3.14 | -213.85% | - | - | 68.14% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN SPRAY
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 61.15% | 100.00% | 38.85% | - | - | - | 1.64 | -63.54% | - | - | 38.85% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 17.23% | 100.00% | 82.77% | - | - | - | 5.80 | -480.47% | - | - | 82.77% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 17.57% | 100.00% | 82.43% | - | - | - | 5.69 | -469.05% | - | - | 82.43% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 23
|
- | - | - | - | - | - | 1.30% | 1.26% | 86.05% | 100.00% | 13.95% | - | - | - | 1.16 | -16.21% | - | - | 13.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 99.04% | 100.00% | 0.96% | - | - | - | 1.01 | -0.97% | - | - | 0.96% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 109.18% | 100.00% | -9.18% | - | - | - | 0.92 | 8.41% | - | - | -9.18% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 146.36% | 100.00% | -46.36% | - | - | - | 0.68 | 31.67% | - | - | -46.36% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.49% | 100.00% | -107.49% | - | - | - | 0.48 | 51.81% | - | - | -107.49% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 110.27% | 100.00% | -10.27% | - | - | - | 0.91 | 9.31% | - | - | -10.27% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.53% | 100.00% | 37.47% | - | - | - | 1.60 | -59.92% | - | - | 37.47% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.99% | 100.00% | 4.01% | - | - | - | 1.04 | -4.17% | - | - | 4.01% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.94% | 100.00% | 41.06% | - | - | - | 1.70 | -69.67% | - | - | 41.06% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.36% | 100.00% | 22.64% | - | - | - | 1.29 | -29.27% | - | - | 22.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.36% | 100.00% | 22.64% | - | - | - | 1.29 | -29.27% | - | - | 22.64% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182.55% | 100.00% | -82.55% | - | - | - | 0.55 | 45.22% | - | - | -82.55% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 107.15% | 100.00% | -7.15% | - | - | - | 0.93 | 6.67% | - | - | -7.15% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 137.38% | 100.00% | -37.38% | - | - | - | 0.73 | 27.21% | - | - | -37.38% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6706.71% | 100.00% | -6606.71% | - | - | - | 0.01 | 98.51% | - | - | -6606.71% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 151.82% | 100.00% | -51.82% | - | - | - | 0.66 | 34.13% | - | - | -51.82% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 137.99% | 100.00% | -37.99% | - | - | - | 0.72 | 27.53% | - | - | -37.99% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.19% | 100.00% | 59.81% | - | - | - | 2.49 | -148.83% | - | - | 59.81% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 252.73% | 100.00% | -152.73% | - | - | - | 0.40 | 60.43% | - | - | -152.73% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 255.82% | 100.00% | -155.82% | - | - | - | 0.39 | 60.91% | - | - | -155.82% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 280.76% | 100.00% | -180.76% | - | - | - | 0.36 | 64.38% | - | - | -180.76% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 143.47% | 100.00% | -43.47% | - | - | - | 0.70 | 30.30% | - | - | -43.47% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 83.41% | 100.00% | 16.59% | - | - | - | 1.20 | -19.89% | - | - | 16.59% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 116.68% | 100.00% | -16.68% | - | - | - | 0.86 | 14.29% | - | - | -16.68% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.95% | 100.00% | 24.05% | - | - | - | 1.32 | -31.67% | - | - | 24.05% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.95% | 100.00% | 24.05% | - | - | - | 1.32 | -31.67% | - | - | 24.05% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 67.29% | 100.00% | 32.71% | - | - | - | 1.49 | -48.60% | - | - | 32.71% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 98.77% | 100.00% | 1.23% | - | - | - | 1.01 | -1.25% | - | - | 1.23% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 109.21% | 100.00% | -9.21% | - | - | - | 0.92 | 8.43% | - | - | -9.21% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 109.21% | 100.00% | -9.21% | - | - | - | 0.92 | 8.43% | - | - | -9.21% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 82.39% | 100.00% | 17.61% | - | - | - | 1.21 | -21.37% | - | - | 17.61% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5564.02% | 100.00% | -5464.02% | - | - | - | 0.02 | 98.20% | - | - | -5464.02% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1058.16% | 100.00% | -958.16% | - | - | - | 0.09 | 90.55% | - | - | -958.16% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1058.16% | 100.00% | -958.16% | - | - | - | 0.09 | 90.55% | - | - | -958.16% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 253.98% | 100.00% | -153.98% | - | - | - | 0.39 | 60.63% | - | - | -153.98% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 143.37% | 100.00% | -43.37% | - | - | - | 0.70 | 30.25% | - | - | -43.37% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 111.25% | 100.00% | -11.25% | - | - | - | 0.90 | 10.11% | - | - | -11.25% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 71.88 | -7088.00% | - | - | 98.61% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.45% | 100.00% | 97.55% | - | - | - | 40.89 | -3989.44% | - | - | 97.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 869.44 | -86844.00% | - | - | 99.88% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 89.16% | 100.00% | 10.84% | - | - | - | 1.12 | -12.16% | - | - | 10.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 125.94% | 100.00% | -25.94% | - | - | - | 0.79 | 20.60% | - | - | -25.94% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 94858.18% | 100.00% | -94758.18% | - | - | - | 0.00 | 99.89% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 10331.69% | 100.00% | -10231.69% | - | - | - | 0.01 | 99.03% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1194.35% | 100.00% | -1094.35% | - | - | - | 0.08 | 91.63% | - | - | -1094.35% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 570.49% | 100.00% | -470.49% | - | - | - | 0.18 | 82.47% | - | - | -470.49% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 666.51% | 100.00% | -566.51% | - | - | - | 0.15 | 85.00% | - | - | -566.51% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 308.99% | 100.00% | -208.99% | - | - | - | 0.32 | 67.64% | - | - | -208.99% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 144.16% | 100.00% | -44.16% | - | - | - | 0.69 | 30.64% | - | - | -44.16% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 127.85% | 100.00% | -27.85% | - | - | - | 0.78 | 21.78% | - | - | -27.85% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 100.94% | 100.00% | -0.94% | - | - | - | 0.99 | 0.94% | - | - | -0.94% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 19.39% | 100.00% | 80.61% | - | - | - | 5.16 | -415.73% | - | - | 80.61% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 185.93% | 100.00% | -85.93% | - | - | - | 0.54 | 46.21% | - | - | -85.93% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.27% | 100.00% | -109.27% | - | - | - | 0.48 | 52.21% | - | - | -109.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 407.89% | 100.00% | -307.89% | - | - | - | 0.25 | 75.48% | - | - | -307.89% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 116.68% | 100.00% | -16.68% | - | - | - | 0.86 | 14.29% | - | - | -16.68% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 619.67% | 100.00% | -519.67% | - | - | - | 0.16 | 83.86% | - | - | -519.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 94.39% | 100.00% | 5.61% | - | - | - | 1.06 | -5.94% | - | - | 5.61% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 63.70% | 100.00% | 36.30% | - | - | - | 1.57 | -56.99% | - | - | 36.30% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO REDONDO HIERRO NEGRO 1" CHAPA 16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 49.39% | 100.00% | 50.61% | - | - | - | 2.02 | -102.45% | - | - | 50.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 49.39% | 100.00% | 50.61% | - | - | - | 2.02 | -102.45% | - | - | 50.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.00% | 100.00% | 4.00% | - | - | - | 1.04 | -4.17% | - | - | 4.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.44% | 84.00% | 100.00% | 16.00% | - | - | - | 1.19 | -19.05% | - | - | 16.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 581.64% | 100.00% | -481.64% | - | - | - | 0.17 | 82.81% | - | - | -481.64% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 564.80% | 100.00% | -464.80% | - | - | - | 0.18 | 82.29% | - | - | -464.80% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 496.66% | 100.00% | -396.66% | - | - | - | 0.20 | 79.87% | - | - | -396.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. HERRERIA, ESTRUCTURA METALICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MANTENIMIENTO BARANDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO DE ALAMBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 121.92% | 100.00% | -21.92% | - | - | - | 0.82 | 17.98% | - | - | -21.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 175.97% | 100.00% | -75.97% | - | - | - | 0.57 | 43.17% | - | - | -75.97% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 154.45% | 100.00% | -54.45% | - | - | - | 0.65 | 35.25% | - | - | -54.45% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 154.45% | 100.00% | -54.45% | - | - | - | 0.65 | 35.25% | - | - | -54.45% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 93.21% | 100.00% | 6.79% | - | - | - | 1.07 | -7.29% | - | - | 6.79% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.19% | 100.00% | 17.81% | - | - | - | 1.22 | -21.68% | - | - | 17.81% | - | 0.00% |
|
ADHESIVO NORMAL GRIS SACO DE 20 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.86% | 100.00% | -17.86% | - | - | - | 0.85 | 15.16% | - | - | -17.86% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.68% | 100.00% | -4.68% | - | - | - | 0.96 | 4.47% | - | - | -4.68% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.68% | 100.00% | -4.68% | - | - | - | 0.96 | 4.47% | - | - | -4.68% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.68% | 100.00% | -4.68% | - | - | - | 0.96 | 4.47% | - | - | -4.68% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 104.68% | 100.00% | -4.68% | - | - | - | 0.96 | 4.47% | - | - | -4.68% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.95% | 100.00% | 4.05% | - | - | - | 1.04 | -4.22% | - | - | 4.05% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.88% | 100.00% | 5.12% | - | - | - | 1.05 | -5.39% | - | - | 5.12% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.35% | 100.00% | 99.65% | - | - | - | 289.12 | -28811.52% | - | - | 99.65% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.35% | 100.00% | 99.65% | - | - | - | 289.12 | -28811.52% | - | - | 99.65% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 95.94% | 100.00% | 4.06% | - | - | - | 1.04 | -4.23% | - | - | 4.06% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 52.42% | 100.00% | 47.58% | - | - | - | 1.91 | -90.77% | - | - | 47.58% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CUBETAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 10.74% | 100.00% | 89.26% | - | - | - | 9.31 | -830.72% | - | - | 89.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 30.96% | 100.00% | 69.04% | - | - | - | 3.23 | -223.01% | - | - | 69.04% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 26.85% | 100.00% | 73.15% | - | - | - | 3.72 | -272.39% | - | - | 73.15% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.22% | 100.00% | 37.78% | - | - | - | 1.61 | -60.71% | - | - | 37.78% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.13% | 100.00% | 44.87% | - | - | - | 1.81 | -81.38% | - | - | 44.87% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.18% | 100.00% | -0.18% | - | - | - | 1.00 | 0.18% | - | - | -0.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1.66% | 100.00% | 98.34% | - | - | - | 60.41 | -5940.57% | - | - | 98.34% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.38% | 100.00% | 95.62% | - | - | - | 22.81 | -2181.49% | - | - | 95.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.34% | 100.00% | 95.66% | - | - | - | 23.02 | -2202.22% | - | - | 95.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 41
|
- | - | - | - | - | - | 1.30% | 1.33% | 70.91% | 83.42% | 12.51% | - | - | - | 1.18 | -17.64% | - | - | 15.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.46% | 53.97% | 58.82% | 4.85% | - | - | - | 1.09 | -8.98% | - | - | 8.24% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.10% | 85.45% | 100.00% | 14.55% | - | - | - | 1.17 | -17.03% | - | - | 14.55% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 87.89% | 100.00% | 12.11% | - | - | - | 1.14 | -13.78% | - | - | 12.11% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2500.17% | 100.00% | -2400.17% | - | - | - | 0.04 | 96.00% | - | - | -2400.17% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 2500.17% | 100.00% | -2400.17% | - | - | - | 0.04 | 96.00% | - | - | -2400.17% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 30004.72 | -3000372.33% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 30004.72 | -3000372.33% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.01% | 100.00% | 83.99% | - | - | - | 6.25 | -524.69% | - | - | 83.99% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.01% | 100.00% | 83.99% | - | - | - | 6.25 | -524.69% | - | - | 83.99% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.01% | 100.00% | 83.99% | - | - | - | 6.25 | -524.69% | - | - | 83.99% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.20% | 100.00% | 18.80% | - | - | - | 1.23 | -23.16% | - | - | 18.80% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.20% | 100.00% | 18.80% | - | - | - | 1.23 | -23.16% | - | - | 18.80% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.20% | 100.00% | 18.80% | - | - | - | 1.23 | -23.16% | - | - | 18.80% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.20% | 100.00% | 18.80% | - | - | - | 1.23 | -23.16% | - | - | 18.80% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.07% | 53.32% | 100.00% | 46.68% | - | - | - | 1.88 | -87.54% | - | - | 46.68% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 80.90% | 100.00% | 19.10% | - | - | - | 1.24 | -23.61% | - | - | 19.10% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 80.90% | 100.00% | 19.10% | - | - | - | 1.24 | -23.61% | - | - | 19.10% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 519.63 | -51863.18% | - | - | 99.81% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2209.01 | -220801.18% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 78.42% | 100.00% | 21.58% | - | - | - | 1.28 | -27.51% | - | - | 21.58% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 490.45 | -48945.18% | - | - | 99.80% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7605.52 | -760452.18% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.57% | 100.00% | 68.43% | - | - | - | 3.17 | -216.73% | - | - | 68.43% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 14465.91% | 100.00% | -14365.91% | - | - | - | 0.01 | 99.31% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 1256.82% | 100.00% | -1156.82% | - | - | - | 0.08 | 92.04% | - | - | -1156.82% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 5752.20% | 100.00% | -5652.20% | - | - | - | 0.02 | 98.26% | - | - | -5652.20% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 1005.75% | 100.00% | -905.75% | - | - | - | 0.10 | 90.06% | - | - | -905.75% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6952.60 | -695160.18% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6952.60 | -695160.18% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6952.60 | -695160.18% | - | - | 99.99% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 6.52% | 100.00% | 93.48% | - | - | - | 15.33 | -1433.48% | - | - | 93.48% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 194.17% | 100.00% | -94.17% | - | - | - | 0.52 | 48.50% | - | - | -94.17% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 194.17% | 100.00% | -94.17% | - | - | - | 0.52 | 48.50% | - | - | -94.17% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 175.38% | 100.00% | -75.38% | - | - | - | 0.57 | 42.98% | - | - | -75.38% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 212.96% | 100.00% | -112.96% | - | - | - | 0.47 | 53.04% | - | - | -112.96% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3445.60 | -344460.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3445.60 | -344460.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3445.60 | -344460.00% | - | - | 99.97% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.75% | 0.00% | -60.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.75% | 0.00% | -60.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.75% | 0.00% | -60.75% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.07% | 62.70% | 0.00% | -62.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.07% | 62.70% | 0.00% | -62.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.07% | 62.70% | 0.00% | -62.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.07% | 62.70% | 0.00% | -62.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2215.73 | -221473.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2215.73 | -221473.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2215.73 | -221473.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2215.73 | -221473.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.65% | 88.92% | 100.00% | 11.08% | - | - | - | 1.12 | -12.46% | - | - | 11.08% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.19% | 99.03% | 100.00% | 0.97% | - | - | - | 1.01 | -0.98% | - | - | 0.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.11% | 134.55% | 100.00% | -34.55% | - | - | - | 0.74 | 25.68% | - | - | -34.55% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 188.33% | 100.00% | -88.33% | - | - | - | 0.53 | 46.90% | - | - | -88.33% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9544.98 | -954397.94% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 15216.53% | 100.00% | -15116.53% | - | - | - | 0.01 | 99.34% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7183.26 | -718225.94% | - | - | 99.99% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 112.53% | 100.00% | -12.53% | - | - | - | 0.89 | 11.13% | - | - | -12.53% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 225.30% | 100.00% | -125.30% | - | - | - | 0.44 | 55.61% | - | - | -125.30% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 210.09 | -20908.94% | - | - | 99.52% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.04% | 112.02% | 100.00% | -12.02% | - | - | - | 0.89 | 10.73% | - | - | -12.02% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 115.24% | 100.00% | -15.24% | - | - | - | 0.87 | 13.22% | - | - | -15.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 249.51 | -24850.94% | - | - | 99.60% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 49.40% | 100.00% | 50.60% | - | - | - | 2.02 | -102.41% | - | - | 50.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 754.90 | -75389.94% | - | - | 99.87% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 222.92% | 100.00% | -122.92% | - | - | - | 0.45 | 55.14% | - | - | -122.92% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 331.02 | -33001.94% | - | - | 99.70% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 343.34 | -34233.94% | - | - | 99.71% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 197.98% | 100.00% | -97.98% | - | - | - | 0.51 | 49.49% | - | - | -97.98% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.35% | 100.00% | 97.65% | - | - | - | 42.61 | -4160.96% | - | - | 97.65% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.39% | 100.00% | 97.61% | - | - | - | 41.76 | -4076.08% | - | - | 97.61% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.32% | 100.00% | -10.32% | - | - | - | 0.91 | 9.35% | - | - | -10.32% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 57.08% | 100.00% | 42.92% | - | - | - | 1.75 | -75.18% | - | - | 42.92% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 503.85 | -50284.94% | - | - | 99.80% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 128.79% | 100.00% | -28.79% | - | - | - | 0.78 | 22.36% | - | - | -28.79% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.93% | 100.00% | 57.07% | - | - | - | 2.33 | -132.93% | - | - | 57.07% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 128.79% | 100.00% | -28.79% | - | - | - | 0.78 | 22.36% | - | - | -28.79% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 122.11% | 100.00% | -22.11% | - | - | - | 0.82 | 18.11% | - | - | -22.11% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 209.69 | -20868.94% | - | - | 99.52% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 232.25 | -23124.94% | - | - | 99.57% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 232.25 | -23124.94% | - | - | 99.57% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 429.27 | -42826.89% | - | - | 99.77% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 218.93 | -21792.94% | - | - | 99.54% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 210.34 | -20933.94% | - | - | 99.52% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1181.87 | -118086.83% | - | - | 99.92% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 357.70 | -35669.94% | - | - | 99.72% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 292.62 | -29161.94% | - | - | 99.66% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 531.55 | -53054.94% | - | - | 99.81% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1994.32 | -199331.89% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1137.78 | -113677.94% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 856.54 | -85553.94% | - | - | 99.88% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 54.24% | 100.00% | 45.76% | - | - | - | 1.84 | -84.35% | - | - | 45.76% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 54.24% | 100.00% | 45.76% | - | - | - | 1.84 | -84.35% | - | - | 45.76% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 5915.00% | 100.00% | -5815.00% | - | - | - | 0.02 | 98.31% | - | - | -5815.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 454.65% | 100.00% | -354.65% | - | - | - | 0.22 | 78.00% | - | - | -354.65% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2817.63 | -281662.94% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21380.27 | -2137926.94% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1247.02 | -124601.94% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1247.02 | -124601.94% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1247.02 | -124601.94% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.16% | 96.49% | 100.00% | 3.51% | - | - | - | 1.04 | -3.63% | - | - | 3.51% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 101.58% | 100.00% | -1.58% | - | - | - | 0.98 | 1.55% | - | - | -1.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 101.58% | 100.00% | -1.58% | - | - | - | 0.98 | 1.55% | - | - | -1.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 45774.75% | 100.00% | -45674.75% | - | - | - | 0.00 | 99.78% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3712.15 | -371114.91% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 7455.17% | 100.00% | -7355.17% | - | - | - | 0.01 | 98.66% | - | - | -7355.17% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1563.56 | -156255.91% | - | - | 99.94% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24677.58 | -2467657.91% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 89.77% | 100.00% | 10.23% | - | - | - | 1.11 | -11.40% | - | - | 10.23% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 804.59% | 100.00% | -704.59% | - | - | - | 0.12 | 87.57% | - | - | -704.59% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 804.59% | 100.00% | -704.59% | - | - | - | 0.12 | 87.57% | - | - | -704.59% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 289.40% | 100.00% | -189.40% | - | - | - | 0.35 | 65.45% | - | - | -189.40% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.84 | -7983.91% | - | - | 98.76% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 697.12% | 100.00% | -597.12% | - | - | - | 0.14 | 85.66% | - | - | -597.12% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 281.71% | 100.00% | -181.71% | - | - | - | 0.35 | 64.50% | - | - | -181.71% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 140.97 | -13996.91% | - | - | 99.29% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 133.19% | 100.00% | -33.19% | - | - | - | 0.75 | 24.92% | - | - | -33.19% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2078.69% | 100.00% | -1978.69% | - | - | - | 0.05 | 95.19% | - | - | -1978.69% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 4373.72% | 100.00% | -4273.72% | - | - | - | 0.02 | 97.71% | - | - | -4273.72% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 177.54% | 100.00% | -77.54% | - | - | - | 0.56 | 43.67% | - | - | -77.54% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 177.54% | 100.00% | -77.54% | - | - | - | 0.56 | 43.67% | - | - | -77.54% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 114.06% | 100.00% | -14.06% | - | - | - | 0.88 | 12.33% | - | - | -14.06% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1723.36 | -172235.91% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 3539.95% | 100.00% | -3439.95% | - | - | - | 0.03 | 97.18% | - | - | -3439.95% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 55.94% | 100.00% | 44.06% | - | - | - | 1.79 | -78.77% | - | - | 44.06% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.50% | 100.00% | 85.50% | - | - | - | 6.90 | -589.84% | - | - | 85.50% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 68.62 | -6761.91% | - | - | 98.54% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 929.33% | 100.00% | -829.33% | - | - | - | 0.11 | 89.24% | - | - | -829.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 637.67% | 100.00% | -537.67% | - | - | - | 0.16 | 84.32% | - | - | -537.67% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 456.49% | 100.00% | -356.49% | - | - | - | 0.22 | 78.09% | - | - | -356.49% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.87% | 100.00% | 57.13% | - | - | - | 2.33 | -133.25% | - | - | 57.13% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.44% | 100.00% | -3.44% | - | - | - | 0.97 | 3.32% | - | - | -3.44% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.99% | 100.00% | 31.01% | - | - | - | 1.45 | -44.94% | - | - | 31.01% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1787.47 | -178646.91% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 18.72% | 100.00% | 81.28% | - | - | - | 5.34 | -434.14% | - | - | 81.28% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 920.24 | -91923.91% | - | - | 99.89% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 339.84% | 100.00% | -239.84% | - | - | - | 0.29 | 70.57% | - | - | -239.84% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 63.96 | -6295.91% | - | - | 98.44% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 67.21 | -6620.91% | - | - | 98.51% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 67.21 | -6620.91% | - | - | 98.51% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 140.69 | -13968.82% | - | - | 99.29% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 76.56 | -7555.91% | - | - | 98.69% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 64.13 | -6312.91% | - | - | 98.44% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 738.17 | -73716.91% | - | - | 99.86% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 738.17 | -73716.91% | - | - | 99.86% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9396.42 | -939541.82% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 138.05 | -13704.91% | - | - | 99.28% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9258.37 | -925736.91% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 213.36 | -21235.91% | - | - | 99.53% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 213.36 | -21235.91% | - | - | 99.53% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 213.36 | -21235.91% | - | - | 99.53% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 90.12% | 100.00% | 9.88% | - | - | - | 1.11 | -10.96% | - | - | 9.88% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 171.20% | 100.00% | -71.20% | - | - | - | 0.58 | 41.59% | - | - | -71.20% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 241.92% | 100.00% | -141.92% | - | - | - | 0.41 | 58.66% | - | - | -141.92% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.43% | 100.00% | -102.43% | - | - | - | 0.49 | 50.60% | - | - | -102.43% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 138.55% | 100.00% | -38.55% | - | - | - | 0.72 | 27.83% | - | - | -38.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 70.85% | 100.00% | 29.15% | - | - | - | 1.41 | -41.14% | - | - | 29.15% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.96% | 100.00% | 6.04% | - | - | - | 1.06 | -6.43% | - | - | 6.04% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.29% | 100.00% | -27.29% | - | - | - | 0.79 | 21.44% | - | - | -27.29% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.22% | 74.45% | 100.00% | 25.55% | - | - | - | 1.34 | -34.31% | - | - | 25.55% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.12% | 117.59% | 100.00% | -17.59% | - | - | - | 0.85 | 14.96% | - | - | -17.59% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 369.43% | 100.00% | -269.43% | - | - | - | 0.27 | 72.93% | - | - | -269.43% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 151.74 | -15073.57% | - | - | 99.34% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 740.21% | 100.00% | -640.21% | - | - | - | 0.14 | 86.49% | - | - | -640.21% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 169.49% | 100.00% | -69.49% | - | - | - | 0.59 | 41.00% | - | - | -69.49% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 162.52 | -16151.57% | - | - | 99.38% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 350.65% | 100.00% | -250.65% | - | - | - | 0.29 | 71.48% | - | - | -250.65% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 140.91% | 100.00% | -40.91% | - | - | - | 0.71 | 29.03% | - | - | -40.91% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 104.60% | 100.00% | -4.60% | - | - | - | 0.96 | 4.40% | - | - | -4.60% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 199.91 | -19890.57% | - | - | 99.50% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 105.61% | 100.00% | -5.61% | - | - | - | 0.95 | 5.31% | - | - | -5.61% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 817.62 | -81661.57% | - | - | 99.88% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.59% | 100.00% | -142.59% | - | - | - | 0.41 | 58.78% | - | - | -142.59% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.95% | 100.00% | -3.95% | - | - | - | 0.96 | 3.80% | - | - | -3.95% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 139.02% | 100.00% | -39.02% | - | - | - | 0.72 | 28.07% | - | - | -39.02% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 267.06% | 100.00% | -167.06% | - | - | - | 0.37 | 62.56% | - | - | -167.06% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.76% | 100.00% | 90.24% | - | - | - | 10.24 | -924.29% | - | - | 90.24% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.95% | 100.00% | 90.05% | - | - | - | 10.05 | -904.56% | - | - | 90.05% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 401.15% | 100.00% | -301.15% | - | - | - | 0.25 | 75.07% | - | - | -301.15% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.07% | 123.87% | 100.00% | -23.87% | - | - | - | 0.81 | 19.27% | - | - | -23.87% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11561.05 | -1156004.57% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 16703.99% | 100.00% | -16603.99% | - | - | - | 0.01 | 99.40% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8674.50 | -867349.57% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.67% | 100.00% | 62.33% | - | - | - | 2.65 | -165.49% | - | - | 62.33% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 510.78 | -50977.57% | - | - | 99.80% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 158.75% | 100.00% | -58.75% | - | - | - | 0.63 | 37.01% | - | - | -58.75% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.23% | 100.00% | 95.77% | - | - | - | 23.62 | -2262.28% | - | - | 95.77% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.74% | 100.00% | 46.26% | - | - | - | 1.86 | -86.07% | - | - | 46.26% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.26% | 100.00% | 95.74% | - | - | - | 23.48 | -2247.60% | - | - | 95.74% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.29% | 100.00% | -32.29% | - | - | - | 0.76 | 24.41% | - | - | -32.29% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 151.25 | -15024.57% | - | - | 99.34% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 178.82 | -17781.57% | - | - | 99.44% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 178.82 | -17781.57% | - | - | 99.44% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1129.37 | -112836.71% | - | - | 99.91% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 332.15 | -33114.57% | - | - | 99.70% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 252.60 | -25159.57% | - | - | 99.60% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 544.63 | -54362.57% | - | - | 99.82% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2227.45 | -222645.14% | - | - | 99.96% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1285.62 | -128461.57% | - | - | 99.92% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 941.84 | -94083.57% | - | - | 99.89% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 20.77% | 100.00% | 79.23% | - | - | - | 4.81 | -381.42% | - | - | 79.23% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 20.77% | 100.00% | 79.23% | - | - | - | 4.81 | -381.42% | - | - | 79.23% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 4055.34% | 100.00% | -3955.34% | - | - | - | 0.02 | 97.53% | - | - | -3955.34% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3338.73 | -333772.57% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 26026.40 | -2602539.57% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1419.10 | -141809.57% | - | - | 99.93% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1419.10 | -141809.57% | - | - | 99.93% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1419.10 | -141809.57% | - | - | 99.93% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.23% | 53.94% | 86.12% | 32.18% | - | - | - | 1.60 | -59.67% | - | - | 37.37% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.20% | 88.00% | -13.20% | - | - | - | 0.87 | 13.05% | - | - | -15.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 104.63% | 88.00% | -16.63% | - | - | - | 0.84 | 15.89% | - | - | -18.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1091.44% | 88.00% | -1003.44% | - | - | - | 0.08 | 91.94% | - | - | -1140.27% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 1125.67% | 88.00% | -1037.67% | - | - | - | 0.08 | 92.18% | - | - | -1179.17% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 1057.20% | 88.00% | -969.20% | - | - | - | 0.08 | 91.68% | - | - | -1101.36% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 99.75% | 88.00% | -11.75% | - | - | - | 0.88 | 11.78% | - | - | -13.36% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 99.75% | 88.00% | -11.75% | - | - | - | 0.88 | 11.78% | - | - | -13.36% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.73% | 88.00% | 73.27% | - | - | - | 5.97 | -497.39% | - | - | 83.26% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.14% | 88.00% | 8.86% | - | - | - | 1.11 | -11.20% | - | - | 10.07% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.59% | 88.00% | -41.59% | - | - | - | 0.68 | 32.09% | - | - | -47.26% | - | 0.00% |
|
COPLA PVC GRIS DE 2" ELECTRICIDAD
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.66% | 88.00% | 71.34% | - | - | - | 5.28 | -428.21% | - | - | 81.07% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 91.17% | 88.00% | -3.17% | - | - | - | 0.97 | 3.48% | - | - | -3.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1025.43 | -102443.38% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1025.43 | -102443.38% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.11% | 0.69% | 84.00% | 83.31% | - | - | - | 121.09 | -12009.13% | - | - | 99.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16.90% | 84.00% | 67.10% | - | - | - | 4.97 | -397.14% | - | - | 79.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 128.23% | 84.00% | -44.23% | - | - | - | 0.66 | 34.49% | - | - | -52.65% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 128.23% | 84.00% | -44.23% | - | - | - | 0.66 | 34.49% | - | - | -52.65% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 39.46% | 84.00% | 44.54% | - | - | - | 2.13 | -112.90% | - | - | 53.03% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 39.46% | 84.00% | 44.54% | - | - | - | 2.13 | -112.90% | - | - | 53.03% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 918.59 | -91758.62% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 918.59 | -91758.62% | - | - | 99.89% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26871.31 | -2687031.02% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26871.31 | -2687031.02% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26871.31 | -2687031.02% | - | - | 100.00% | - | 0.00% |
|
CASA # 46
|
- | - | - | - | - | - | 1.30% | 1.31% | 42.09% | 49.80% | 7.71% | - | - | - | 1.18 | -18.32% | - | - | 15.49% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 80.70% | 74.29% | -6.41% | - | - | - | 0.92 | 7.94% | - | - | -8.63% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 111.70% | 100.00% | -11.70% | - | - | - | 0.90 | 10.47% | - | - | -11.70% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 171.72% | 100.00% | -71.72% | - | - | - | 0.58 | 41.77% | - | - | -71.72% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 12512.51% | 100.00% | -12412.51% | - | - | - | 0.01 | 99.20% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 277.85% | 100.00% | -177.85% | - | - | - | 0.36 | 64.01% | - | - | -177.85% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 181.52% | 100.00% | -81.52% | - | - | - | 0.55 | 44.91% | - | - | -81.52% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 218.52% | 100.00% | -118.52% | - | - | - | 0.46 | 54.24% | - | - | -118.52% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 35.44% | 100.00% | 64.56% | - | - | - | 2.82 | -182.20% | - | - | 64.56% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 513.08% | 100.00% | -413.08% | - | - | - | 0.19 | 80.51% | - | - | -413.08% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.20% | 100.00% | -120.20% | - | - | - | 0.45 | 54.59% | - | - | -120.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 631.67% | 100.00% | -531.67% | - | - | - | 0.16 | 84.17% | - | - | -531.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 179.22% | 100.00% | -79.22% | - | - | - | 0.56 | 44.20% | - | - | -79.22% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 45.32% | 100.00% | 54.68% | - | - | - | 2.21 | -120.63% | - | - | 54.68% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 45.32% | 100.00% | 54.68% | - | - | - | 2.21 | -120.63% | - | - | 54.68% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 103.85% | 100.00% | -3.85% | - | - | - | 0.96 | 3.71% | - | - | -3.85% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 195.16% | 100.00% | -95.16% | - | - | - | 0.51 | 48.76% | - | - | -95.16% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2127.01% | 100.00% | -2027.01% | - | - | - | 0.05 | 95.30% | - | - | -2027.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 218.38% | 100.00% | -118.38% | - | - | - | 0.46 | 54.21% | - | - | -118.38% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 201.20% | 100.00% | -101.20% | - | - | - | 0.50 | 50.30% | - | - | -101.20% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 102.74% | 100.00% | -2.74% | - | - | - | 0.97 | 2.67% | - | - | -2.74% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 49.10% | 100.00% | 50.90% | - | - | - | 2.04 | -103.65% | - | - | 50.90% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 173.72% | 100.00% | -73.72% | - | - | - | 0.58 | 42.44% | - | - | -73.72% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 402.70% | 100.00% | -302.70% | - | - | - | 0.25 | 75.17% | - | - | -302.70% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1480.53% | 100.00% | -1380.53% | - | - | - | 0.07 | 93.25% | - | - | -1380.53% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 75.56% | 100.00% | 24.44% | - | - | - | 1.32 | -32.35% | - | - | 24.44% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 93.77% | 100.00% | 6.23% | - | - | - | 1.07 | -6.64% | - | - | 6.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 182.47% | 100.00% | -82.47% | - | - | - | 0.55 | 45.20% | - | - | -82.47% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 103.51% | 100.00% | -3.51% | - | - | - | 0.97 | 3.39% | - | - | -3.51% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.73% | 100.00% | 7.27% | - | - | - | 1.08 | -7.85% | - | - | 7.27% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.74% | 100.00% | 12.26% | - | - | - | 1.14 | -13.97% | - | - | 12.26% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.04% | 100.00% | -27.04% | - | - | - | 0.79 | 21.29% | - | - | -27.04% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 87.19% | 100.00% | 12.81% | - | - | - | 1.15 | -14.69% | - | - | 12.81% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 9.82% | 0.00% | -9.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.13% | 0.00% | -6.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 37.22% | 0.00% | -37.22% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 4983.98% | 0.00% | -4983.98% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 467.79% | 0.00% | -467.79% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 1623.17% | 0.00% | -1623.17% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.47% | 0.00% | -2.47% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 84.94% | 0.00% | -84.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 12.15% | 0.00% | -12.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.10% | 12.15% | 0.00% | -12.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 22722.13% | 0.00% | -22722.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.24% | 9.75% | 86.05% | 76.30% | - | - | - | 8.83 | -782.82% | - | - | 88.67% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.12% | 17.20% | 84.00% | 66.80% | - | - | - | 4.88 | -388.25% | - | - | 79.52% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 141.86% | 84.00% | -57.86% | - | - | - | 0.59 | 40.79% | - | - | -68.89% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 238.68% | 84.00% | -154.68% | - | - | - | 0.35 | 64.81% | - | - | -184.14% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 122.06% | 84.00% | -38.06% | - | - | - | 0.69 | 31.18% | - | - | -45.31% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 113.78% | 84.00% | -29.78% | - | - | - | 0.74 | 26.18% | - | - | -35.46% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 139.30% | 84.00% | -55.30% | - | - | - | 0.60 | 39.70% | - | - | -65.83% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 258.60% | 84.00% | -174.60% | - | - | - | 0.32 | 67.52% | - | - | -207.86% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 775.80% | 84.00% | -691.80% | - | - | - | 0.11 | 89.17% | - | - | -823.57% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.00% | 0.00% | 227.57% | 84.00% | -143.57% | - | - | - | 0.37 | 63.09% | - | - | -170.91% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 50.69% | 84.00% | 33.31% | - | - | - | 1.66 | -65.73% | - | - | 39.66% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 315.49% | 84.00% | -231.49% | - | - | - | 0.27 | 73.37% | - | - | -275.59% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 144.82% | 84.00% | -60.82% | - | - | - | 0.58 | 42.00% | - | - | -72.40% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 10.84% | 84.00% | 73.16% | - | - | - | 7.75 | -675.24% | - | - | 87.10% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 18.77% | 84.00% | 65.23% | - | - | - | 4.47 | -347.42% | - | - | 77.65% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.90% | 84.00% | 81.10% | - | - | - | 29.00 | -2800.23% | - | - | 96.55% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 1046.28 | -104528.14% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 1046.28 | -104528.14% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26999.01 | -2699800.54% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26999.01 | -2699800.54% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26999.01 | -2699800.54% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.68% | 88.00% | 85.32% | - | - | - | 32.81 | -3180.91% | - | - | 96.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.72% | 88.00% | 85.28% | - | - | - | 32.30 | -3130.12% | - | - | 96.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.42% | 88.00% | -154.42% | - | - | - | 0.36 | 63.70% | - | - | -175.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 242.42% | 88.00% | -154.42% | - | - | - | 0.36 | 63.70% | - | - | -175.48% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.12% | 0.00% | 88.00% | 88.00% | - | - | - | 31938.18 | -3193718.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.12% | 0.00% | 88.00% | 88.00% | - | - | - | 31938.18 | -3193718.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.01% | 1.87% | 88.00% | 86.13% | - | - | - | 47.11 | -4610.75% | - | - | 97.88% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.61% | 88.00% | 79.39% | - | - | - | 10.22 | -921.96% | - | - | 90.21% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.61% | 88.00% | 79.39% | - | - | - | 10.22 | -921.96% | - | - | 90.21% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1310.26 | -130925.84% | - | - | 99.92% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 1310.26 | -130925.84% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.47% | 9.24% | 0.00% | -9.24% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 22
|
- | - | - | - | - | - | 1.30% | 1.26% | 83.69% | 100.00% | 16.31% | - | - | - | 1.19 | -19.48% | - | - | 16.31% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 95.96% | 100.00% | 4.04% | - | - | - | 1.04 | -4.21% | - | - | 4.04% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 115.26% | 100.00% | -15.26% | - | - | - | 0.87 | 13.24% | - | - | -15.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 158.19% | 100.00% | -58.19% | - | - | - | 0.63 | 36.79% | - | - | -58.19% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 170786.52% | 100.00% | -170686.52% | - | - | - | 0.00 | 99.94% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 230303.03% | 100.00% | -230203.03% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.49% | 100.00% | -107.49% | - | - | - | 0.48 | 51.81% | - | - | -107.49% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 110.27% | 100.00% | -10.27% | - | - | - | 0.91 | 9.31% | - | - | -10.27% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.53% | 100.00% | 37.47% | - | - | - | 1.60 | -59.92% | - | - | 37.47% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.99% | 100.00% | 4.01% | - | - | - | 1.04 | -4.17% | - | - | 4.01% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.36% | 100.00% | 22.64% | - | - | - | 1.29 | -29.27% | - | - | 22.64% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.36% | 100.00% | 22.64% | - | - | - | 1.29 | -29.27% | - | - | 22.64% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182.55% | 100.00% | -82.55% | - | - | - | 0.55 | 45.22% | - | - | -82.55% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 111.87% | 100.00% | -11.87% | - | - | - | 0.89 | 10.61% | - | - | -11.87% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 140.57% | 100.00% | -40.57% | - | - | - | 0.71 | 28.86% | - | - | -40.57% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 80000.00% | 100.00% | -79900.00% | - | - | - | 0.00 | 99.88% | - | - | 0.00% | - | 0.00% |
|
PLANIGROUT 755
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6706.71% | 100.00% | -6606.71% | - | - | - | 0.01 | 98.51% | - | - | -6606.71% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 528.43% | 100.00% | -428.43% | - | - | - | 0.19 | 81.08% | - | - | -428.43% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 1973.50% | 100.00% | -1873.50% | - | - | - | 0.05 | 94.93% | - | - | -1873.50% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 150.66% | 100.00% | -50.66% | - | - | - | 0.66 | 33.63% | - | - | -50.66% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 69.51% | 100.00% | 30.49% | - | - | - | 1.44 | -43.86% | - | - | 30.49% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 33.50% | 100.00% | 66.50% | - | - | - | 2.99 | -198.52% | - | - | 66.50% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 147.35% | 100.00% | -47.35% | - | - | - | 0.68 | 32.14% | - | - | -47.35% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 113.30% | 100.00% | -13.30% | - | - | - | 0.88 | 11.74% | - | - | -13.30% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 137.99% | 100.00% | -37.99% | - | - | - | 0.72 | 27.53% | - | - | -37.99% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 33.61% | 100.00% | 66.39% | - | - | - | 2.98 | -197.53% | - | - | 66.39% | - | 0.00% |
|
ACERO DE 1/2 X 12 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.05% | 100.00% | -43.05% | - | - | - | 0.70 | 30.09% | - | - | -43.05% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 83.07% | 100.00% | 16.93% | - | - | - | 1.20 | -20.38% | - | - | 16.93% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 82.68% | 100.00% | 17.32% | - | - | - | 1.21 | -20.95% | - | - | 17.32% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 82.68% | 100.00% | 17.32% | - | - | - | 1.21 | -20.95% | - | - | 17.32% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 72.47% | 100.00% | 27.53% | - | - | - | 1.38 | -37.99% | - | - | 27.53% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 97.25% | 100.00% | 2.75% | - | - | - | 1.03 | -2.83% | - | - | 2.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 141.67% | 100.00% | -41.67% | - | - | - | 0.71 | 29.41% | - | - | -41.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27087.27% | 100.00% | -26987.27% | - | - | - | 0.00 | 99.63% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 16143.19% | 100.00% | -16043.19% | - | - | - | 0.01 | 99.38% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1324.19% | 100.00% | -1224.19% | - | - | - | 0.08 | 92.45% | - | - | -1224.19% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 2086.51% | 100.00% | -1986.51% | - | - | - | 0.05 | 95.21% | - | - | -1986.51% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 395.19% | 100.00% | -295.19% | - | - | - | 0.25 | 74.70% | - | - | -295.19% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 138.13% | 100.00% | -38.13% | - | - | - | 0.72 | 27.60% | - | - | -38.13% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 123.59% | 100.00% | -23.59% | - | - | - | 0.81 | 19.09% | - | - | -23.59% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 83.12% | 100.00% | 16.88% | - | - | - | 1.20 | -20.31% | - | - | 16.88% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 23.54% | 100.00% | 76.46% | - | - | - | 4.25 | -324.72% | - | - | 76.46% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 134.97% | 100.00% | -34.97% | - | - | - | 0.74 | 25.91% | - | - | -34.97% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 348.78% | 100.00% | -248.78% | - | - | - | 0.29 | 71.33% | - | - | -248.78% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 540.82% | 100.00% | -440.82% | - | - | - | 0.18 | 81.51% | - | - | -440.82% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 94.26% | 100.00% | 5.74% | - | - | - | 1.06 | -6.08% | - | - | 5.74% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 703.16% | 100.00% | -603.16% | - | - | - | 0.14 | 85.78% | - | - | -603.16% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 91.66% | 100.00% | 8.34% | - | - | - | 1.09 | -9.09% | - | - | 8.34% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 160.14% | 100.00% | -60.14% | - | - | - | 0.62 | 37.55% | - | - | -60.14% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO REDONDO HIERRO NEGRO 1" CHAPA 16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.78% | 100.00% | 51.22% | - | - | - | 2.05 | -105.02% | - | - | 51.22% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.78% | 100.00% | 51.22% | - | - | - | 2.05 | -105.02% | - | - | 51.22% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 90.35% | 100.00% | 9.65% | - | - | - | 1.11 | -10.68% | - | - | 9.65% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 67.80% | 100.00% | 32.20% | - | - | - | 1.48 | -47.50% | - | - | 32.20% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 82.96% | 100.00% | 17.04% | - | - | - | 1.21 | -20.54% | - | - | 17.04% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 82.96% | 100.00% | 17.04% | - | - | - | 1.21 | -20.54% | - | - | 17.04% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 43.36% | 100.00% | 56.64% | - | - | - | 2.31 | -130.61% | - | - | 56.64% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2095.48% | 100.00% | -1995.48% | - | - | - | 0.05 | 95.23% | - | - | -1995.48% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 149.80% | 100.00% | -49.80% | - | - | - | 0.67 | 33.24% | - | - | -49.80% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.13% | 100.00% | 12.87% | - | - | - | 1.15 | -14.78% | - | - | 12.87% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1867.15% | 100.00% | -1767.15% | - | - | - | 0.05 | 94.64% | - | - | -1767.15% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 131.06% | 100.00% | -31.06% | - | - | - | 0.76 | 23.70% | - | - | -31.06% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA EN POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MALLA GALVANIZADA MAS ESTRUCTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.18% | 100.00% | 11.82% | - | - | - | 1.13 | -13.40% | - | - | 11.82% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 88.18% | 100.00% | 11.82% | - | - | - | 1.13 | -13.40% | - | - | 11.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 16.79% | 100.00% | 83.21% | - | - | - | 5.96 | -495.75% | - | - | 83.21% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 1 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.44% | 81.35% | 100.00% | 18.65% | - | - | - | 1.23 | -22.92% | - | - | 18.65% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 185.33% | 100.00% | -85.33% | - | - | - | 0.54 | 46.04% | - | - | -85.33% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 146.61% | 100.00% | -46.61% | - | - | - | 0.68 | 31.79% | - | - | -46.61% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 146.61% | 100.00% | -46.61% | - | - | - | 0.68 | 31.79% | - | - | -46.61% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIQUIDO ATRAPA POLVO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SQUEEGEE LIMPIADOR DE VIDRIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 117.36% | 100.00% | -17.36% | - | - | - | 0.85 | 14.79% | - | - | -17.36% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 112.29% | 100.00% | -12.29% | - | - | - | 0.89 | 10.94% | - | - | -12.29% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 112.29% | 100.00% | -12.29% | - | - | - | 0.89 | 10.94% | - | - | -12.29% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 76.29% | 100.00% | 23.71% | - | - | - | 1.31 | -31.08% | - | - | 23.71% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 116.49% | 100.00% | -16.49% | - | - | - | 0.86 | 14.16% | - | - | -16.49% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 100.00% | 5.46% | - | - | - | 1.06 | -5.78% | - | - | 5.46% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA 4" INOXIDABLE MANGO DE PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAMENT-1 ADITIVO ACELERANTE P/CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTENSION ELECTRICA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICON BLANCO 10.1Z ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BANDEJA PARA PINTURA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINCEL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 240 P/AGUA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SELLADOR ACRILICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 102.66% | 100.00% | -2.66% | - | - | - | 0.97 | 2.60% | - | - | -2.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 135.66% | 100.00% | -35.66% | - | - | - | 0.74 | 26.29% | - | - | -35.66% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 135.66% | 100.00% | -35.66% | - | - | - | 0.74 | 26.29% | - | - | -35.66% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 135.66% | 100.00% | -35.66% | - | - | - | 0.74 | 26.29% | - | - | -35.66% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 85.13% | 100.00% | 14.87% | - | - | - | 1.17 | -17.46% | - | - | 14.87% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 81.19% | 100.00% | 18.81% | - | - | - | 1.23 | -23.16% | - | - | 18.81% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 117.86% | 100.00% | -17.86% | - | - | - | 0.85 | 15.16% | - | - | -17.86% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 97.06% | 100.00% | 2.94% | - | - | - | 1.03 | -3.03% | - | - | 2.94% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 97.06% | 100.00% | 2.94% | - | - | - | 1.03 | -3.03% | - | - | 2.94% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 97.06% | 100.00% | 2.94% | - | - | - | 1.03 | -3.03% | - | - | 2.94% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 97.06% | 100.00% | 2.94% | - | - | - | 1.03 | -3.03% | - | - | 2.94% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.58% | 100.00% | 26.42% | - | - | - | 1.36 | -35.90% | - | - | 26.42% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.31% | 100.00% | 93.69% | - | - | - | 15.84 | -1484.35% | - | - | 93.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 18.19% | 100.00% | 81.81% | - | - | - | 5.50 | -449.86% | - | - | 81.81% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 14.08% | 100.00% | 85.92% | - | - | - | 7.10 | -610.16% | - | - | 85.92% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1350.00 | -134900.00% | - | - | 99.93% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCTO PARA EXTRACTOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.27% | 100.00% | 44.73% | - | - | - | 1.81 | -80.92% | - | - | 44.73% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.34% | 100.00% | -0.34% | - | - | - | 1.00 | 0.34% | - | - | -0.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.94% | 100.00% | 93.06% | - | - | - | 14.40 | -1340.43% | - | - | 93.06% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLACA DE DOS PUERTOS BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.51% | 100.00% | 95.49% | - | - | - | 22.18 | -2118.25% | - | - | 95.49% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.99% | 100.00% | 90.01% | - | - | - | 10.01 | -901.10% | - | - | 90.01% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE GALVANIZADO CALIBRE 10
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.34% | 100.00% | 95.66% | - | - | - | 23.02 | -2202.22% | - | - | 95.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 42
|
- | - | - | - | - | - | 1.30% | 1.25% | 68.89% | 83.25% | 14.36% | - | - | - | 1.21 | -20.85% | - | - | 17.25% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 60.28% | 58.56% | -1.72% | - | - | - | 0.97 | 2.85% | - | - | -2.94% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 105.20% | 100.00% | -5.20% | - | - | - | 0.95 | 4.95% | - | - | -5.20% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 100.00% | 5.46% | - | - | - | 1.06 | -5.78% | - | - | 5.46% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 86.06% | 100.00% | 13.94% | - | - | - | 1.16 | -16.20% | - | - | 13.94% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 85.63% | 100.00% | 14.37% | - | - | - | 1.17 | -16.78% | - | - | 14.37% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 54.62% | 100.00% | 45.38% | - | - | - | 1.83 | -83.09% | - | - | 45.38% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 83.63% | 100.00% | 16.37% | - | - | - | 1.20 | -19.57% | - | - | 16.37% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 83.63% | 100.00% | 16.37% | - | - | - | 1.20 | -19.57% | - | - | 16.37% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.95% | 100.00% | 13.05% | - | - | - | 1.15 | -15.01% | - | - | 13.05% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.28% | 100.00% | 67.72% | - | - | - | 3.10 | -209.74% | - | - | 67.72% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6908.59 | -690759.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6908.59 | -690759.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6908.59 | -690759.00% | - | - | 99.99% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 25.65% | 100.00% | 74.35% | - | - | - | 3.90 | -289.84% | - | - | 74.35% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.43% | 0.00% | -79.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.43% | 0.00% | -79.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 79.43% | 0.00% | -79.43% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 70.39% | 0.00% | -70.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 92.74% | 100.00% | 7.26% | - | - | - | 1.08 | -7.83% | - | - | 7.26% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 190.61% | 100.00% | -90.61% | - | - | - | 0.52 | 47.54% | - | - | -90.61% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 342.60% | 100.00% | -242.60% | - | - | - | 0.29 | 70.81% | - | - | -242.60% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 620.40% | 100.00% | -520.40% | - | - | - | 0.16 | 83.88% | - | - | -520.40% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 587.06% | 100.00% | -487.06% | - | - | - | 0.17 | 82.97% | - | - | -487.06% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 138.39% | 100.00% | -38.39% | - | - | - | 0.72 | 27.74% | - | - | -38.39% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.00% | 100.00% | 29.00% | - | - | - | 1.41 | -40.84% | - | - | 29.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.83% | 100.00% | 6.17% | - | - | - | 1.07 | -6.58% | - | - | 6.17% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.02% | 100.00% | -27.02% | - | - | - | 0.79 | 21.27% | - | - | -27.02% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 33.15% | 100.00% | 66.85% | - | - | - | 3.02 | -201.70% | - | - | 66.85% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 33.15% | 100.00% | 66.85% | - | - | - | 3.02 | -201.70% | - | - | 66.85% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 205.36% | 100.00% | -105.36% | - | - | - | 0.49 | 51.31% | - | - | -105.36% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 101.86% | 100.00% | -1.86% | - | - | - | 0.98 | 1.83% | - | - | -1.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 148.77% | 100.00% | -48.77% | - | - | - | 0.67 | 32.78% | - | - | -48.77% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 308.00% | 100.00% | -208.00% | - | - | - | 0.32 | 67.53% | - | - | -208.00% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 139.23% | 100.00% | -39.23% | - | - | - | 0.72 | 28.18% | - | - | -39.23% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 50.62% | 100.00% | 49.38% | - | - | - | 1.98 | -97.53% | - | - | 49.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 50.62% | 100.00% | 49.38% | - | - | - | 1.98 | -97.53% | - | - | 49.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 78.25% | 100.00% | 21.75% | - | - | - | 1.28 | -27.79% | - | - | 21.75% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.24% | 100.00% | 0.76% | - | - | - | 1.01 | -0.77% | - | - | 0.76% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.24% | 100.00% | 0.76% | - | - | - | 1.01 | -0.77% | - | - | 0.76% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 44.32% | 100.00% | 55.68% | - | - | - | 2.26 | -125.64% | - | - | 55.68% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1508.61% | 100.00% | -1408.61% | - | - | - | 0.07 | 93.37% | - | - | -1408.61% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 191.64% | 100.00% | -91.64% | - | - | - | 0.52 | 47.82% | - | - | -91.64% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 109.64% | 100.00% | -9.64% | - | - | - | 0.91 | 8.79% | - | - | -9.64% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3631.86% | 100.00% | -3531.86% | - | - | - | 0.03 | 97.25% | - | - | -3531.86% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 65.62% | 100.00% | 34.38% | - | - | - | 1.52 | -52.40% | - | - | 34.38% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 17.84% | 100.00% | 82.16% | - | - | - | 5.60 | -460.48% | - | - | 82.16% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1980.90% | 100.00% | -1880.90% | - | - | - | 0.05 | 94.95% | - | - | -1880.90% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 452.16% | 100.00% | -352.16% | - | - | - | 0.22 | 77.88% | - | - | -352.16% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.70% | 100.00% | -446.70% | - | - | - | 0.18 | 81.71% | - | - | -446.70% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 869.44 | -86844.00% | - | - | 99.88% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 62.74% | 100.00% | 37.26% | - | - | - | 1.59 | -59.40% | - | - | 37.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 114.62% | 100.00% | -14.62% | - | - | - | 0.87 | 12.76% | - | - | -14.62% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 68127.27% | 100.00% | -68027.27% | - | - | - | 0.00 | 99.85% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 159.88% | 100.00% | -59.88% | - | - | - | 0.63 | 37.45% | - | - | -59.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 146.97% | 100.00% | -46.97% | - | - | - | 0.68 | 31.96% | - | - | -46.97% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 81.82% | 100.00% | 18.18% | - | - | - | 1.22 | -22.22% | - | - | 18.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 267.81% | 100.00% | -167.81% | - | - | - | 0.37 | 62.66% | - | - | -167.81% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 398.75% | 100.00% | -298.75% | - | - | - | 0.25 | 74.92% | - | - | -298.75% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 226.55% | 100.00% | -126.55% | - | - | - | 0.44 | 55.86% | - | - | -126.55% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 887.01% | 100.00% | -787.01% | - | - | - | 0.11 | 88.73% | - | - | -787.01% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 3.89% | 100.00% | 96.11% | - | - | - | 25.69 | -2469.47% | - | - | 96.11% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 21.40% | 86.12% | 64.72% | - | - | - | 4.02 | -302.36% | - | - | 75.15% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 39.50% | 88.00% | 48.50% | - | - | - | 2.23 | -122.78% | - | - | 55.11% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 40.69% | 88.00% | 47.31% | - | - | - | 2.16 | -116.29% | - | - | 53.77% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 35.28% | 88.00% | 52.72% | - | - | - | 2.49 | -149.42% | - | - | 59.91% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 35.28% | 88.00% | 52.72% | - | - | - | 2.49 | -149.42% | - | - | 59.91% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.02% | 84.00% | 82.98% | - | - | - | 82.62 | -8162.29% | - | - | 98.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 15.22% | 84.00% | 68.78% | - | - | - | 5.52 | -451.85% | - | - | 81.88% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NIPLE CORRIDO DE 1/2" X 1" HG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COPLA HG DE 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.59% | 84.00% | 83.41% | - | - | - | 142.25 | -14124.78% | - | - | 99.30% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 30
|
- | - | - | - | - | - | 1.30% | 1.25% | 81.80% | 100.00% | 18.20% | - | - | - | 1.22 | -22.25% | - | - | 18.20% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 91.47% | 100.00% | 8.53% | - | - | - | 1.09 | -9.33% | - | - | 8.53% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 109.23% | 100.00% | -9.23% | - | - | - | 0.92 | 8.45% | - | - | -9.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 137.92% | 100.00% | -37.92% | - | - | - | 0.73 | 27.49% | - | - | -37.92% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 533635.56% | 100.00% | -533535.56% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5005.01% | 100.00% | -4905.01% | - | - | - | 0.02 | 98.00% | - | - | -4905.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 319.88% | 100.00% | -219.88% | - | - | - | 0.31 | 68.74% | - | - | -219.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 138.44% | 100.00% | -38.44% | - | - | - | 0.72 | 27.76% | - | - | -38.44% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 95.46% | 100.00% | 4.54% | - | - | - | 1.05 | -4.75% | - | - | 4.54% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.29% | 100.00% | 57.71% | - | - | - | 2.36 | -136.45% | - | - | 57.71% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.03% | 100.00% | -154.03% | - | - | - | 0.39 | 60.63% | - | - | -154.03% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 304.49% | 100.00% | -204.49% | - | - | - | 0.33 | 67.16% | - | - | -204.49% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 371.35% | 100.00% | -271.35% | - | - | - | 0.27 | 73.07% | - | - | -271.35% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 134.82% | 100.00% | -34.82% | - | - | - | 0.74 | 25.83% | - | - | -34.82% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 69.51% | 100.00% | 30.49% | - | - | - | 1.44 | -43.86% | - | - | 30.49% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.94% | 100.00% | 20.06% | - | - | - | 1.25 | -25.09% | - | - | 20.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 100.36% | 100.00% | -0.36% | - | - | - | 1.00 | 0.36% | - | - | -0.36% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 126.97% | 100.00% | -26.97% | - | - | - | 0.79 | 21.24% | - | - | -26.97% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.07% | 100.00% | -72.07% | - | - | - | 0.58 | 41.88% | - | - | -72.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.14% | 100.00% | -6.14% | - | - | - | 0.94 | 5.79% | - | - | -6.14% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.24% | 100.00% | 32.76% | - | - | - | 1.49 | -48.71% | - | - | 32.76% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 97.82% | 100.00% | 2.18% | - | - | - | 1.02 | -2.23% | - | - | 2.18% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.51% | 100.00% | 18.49% | - | - | - | 1.23 | -22.69% | - | - | 18.49% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 79.97% | 100.00% | 20.03% | - | - | - | 1.25 | -25.05% | - | - | 20.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 79.97% | 100.00% | 20.03% | - | - | - | 1.25 | -25.05% | - | - | 20.03% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 163.33% | 100.00% | -63.33% | - | - | - | 0.61 | 38.77% | - | - | -63.33% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 86.64% | 100.00% | 13.36% | - | - | - | 1.15 | -15.42% | - | - | 13.36% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 101.31% | 100.00% | -1.31% | - | - | - | 0.99 | 1.30% | - | - | -1.31% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 101.31% | 100.00% | -1.31% | - | - | - | 0.99 | 1.30% | - | - | -1.31% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 63.19% | 100.00% | 36.81% | - | - | - | 1.58 | -58.25% | - | - | 36.81% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1711.85% | 100.00% | -1611.85% | - | - | - | 0.06 | 94.16% | - | - | -1611.85% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 168.05% | 100.00% | -68.05% | - | - | - | 0.60 | 40.49% | - | - | -68.05% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 99.71% | 100.00% | 0.29% | - | - | - | 1.00 | -0.29% | - | - | 0.29% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3044.53% | 100.00% | -2944.53% | - | - | - | 0.03 | 96.72% | - | - | -2944.53% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 104.80% | 100.00% | -4.80% | - | - | - | 0.95 | 4.58% | - | - | -4.80% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 52.28% | 100.00% | 47.72% | - | - | - | 1.91 | -91.29% | - | - | 47.72% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 38.75% | 100.00% | 61.25% | - | - | - | 2.58 | -158.08% | - | - | 61.25% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 19.24% | 100.00% | 80.76% | - | - | - | 5.20 | -419.65% | - | - | 80.76% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1243.80% | 100.00% | -1143.80% | - | - | - | 0.08 | 91.96% | - | - | -1143.80% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA FINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO TABLAYESO DE 7 X 7/16" ROSCA FINA PUNTA CORRIENTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 77.50% | 100.00% | 22.50% | - | - | - | 1.29 | -29.04% | - | - | 22.50% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 104.41% | 100.00% | -4.41% | - | - | - | 0.96 | 4.22% | - | - | -4.41% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6883.42% | 100.00% | -6783.42% | - | - | - | 0.01 | 98.55% | - | - | -6783.42% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 289.59% | 100.00% | -189.59% | - | - | - | 0.35 | 65.47% | - | - | -189.59% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 122.75% | 100.00% | -22.75% | - | - | - | 0.81 | 18.53% | - | - | -22.75% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.39% | 100.00% | 11.61% | - | - | - | 1.13 | -13.14% | - | - | 11.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.35% | 100.00% | 27.65% | - | - | - | 1.38 | -38.21% | - | - | 27.65% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 282.29% | 100.00% | -182.29% | - | - | - | 0.35 | 64.58% | - | - | -182.29% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 69.76% | 100.00% | 30.24% | - | - | - | 1.43 | -43.36% | - | - | 30.24% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 576.67% | 100.00% | -476.67% | - | - | - | 0.17 | 82.66% | - | - | -476.67% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 150.61% | 100.00% | -50.61% | - | - | - | 0.66 | 33.60% | - | - | -50.61% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 871.79% | 100.00% | -771.79% | - | - | - | 0.11 | 88.53% | - | - | -771.79% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 98.76% | 100.00% | 1.24% | - | - | - | 1.01 | -1.25% | - | - | 1.24% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.87% | 100.00% | 43.13% | - | - | - | 1.76 | -75.83% | - | - | 43.13% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.93% | 100.00% | 51.07% | - | - | - | 2.04 | -104.37% | - | - | 51.07% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.93% | 100.00% | 51.07% | - | - | - | 2.04 | -104.37% | - | - | 51.07% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 91.76% | 100.00% | 8.24% | - | - | - | 1.09 | -8.98% | - | - | 8.24% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 80.11% | 100.00% | 19.89% | - | - | - | 1.25 | -24.84% | - | - | 19.89% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 588.64% | 100.00% | -488.64% | - | - | - | 0.17 | 83.01% | - | - | -488.64% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 543.47% | 100.00% | -443.47% | - | - | - | 0.18 | 81.60% | - | - | -443.47% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 543.47% | 100.00% | -443.47% | - | - | - | 0.18 | 81.60% | - | - | -443.47% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 145.60% | 100.00% | -45.60% | - | - | - | 0.69 | 31.32% | - | - | -45.60% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 226.90% | 100.00% | -126.90% | - | - | - | 0.44 | 55.93% | - | - | -126.90% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 220.63% | 100.00% | -120.63% | - | - | - | 0.45 | 54.68% | - | - | -120.63% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 220.63% | 100.00% | -120.63% | - | - | - | 0.45 | 54.68% | - | - | -120.63% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 102.40% | 100.00% | -2.40% | - | - | - | 0.98 | 2.35% | - | - | -2.40% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 102.40% | 100.00% | -2.40% | - | - | - | 0.98 | 2.35% | - | - | -2.40% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 101.88% | 100.00% | -1.88% | - | - | - | 0.98 | 1.84% | - | - | -1.88% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 101.88% | 100.00% | -1.88% | - | - | - | 0.98 | 1.84% | - | - | -1.88% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 101.88% | 100.00% | -1.88% | - | - | - | 0.98 | 1.84% | - | - | -1.88% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 101.88% | 100.00% | -1.88% | - | - | - | 0.98 | 1.84% | - | - | -1.88% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 101.37% | 100.00% | -1.37% | - | - | - | 0.99 | 1.36% | - | - | -1.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 78.96% | 100.00% | 21.04% | - | - | - | 1.27 | -26.64% | - | - | 21.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 29.53% | 100.00% | 70.47% | - | - | - | 3.39 | -238.68% | - | - | 70.47% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 47.77% | 100.00% | 52.23% | - | - | - | 2.09 | -109.33% | - | - | 52.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 130.90% | 100.00% | -30.90% | - | - | - | 0.76 | 23.61% | - | - | -30.90% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 126.79% | 100.00% | -26.79% | - | - | - | 0.79 | 21.13% | - | - | -26.79% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 136.03% | 100.00% | -36.03% | - | - | - | 0.74 | 26.49% | - | - | -36.03% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 70.18% | 100.00% | 29.82% | - | - | - | 1.42 | -42.50% | - | - | 29.82% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 3.59% | 100.00% | 96.41% | - | - | - | 27.87 | -2687.30% | - | - | 96.41% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 3.59% | 100.00% | 96.41% | - | - | - | 27.87 | -2687.30% | - | - | 96.41% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 38.07% | 100.00% | 61.93% | - | - | - | 2.63 | -162.66% | - | - | 61.93% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 1.69% | 100.00% | 98.31% | - | - | - | 59.30 | -5829.62% | - | - | 98.31% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 59.03% | 100.00% | 40.97% | - | - | - | 1.69 | -69.40% | - | - | 40.97% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.15% | 100.00% | -0.15% | - | - | - | 1.00 | 0.15% | - | - | -0.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.42% | 100.00% | 99.58% | - | - | - | 239.21 | -23820.67% | - | - | 99.58% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 12.71% | 100.00% | 87.29% | - | - | - | 7.87 | -686.51% | - | - | 87.29% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 12.92% | 100.00% | 87.08% | - | - | - | 7.74 | -673.70% | - | - | 87.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 32
|
- | - | - | - | - | - | 1.30% | 1.26% | 81.16% | 100.00% | 18.84% | - | - | - | 1.23 | -23.21% | - | - | 18.84% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 95.00% | 100.00% | 5.00% | - | - | - | 1.05 | -5.26% | - | - | 5.00% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 104.49% | 100.00% | -4.49% | - | - | - | 0.96 | 4.29% | - | - | -4.49% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 143.90% | 100.00% | -43.90% | - | - | - | 0.69 | 30.51% | - | - | -43.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 143.90% | 100.00% | -43.90% | - | - | - | 0.69 | 30.51% | - | - | -43.90% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 40.39% | 100.00% | 59.61% | - | - | - | 2.48 | -147.61% | - | - | 59.61% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1457.80% | 100.00% | -1357.80% | - | - | - | 0.07 | 93.14% | - | - | -1357.80% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 178.04% | 100.00% | -78.04% | - | - | - | 0.56 | 43.83% | - | - | -78.04% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.15% | 100.00% | -18.15% | - | - | - | 0.85 | 15.36% | - | - | -18.15% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2734.54% | 100.00% | -2634.54% | - | - | - | 0.04 | 96.34% | - | - | -2634.54% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 5.27% | 100.00% | 94.73% | - | - | - | 18.99 | -1798.85% | - | - | 94.73% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 459.65% | 100.00% | -359.65% | - | - | - | 0.22 | 78.24% | - | - | -359.65% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.57% | 100.00% | 95.43% | - | - | - | 21.88 | -2087.82% | - | - | 95.43% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 104.32% | 100.00% | -4.32% | - | - | - | 0.96 | 4.14% | - | - | -4.32% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 127.39% | 100.00% | -27.39% | - | - | - | 0.78 | 21.50% | - | - | -27.39% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 211544.44% | 100.00% | -211444.44% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 8547.75% | 100.00% | -8447.75% | - | - | - | 0.01 | 98.83% | - | - | -8447.75% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 151.57% | 100.00% | -51.57% | - | - | - | 0.66 | 34.02% | - | - | -51.57% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 149.25% | 100.00% | -49.25% | - | - | - | 0.67 | 33.00% | - | - | -49.25% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 93.05% | 100.00% | 6.95% | - | - | - | 1.07 | -7.47% | - | - | 6.95% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 98.95% | 100.00% | 1.05% | - | - | - | 1.01 | -1.06% | - | - | 1.05% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 97.73% | 100.00% | 2.27% | - | - | - | 1.02 | -2.33% | - | - | 2.27% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 55.48% | 100.00% | 44.52% | - | - | - | 1.80 | -80.25% | - | - | 44.52% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 190.08% | 100.00% | -90.08% | - | - | - | 0.53 | 47.39% | - | - | -90.08% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 232.66% | 100.00% | -132.66% | - | - | - | 0.43 | 57.02% | - | - | -132.66% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.50% | 100.00% | 18.50% | - | - | - | 1.23 | -22.70% | - | - | 18.50% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 81.50% | 100.00% | 18.50% | - | - | - | 1.23 | -22.70% | - | - | 18.50% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 103.87% | 100.00% | -3.87% | - | - | - | 0.96 | 3.72% | - | - | -3.87% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 131.18% | 100.00% | -31.18% | - | - | - | 0.76 | 23.77% | - | - | -31.18% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.07% | 100.00% | -72.07% | - | - | - | 0.58 | 41.88% | - | - | -72.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 116.06% | 100.00% | -16.06% | - | - | - | 0.86 | 13.84% | - | - | -16.06% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 48.63% | 100.00% | 51.37% | - | - | - | 2.06 | -105.63% | - | - | 51.37% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 86.32% | 100.00% | 13.68% | - | - | - | 1.16 | -15.85% | - | - | 13.68% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 125.80% | 100.00% | -25.80% | - | - | - | 0.79 | 20.51% | - | - | -25.80% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.45% | - | - | 16.97% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.45% | - | - | 16.97% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 163.33% | 100.00% | -63.33% | - | - | - | 0.61 | 38.77% | - | - | -63.33% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 77.34% | 100.00% | 22.66% | - | - | - | 1.29 | -29.30% | - | - | 22.66% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 104.12% | 100.00% | -4.12% | - | - | - | 0.96 | 3.96% | - | - | -4.12% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 338780.00% | 100.00% | -338680.00% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9789.16% | 100.00% | -9689.16% | - | - | - | 0.01 | 98.98% | - | - | -9689.16% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2389.03% | 100.00% | -2289.03% | - | - | - | 0.04 | 95.81% | - | - | -2289.03% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 312.19% | 100.00% | -212.19% | - | - | - | 0.32 | 67.97% | - | - | -212.19% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 110.61% | 100.00% | -10.61% | - | - | - | 0.90 | 9.59% | - | - | -10.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 75.44% | 100.00% | 24.56% | - | - | - | 1.33 | -32.55% | - | - | 24.56% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.95% | 100.00% | 28.05% | - | - | - | 1.39 | -38.99% | - | - | 28.05% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 271.21% | 100.00% | -171.21% | - | - | - | 0.37 | 63.13% | - | - | -171.21% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 211.59% | 100.00% | -111.59% | - | - | - | 0.47 | 52.74% | - | - | -111.59% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.39% | 100.00% | -166.39% | - | - | - | 0.38 | 62.46% | - | - | -166.39% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.07% | 100.00% | -43.07% | - | - | - | 0.70 | 30.10% | - | - | -43.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 874.04% | 100.00% | -774.04% | - | - | - | 0.11 | 88.56% | - | - | -774.04% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 90.48% | 100.00% | 9.52% | - | - | - | 1.11 | -10.52% | - | - | 9.52% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.87% | 100.00% | 43.13% | - | - | - | 1.76 | -75.83% | - | - | 43.13% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.93% | 100.00% | 51.07% | - | - | - | 2.04 | -104.37% | - | - | 51.07% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.93% | 100.00% | 51.07% | - | - | - | 2.04 | -104.37% | - | - | 51.07% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 91.76% | 100.00% | 8.24% | - | - | - | 1.09 | -8.98% | - | - | 8.24% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 75.27% | 100.00% | 24.73% | - | - | - | 1.33 | -32.86% | - | - | 24.73% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 557.62% | 100.00% | -457.62% | - | - | - | 0.18 | 82.07% | - | - | -457.62% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 541.41% | 100.00% | -441.41% | - | - | - | 0.18 | 81.53% | - | - | -441.41% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 541.41% | 100.00% | -441.41% | - | - | - | 0.18 | 81.53% | - | - | -441.41% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACIDO MURIATICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 116.30% | 100.00% | -16.30% | - | - | - | 0.86 | 14.02% | - | - | -16.30% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 115.10% | 100.00% | -15.10% | - | - | - | 0.87 | 13.12% | - | - | -15.10% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 171.08% | 100.00% | -71.08% | - | - | - | 0.58 | 41.55% | - | - | -71.08% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 159.91% | 100.00% | -59.91% | - | - | - | 0.63 | 37.46% | - | - | -59.91% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 159.91% | 100.00% | -59.91% | - | - | - | 0.63 | 37.46% | - | - | -59.91% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 85.36% | 100.00% | 14.64% | - | - | - | 1.17 | -17.15% | - | - | 14.64% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 85.11% | 100.00% | 14.89% | - | - | - | 1.17 | -17.50% | - | - | 14.89% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.90% | 100.00% | 0.10% | - | - | - | 1.00 | -0.10% | - | - | 0.10% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIURETANO MARCA DYMONIC 100
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 80.61% | 100.00% | 19.39% | - | - | - | 1.24 | -24.05% | - | - | 19.39% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 29.53% | 100.00% | 70.47% | - | - | - | 3.39 | -238.68% | - | - | 70.47% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 45.43% | 100.00% | 54.57% | - | - | - | 2.20 | -120.12% | - | - | 54.57% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 130.90% | 100.00% | -30.90% | - | - | - | 0.76 | 23.61% | - | - | -30.90% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 126.79% | 100.00% | -26.79% | - | - | - | 0.79 | 21.13% | - | - | -26.79% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 136.03% | 100.00% | -36.03% | - | - | - | 0.74 | 26.49% | - | - | -36.03% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 70.18% | 100.00% | 29.82% | - | - | - | 1.42 | -42.50% | - | - | 29.82% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 43.62% | 100.00% | 56.38% | - | - | - | 2.29 | -129.28% | - | - | 56.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 43.62% | 100.00% | 56.38% | - | - | - | 2.29 | -129.28% | - | - | 56.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 43.62% | 100.00% | 56.38% | - | - | - | 2.29 | -129.28% | - | - | 56.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 43.62% | 100.00% | 56.38% | - | - | - | 2.29 | -129.28% | - | - | 56.38% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.39% | 100.00% | 44.61% | - | - | - | 1.81 | -80.53% | - | - | 44.61% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 101.59% | 100.00% | -1.59% | - | - | - | 0.98 | 1.56% | - | - | -1.59% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 49.87% | 100.00% | 50.13% | - | - | - | 2.01 | -100.52% | - | - | 50.13% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.35% | 100.00% | 96.65% | - | - | - | 29.82 | -2881.90% | - | - | 96.65% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 42.74% | 100.00% | 57.26% | - | - | - | 2.34 | -133.99% | - | - | 57.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 2.17% | 100.00% | 97.83% | - | - | - | 46.04 | -4503.90% | - | - | 97.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 27
|
- | - | - | - | - | - | 1.30% | 1.26% | 79.17% | 100.00% | 20.83% | - | - | - | 1.26 | -26.32% | - | - | 20.83% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 83.86% | 100.00% | 16.14% | - | - | - | 1.19 | -19.25% | - | - | 16.14% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 109.41% | 100.00% | -9.41% | - | - | - | 0.91 | 8.60% | - | - | -9.41% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 134.46% | 100.00% | -34.46% | - | - | - | 0.74 | 25.63% | - | - | -34.46% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 218.44% | 100.00% | -118.44% | - | - | - | 0.46 | 54.22% | - | - | -118.44% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE BOMBEO CONVENCIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION CON PLUMA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 56.53% | 100.00% | 43.47% | - | - | - | 1.77 | -76.89% | - | - | 43.47% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 326.34 | -32534.00% | - | - | 99.69% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 4.28% | 100.00% | 95.72% | - | - | - | 23.38 | -2238.36% | - | - | 95.72% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 4" X 4" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 91.81% | 100.00% | 8.19% | - | - | - | 1.09 | -8.92% | - | - | 8.19% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 91.81% | 100.00% | 8.19% | - | - | - | 1.09 | -8.92% | - | - | 8.19% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 88.15% | 100.00% | 11.85% | - | - | - | 1.13 | -13.45% | - | - | 11.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 106.49% | 100.00% | -6.49% | - | - | - | 0.94 | 6.10% | - | - | -6.49% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 106.49% | 100.00% | -6.49% | - | - | - | 0.94 | 6.10% | - | - | -6.49% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 58.65% | 100.00% | 41.35% | - | - | - | 1.71 | -70.52% | - | - | 41.35% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2278.43% | 100.00% | -2178.43% | - | - | - | 0.04 | 95.61% | - | - | -2178.43% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 294.52% | 100.00% | -194.52% | - | - | - | 0.34 | 66.05% | - | - | -194.52% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.68% | 100.00% | 28.32% | - | - | - | 1.40 | -39.50% | - | - | 28.32% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.95% | 100.00% | -69.95% | - | - | - | 0.59 | 41.16% | - | - | -69.95% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1046.59% | 100.00% | -946.59% | - | - | - | 0.10 | 90.45% | - | - | -946.59% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.06% | 100.00% | 31.94% | - | - | - | 1.47 | -46.92% | - | - | 31.94% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 68.06% | 100.00% | 31.94% | - | - | - | 1.47 | -46.92% | - | - | 31.94% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 11.78% | 100.00% | 88.22% | - | - | - | 8.49 | -749.02% | - | - | 88.22% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 28.87% | 100.00% | 71.13% | - | - | - | 3.46 | -246.43% | - | - | 71.13% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 854.18% | 100.00% | -754.18% | - | - | - | 0.12 | 88.29% | - | - | -754.18% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2.59% | 100.00% | 97.41% | - | - | - | 38.57 | -3757.32% | - | - | 97.41% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 86.17% | 100.00% | 13.83% | - | - | - | 1.16 | -16.05% | - | - | 13.83% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 117.73% | 100.00% | -17.73% | - | - | - | 0.85 | 15.06% | - | - | -17.73% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 243921.82% | 100.00% | -243821.82% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 23330.38% | 100.00% | -23230.38% | - | - | - | 0.00 | 99.57% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EMULSIKA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.59% | 100.00% | -192.59% | - | - | - | 0.34 | 65.82% | - | - | -192.59% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 147.73% | 100.00% | -47.73% | - | - | - | 0.68 | 32.31% | - | - | -47.73% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.40% | 100.00% | 11.60% | - | - | - | 1.13 | -13.12% | - | - | 11.60% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.15% | 100.00% | 53.85% | - | - | - | 2.17 | -116.69% | - | - | 53.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.69% | 100.00% | 90.31% | - | - | - | 10.31 | -931.47% | - | - | 90.31% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 354.77% | 100.00% | -254.77% | - | - | - | 0.28 | 71.81% | - | - | -254.77% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 418.54% | 100.00% | -318.54% | - | - | - | 0.24 | 76.11% | - | - | -318.54% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1608.12% | 100.00% | -1508.12% | - | - | - | 0.06 | 93.78% | - | - | -1508.12% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 160.94% | 100.00% | -60.94% | - | - | - | 0.62 | 37.87% | - | - | -60.94% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 582.96% | 100.00% | -482.96% | - | - | - | 0.17 | 82.85% | - | - | -482.96% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 90.48% | 100.00% | 9.52% | - | - | - | 1.11 | -10.52% | - | - | 9.52% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.87% | 100.00% | 43.13% | - | - | - | 1.76 | -75.83% | - | - | 43.13% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 52.48% | 100.00% | 47.52% | - | - | - | 1.91 | -90.54% | - | - | 47.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 52.48% | 100.00% | 47.52% | - | - | - | 1.91 | -90.54% | - | - | 47.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 91.76% | 100.00% | 8.24% | - | - | - | 1.09 | -8.98% | - | - | 8.24% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 66.54% | 100.00% | 33.46% | - | - | - | 1.50 | -50.29% | - | - | 33.46% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 61.45% | 100.00% | 38.55% | - | - | - | 1.63 | -62.73% | - | - | 38.55% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2522.52% | 100.00% | -2422.52% | - | - | - | 0.04 | 96.04% | - | - | -2422.52% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.06% | 100.00% | -243.06% | - | - | - | 0.29 | 70.85% | - | - | -243.06% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 152.67% | 100.00% | -52.67% | - | - | - | 0.66 | 34.50% | - | - | -52.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.26% | 100.00% | -36.26% | - | - | - | 0.73 | 26.61% | - | - | -36.26% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 48.55% | 100.00% | 51.45% | - | - | - | 2.06 | -105.96% | - | - | 51.45% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.03% | 100.00% | -154.03% | - | - | - | 0.39 | 60.63% | - | - | -154.03% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 257.34% | 100.00% | -157.34% | - | - | - | 0.39 | 61.14% | - | - | -157.34% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 362.05% | 100.00% | -262.05% | - | - | - | 0.28 | 72.38% | - | - | -262.05% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 10.07% | 100.00% | 89.93% | - | - | - | 9.93 | -892.94% | - | - | 89.93% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.44% | 82.40% | 100.00% | 17.60% | - | - | - | 1.21 | -21.35% | - | - | 17.60% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 307.89% | 100.00% | -207.89% | - | - | - | 0.32 | 67.52% | - | - | -207.89% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 296.13% | 100.00% | -196.13% | - | - | - | 0.34 | 66.23% | - | - | -196.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 296.13% | 100.00% | -196.13% | - | - | - | 0.34 | 66.23% | - | - | -196.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.91% | 100.00% | -74.91% | - | - | - | 0.57 | 42.83% | - | - | -74.91% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.91% | 100.00% | -74.91% | - | - | - | 0.57 | 42.83% | - | - | -74.91% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 174.91% | 100.00% | -74.91% | - | - | - | 0.57 | 42.83% | - | - | -74.91% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 493.16 | -49216.00% | - | - | 99.80% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 147.15% | 100.00% | -47.15% | - | - | - | 0.68 | 32.04% | - | - | -47.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 213.33% | 100.00% | -113.33% | - | - | - | 0.47 | 53.13% | - | - | -113.33% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.20% | 100.00% | -102.20% | - | - | - | 0.49 | 50.54% | - | - | -102.20% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.20% | 100.00% | -102.20% | - | - | - | 0.49 | 50.54% | - | - | -102.20% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 111.99% | 100.00% | -11.99% | - | - | - | 0.89 | 10.71% | - | - | -11.99% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 104.77% | 100.00% | -4.77% | - | - | - | 0.95 | 4.55% | - | - | -4.77% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.41% | 100.00% | 59.59% | - | - | - | 2.47 | -147.46% | - | - | 59.59% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.14% | 100.00% | -18.14% | - | - | - | 0.85 | 15.35% | - | - | -18.14% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.23% | 100.00% | 15.77% | - | - | - | 1.19 | -18.72% | - | - | 15.77% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 102.04% | 100.00% | -2.04% | - | - | - | 0.98 | 2.00% | - | - | -2.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 98.89% | 100.00% | 1.11% | - | - | - | 1.01 | -1.12% | - | - | 1.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 4.35% | 100.00% | 95.65% | - | - | - | 22.98 | -2197.74% | - | - | 95.65% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA ELECTRICA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BARRENO ROTOMARTILLO ELEC. TRUPER 1/2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCA DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 82.27% | 100.00% | 17.73% | - | - | - | 1.22 | -21.56% | - | - | 17.73% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.19% | 100.00% | 22.81% | - | - | - | 1.30 | -29.55% | - | - | 22.81% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 77.19% | 100.00% | 22.81% | - | - | - | 1.30 | -29.55% | - | - | 22.81% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 37.27% | 100.00% | 62.73% | - | - | - | 2.68 | -168.29% | - | - | 62.73% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.09% | 73.90% | 100.00% | 26.10% | - | - | - | 1.35 | -35.32% | - | - | 26.10% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 77.52% | 100.00% | 22.48% | - | - | - | 1.29 | -28.99% | - | - | 22.48% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 77.52% | 100.00% | 22.48% | - | - | - | 1.29 | -28.99% | - | - | 22.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 77.52% | 100.00% | 22.48% | - | - | - | 1.29 | -28.99% | - | - | 22.48% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.28% | 100.00% | 93.72% | - | - | - | 15.93 | -1492.52% | - | - | 93.72% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 11.00% | 100.00% | 89.00% | - | - | - | 9.09 | -809.31% | - | - | 89.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 11.00% | 100.00% | 89.00% | - | - | - | 9.09 | -809.31% | - | - | 89.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1.56% | 100.00% | 98.44% | - | - | - | 64.05 | -6304.76% | - | - | 98.44% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 1.56% | 100.00% | 98.44% | - | - | - | 64.05 | -6304.76% | - | - | 98.44% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 48.30% | 100.00% | 51.70% | - | - | - | 2.07 | -107.04% | - | - | 51.70% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.33% | 100.00% | -36.33% | - | - | - | 0.73 | 26.65% | - | - | -36.33% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 132.22% | 100.00% | -32.22% | - | - | - | 0.76 | 24.37% | - | - | -32.22% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.22% | 100.00% | 37.78% | - | - | - | 1.61 | -60.71% | - | - | 37.78% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 100.00% | 3.30% | - | - | - | 1.03 | -3.41% | - | - | 3.30% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 129.63% | 100.00% | -29.63% | - | - | - | 0.77 | 22.86% | - | - | -29.63% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.51% | 100.00% | 98.49% | - | - | - | 66.20 | -6519.75% | - | - | 98.49% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.51% | 100.00% | 98.49% | - | - | - | 66.20 | -6519.75% | - | - | 98.49% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 42.69% | 100.00% | 57.31% | - | - | - | 2.34 | -134.26% | - | - | 57.31% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 42.69% | 100.00% | 57.31% | - | - | - | 2.34 | -134.26% | - | - | 57.31% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 42.69% | 100.00% | 57.31% | - | - | - | 2.34 | -134.26% | - | - | 57.31% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 42.69% | 100.00% | 57.31% | - | - | - | 2.34 | -134.26% | - | - | 57.31% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 35.60% | 100.00% | 64.40% | - | - | - | 2.81 | -180.88% | - | - | 64.40% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 22.29% | 100.00% | 77.71% | - | - | - | 4.49 | -348.65% | - | - | 77.71% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 60.14% | 100.00% | 39.86% | - | - | - | 1.66 | -66.28% | - | - | 39.86% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.37% | 100.00% | -0.37% | - | - | - | 1.00 | 0.36% | - | - | -0.37% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.37% | 100.00% | -3.37% | - | - | - | 0.97 | 3.26% | - | - | -3.37% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.28% | 100.00% | 99.72% | - | - | - | 362.43 | -36143.43% | - | - | 99.72% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 14.82% | 100.00% | 85.18% | - | - | - | 6.75 | -574.63% | - | - | 85.18% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 15.10% | 100.00% | 84.90% | - | - | - | 6.62 | -562.40% | - | - | 84.90% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 25
|
- | - | - | - | - | - | 1.30% | 1.25% | 78.79% | 100.00% | 21.21% | - | - | - | 1.27 | -26.91% | - | - | 21.21% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 85.17% | 100.00% | 14.83% | - | - | - | 1.17 | -17.42% | - | - | 14.83% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 546.15% | 100.00% | -446.15% | - | - | - | 0.18 | 81.69% | - | - | -446.15% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 501.47% | 100.00% | -401.47% | - | - | - | 0.20 | 80.06% | - | - | -401.47% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 501.47% | 100.00% | -401.47% | - | - | - | 0.20 | 80.06% | - | - | -401.47% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SEGURIDAD INDUSTRIAL',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GUANTES DE LATEX
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASCARILLAS KN95
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 5 TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MANO DE OBRA PLANILLA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PERSONAL DE OBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SQUEEGEE LIMPIADOR DE VIDRIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 121.14% | 100.00% | -21.14% | - | - | - | 0.83 | 17.45% | - | - | -21.14% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 171.21% | 100.00% | -71.21% | - | - | - | 0.58 | 41.59% | - | - | -71.21% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 155.70% | 100.00% | -55.70% | - | - | - | 0.64 | 35.77% | - | - | -55.70% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 155.70% | 100.00% | -55.70% | - | - | - | 0.64 | 35.77% | - | - | -55.70% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 94.54% | 100.00% | 5.46% | - | - | - | 1.06 | -5.77% | - | - | 5.46% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 93.77% | 100.00% | 6.23% | - | - | - | 1.07 | -6.65% | - | - | 6.23% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 118.95% | 100.00% | -18.95% | - | - | - | 0.84 | 15.93% | - | - | -18.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.98% | 100.00% | 13.02% | - | - | - | 1.15 | -14.96% | - | - | 13.02% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.15% | 100.00% | -3.15% | - | - | - | 0.97 | 3.06% | - | - | -3.15% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 31.22% | 100.00% | 68.78% | - | - | - | 3.20 | -220.31% | - | - | 68.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 2''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.64% | 100.00% | -0.64% | - | - | - | 0.99 | 0.63% | - | - | -0.64% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.03% | 100.00% | -0.03% | - | - | - | 1.00 | 0.03% | - | - | -0.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.03% | 100.00% | -0.03% | - | - | - | 1.00 | 0.03% | - | - | -0.03% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 100.03% | 100.00% | -0.03% | - | - | - | 1.00 | 0.03% | - | - | -0.03% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA METALICA DE 2" MANGO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 5 TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 1''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 100.62% | 100.00% | -0.62% | - | - | - | 0.99 | 0.61% | - | - | -0.62% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 93.49% | 100.00% | 6.51% | - | - | - | 1.07 | -6.96% | - | - | 6.51% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 88.42% | 100.00% | 11.58% | - | - | - | 1.13 | -13.10% | - | - | 11.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 52.42% | 100.00% | 47.58% | - | - | - | 1.91 | -90.77% | - | - | 47.58% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 80.20% | 100.00% | 19.80% | - | - | - | 1.25 | -24.69% | - | - | 19.80% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 79.66% | 100.00% | 20.34% | - | - | - | 1.26 | -25.54% | - | - | 20.34% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 10.74% | 100.00% | 89.26% | - | - | - | 9.31 | -830.72% | - | - | 89.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 30.96% | 100.00% | 69.04% | - | - | - | 3.23 | -223.01% | - | - | 69.04% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 26.85% | 100.00% | 73.15% | - | - | - | 3.72 | -272.39% | - | - | 73.15% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 354.38 | -35338.00% | - | - | 99.72% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 62.22% | 100.00% | 37.78% | - | - | - | 1.61 | -60.71% | - | - | 37.78% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 500.50 | -49950.00% | - | - | 99.80% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 506.24 | -50524.00% | - | - | 99.80% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2326.71 | -232571.00% | - | - | 99.96% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1539.00 | -153800.00% | - | - | 99.94% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONTRALLAVE 1/2 X 1/4 A LA PARED ICE MAKER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 82.91% | 100.00% | 17.09% | - | - | - | 1.21 | -20.61% | - | - | 17.09% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 110.13% | 100.00% | -10.13% | - | - | - | 0.91 | 9.20% | - | - | -10.13% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 144.30% | 100.00% | -44.30% | - | - | - | 0.69 | 30.70% | - | - | -44.30% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.49% | 100.00% | -107.49% | - | - | - | 0.48 | 51.81% | - | - | -107.49% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 109.17% | 100.00% | -9.17% | - | - | - | 0.92 | 8.40% | - | - | -9.17% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 46.39% | 100.00% | 53.61% | - | - | - | 2.16 | -115.56% | - | - | 53.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.99% | 100.00% | 4.01% | - | - | - | 1.04 | -4.17% | - | - | 4.01% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 95.43% | 100.00% | 4.57% | - | - | - | 1.05 | -4.79% | - | - | 4.57% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 81.94% | 100.00% | 18.06% | - | - | - | 1.22 | -22.05% | - | - | 18.06% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 81.94% | 100.00% | 18.06% | - | - | - | 1.22 | -22.05% | - | - | 18.06% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 182.55% | 100.00% | -82.55% | - | - | - | 0.55 | 45.22% | - | - | -82.55% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 86.88% | 100.00% | 13.12% | - | - | - | 1.15 | -15.10% | - | - | 13.12% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 116.41% | 100.00% | -16.41% | - | - | - | 0.86 | 14.10% | - | - | -16.41% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 116.41% | 100.00% | -16.41% | - | - | - | 0.86 | 14.10% | - | - | -16.41% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 38.93% | 100.00% | 61.07% | - | - | - | 2.57 | -156.89% | - | - | 61.07% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2074.17% | 100.00% | -1974.17% | - | - | - | 0.05 | 95.18% | - | - | -1974.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 440.90% | 100.00% | -340.90% | - | - | - | 0.23 | 77.32% | - | - | -340.90% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 440.90% | 100.00% | -340.90% | - | - | - | 0.23 | 77.32% | - | - | -340.90% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 113.24% | 100.00% | -13.24% | - | - | - | 0.88 | 11.69% | - | - | -13.24% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.68% | 100.00% | 28.32% | - | - | - | 1.40 | -39.50% | - | - | 28.32% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.77% | 100.00% | 1.23% | - | - | - | 1.01 | -1.25% | - | - | 1.23% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 314.13% | 100.00% | -214.13% | - | - | - | 0.32 | 68.17% | - | - | -214.13% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 27.03% | 100.00% | 72.97% | - | - | - | 3.70 | -269.97% | - | - | 72.97% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.45% | 100.00% | 97.55% | - | - | - | 40.89 | -3989.44% | - | - | 97.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 76.74% | 100.00% | 23.26% | - | - | - | 1.30 | -30.30% | - | - | 23.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 80.63% | 100.00% | 19.37% | - | - | - | 1.24 | -24.02% | - | - | 19.37% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 615733.33% | 100.00% | -615633.33% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5025.03% | 100.00% | -4925.03% | - | - | - | 0.02 | 98.01% | - | - | -4925.03% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 387.24% | 100.00% | -287.24% | - | - | - | 0.26 | 74.18% | - | - | -287.24% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 152.17% | 100.00% | -52.17% | - | - | - | 0.66 | 34.28% | - | - | -52.17% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 136.26% | 100.00% | -36.26% | - | - | - | 0.73 | 26.61% | - | - | -36.26% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 53.78% | 100.00% | 46.22% | - | - | - | 1.86 | -85.96% | - | - | 46.22% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 254.20% | 100.00% | -154.20% | - | - | - | 0.39 | 60.66% | - | - | -154.20% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 257.40% | 100.00% | -157.40% | - | - | - | 0.39 | 61.15% | - | - | -157.40% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 278.20% | 100.00% | -178.20% | - | - | - | 0.36 | 64.06% | - | - | -178.20% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 24.23% | 100.00% | 75.77% | - | - | - | 4.13 | -312.68% | - | - | 75.77% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 75.48% | 100.00% | 24.52% | - | - | - | 1.32 | -32.49% | - | - | 24.52% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 75.76% | 100.00% | 24.24% | - | - | - | 1.32 | -31.99% | - | - | 24.24% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 105.46% | 100.00% | -5.46% | - | - | - | 0.95 | 5.18% | - | - | -5.46% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5172.41% | 100.00% | -5072.41% | - | - | - | 0.02 | 98.07% | - | - | -5072.41% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 249.90% | 100.00% | -149.90% | - | - | - | 0.40 | 59.98% | - | - | -149.90% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 131.47% | 100.00% | -31.47% | - | - | - | 0.76 | 23.94% | - | - | -31.47% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 123.41% | 100.00% | -23.41% | - | - | - | 0.81 | 18.97% | - | - | -23.41% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 77.70% | 100.00% | 22.30% | - | - | - | 1.29 | -28.70% | - | - | 22.30% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.69% | 100.00% | 90.31% | - | - | - | 10.31 | -931.47% | - | - | 90.31% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 169.41% | 100.00% | -69.41% | - | - | - | 0.59 | 40.97% | - | - | -69.41% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.27% | 100.00% | -109.27% | - | - | - | 0.48 | 52.21% | - | - | -109.27% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 97.73% | 100.00% | 2.27% | - | - | - | 1.02 | -2.32% | - | - | 2.27% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 141.24% | 100.00% | -41.24% | - | - | - | 0.71 | 29.20% | - | - | -41.24% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 581.56% | 100.00% | -481.56% | - | - | - | 0.17 | 82.80% | - | - | -481.56% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 96.41% | 100.00% | 3.59% | - | - | - | 1.04 | -3.73% | - | - | 3.59% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 54.60% | 100.00% | 45.40% | - | - | - | 1.83 | -83.16% | - | - | 45.40% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.82% | 100.00% | 56.18% | - | - | - | 2.28 | -128.20% | - | - | 56.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 43.82% | 100.00% | 56.18% | - | - | - | 2.28 | -128.20% | - | - | 56.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 45.18% | 100.00% | 54.82% | - | - | - | 2.21 | -121.36% | - | - | 54.82% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 55.32% | 100.00% | 44.68% | - | - | - | 1.81 | -80.76% | - | - | 44.68% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.84% | 100.00% | 95.16% | - | - | - | 20.67 | -1967.08% | - | - | 95.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 4.81% | 100.00% | 95.19% | - | - | - | 20.78 | -1978.17% | - | - | 95.19% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 31
|
- | - | - | - | - | - | 1.30% | 1.25% | 78.21% | 100.00% | 21.79% | - | - | - | 1.28 | -27.87% | - | - | 21.79% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 91.08% | 100.00% | 8.92% | - | - | - | 1.10 | -9.79% | - | - | 8.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 118.88% | 100.00% | -18.88% | - | - | - | 0.84 | 15.88% | - | - | -18.88% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 164.37% | 100.00% | -64.37% | - | - | - | 0.61 | 39.16% | - | - | -64.37% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 164.37% | 100.00% | -64.37% | - | - | - | 0.61 | 39.16% | - | - | -64.37% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 44.88% | 100.00% | 55.12% | - | - | - | 2.23 | -122.83% | - | - | 55.12% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 3301.11% | 100.00% | -3201.11% | - | - | - | 0.03 | 96.97% | - | - | -3201.11% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
MALLA DE REFUERZO 0.97X45.70 (44.32MST)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.08% | 100.00% | -44.08% | - | - | - | 0.69 | 30.60% | - | - | -44.08% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.47% | 100.00% | -6.47% | - | - | - | 0.94 | 6.08% | - | - | -6.47% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1787.42% | 100.00% | -1687.42% | - | - | - | 0.06 | 94.41% | - | - | -1687.42% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.15% | 100.00% | 74.85% | - | - | - | 3.98 | -297.59% | - | - | 74.85% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.38% | 100.00% | 87.62% | - | - | - | 8.08 | -708.06% | - | - | 87.62% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.38% | 100.00% | 87.62% | - | - | - | 8.08 | -708.06% | - | - | 87.62% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.45% | 100.00% | 97.55% | - | - | - | 40.89 | -3989.44% | - | - | 97.55% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1/2" PUNTA DE BROCA 37709 DE 7X7X16
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DECOPASTA EXTERIOR PARA TABLA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BASECOAT DUROCK SACO 22 KG USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TORNILLO DE 1 1/2" PARA DUROCK
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 1 5/8" X 10' (CAL 26)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 10' (CAL 22) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 101.73% | 100.00% | -1.73% | - | - | - | 0.98 | 1.70% | - | - | -1.73% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 127.02% | 100.00% | -27.02% | - | - | - | 0.79 | 21.27% | - | - | -27.02% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.07% | 100.00% | -72.07% | - | - | - | 0.58 | 41.88% | - | - | -72.07% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.28% | 100.00% | -6.28% | - | - | - | 0.94 | 5.91% | - | - | -6.28% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 47.07% | 100.00% | 52.93% | - | - | - | 2.12 | -112.45% | - | - | 52.93% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 99.60% | 100.00% | 0.40% | - | - | - | 1.00 | -0.40% | - | - | 0.40% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 82.89% | 100.00% | 17.11% | - | - | - | 1.21 | -20.65% | - | - | 17.11% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.59% | 100.00% | 62.41% | - | - | - | 2.66 | -166.06% | - | - | 62.41% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.45% | - | - | 16.97% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 83.03% | 100.00% | 16.97% | - | - | - | 1.20 | -20.45% | - | - | 16.97% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 163.33% | 100.00% | -63.33% | - | - | - | 0.61 | 38.77% | - | - | -63.33% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 82.11% | 100.00% | 17.89% | - | - | - | 1.22 | -21.78% | - | - | 17.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 84.87% | 100.00% | 15.13% | - | - | - | 1.18 | -17.82% | - | - | 15.13% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 926440.00% | 100.00% | -926340.00% | - | - | - | 0.00 | 99.99% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6776.38% | 100.00% | -6676.38% | - | - | - | 0.01 | 98.52% | - | - | -6676.38% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 319.88% | 100.00% | -219.88% | - | - | - | 0.31 | 68.74% | - | - | -219.88% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 106.10% | 100.00% | -6.10% | - | - | - | 0.94 | 5.75% | - | - | -6.10% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 97.73% | 100.00% | 2.27% | - | - | - | 1.02 | -2.33% | - | - | 2.27% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 65.16% | 100.00% | 34.84% | - | - | - | 1.53 | -53.46% | - | - | 34.84% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 89.46% | 100.00% | 10.54% | - | - | - | 1.12 | -11.78% | - | - | 10.54% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 190.08% | 100.00% | -90.08% | - | - | - | 0.53 | 47.39% | - | - | -90.08% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 232.66% | 100.00% | -132.66% | - | - | - | 0.43 | 57.02% | - | - | -132.66% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 49.86% | 100.00% | 50.14% | - | - | - | 2.01 | -100.57% | - | - | 50.14% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO FLUIDO 3003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 82.42% | 100.00% | 17.58% | - | - | - | 1.21 | -21.33% | - | - | 17.58% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 82.42% | 100.00% | 17.58% | - | - | - | 1.21 | -21.33% | - | - | 17.58% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 62.98% | 100.00% | 37.02% | - | - | - | 1.59 | -58.78% | - | - | 37.02% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 74.22% | 100.00% | 25.78% | - | - | - | 1.35 | -34.73% | - | - | 25.78% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 98.78% | 100.00% | 1.22% | - | - | - | 1.01 | -1.23% | - | - | 1.22% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13894.25% | 100.00% | -13794.25% | - | - | - | 0.01 | 99.28% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 289.59% | 100.00% | -189.59% | - | - | - | 0.35 | 65.47% | - | - | -189.59% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 122.82% | 100.00% | -22.82% | - | - | - | 0.81 | 18.58% | - | - | -22.82% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 88.39% | 100.00% | 11.61% | - | - | - | 1.13 | -13.14% | - | - | 11.61% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.56% | 100.00% | 27.44% | - | - | - | 1.38 | -37.83% | - | - | 27.44% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 282.38% | 100.00% | -182.38% | - | - | - | 0.35 | 64.59% | - | - | -182.38% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 69.76% | 100.00% | 30.24% | - | - | - | 1.43 | -43.36% | - | - | 30.24% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 576.67% | 100.00% | -476.67% | - | - | - | 0.17 | 82.66% | - | - | -476.67% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 150.61% | 100.00% | -50.61% | - | - | - | 0.66 | 33.60% | - | - | -50.61% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 879.41% | 100.00% | -779.41% | - | - | - | 0.11 | 88.63% | - | - | -779.41% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 84.69% | 100.00% | 15.31% | - | - | - | 1.18 | -18.08% | - | - | 15.31% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.87% | 100.00% | 43.13% | - | - | - | 1.76 | -75.83% | - | - | 43.13% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PLANCHA DE THERMOPOR DE 2*50*100 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.31% | 100.00% | 51.69% | - | - | - | 2.07 | -106.99% | - | - | 51.69% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 48.31% | 100.00% | 51.69% | - | - | - | 2.07 | -106.99% | - | - | 51.69% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 86.12% | 100.00% | 13.88% | - | - | - | 1.16 | -16.12% | - | - | 13.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 72.37% | 100.00% | 27.63% | - | - | - | 1.38 | -38.18% | - | - | 27.63% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 493.47% | 100.00% | -393.47% | - | - | - | 0.20 | 79.74% | - | - | -393.47% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 387.33% | 100.00% | -287.33% | - | - | - | 0.26 | 74.18% | - | - | -287.33% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 387.33% | 100.00% | -287.33% | - | - | - | 0.26 | 74.18% | - | - | -287.33% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1384.32 | -138332.00% | - | - | 99.93% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA FLEXIBLE 12' TRUPER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEPILLO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIA VIDRIO LIQUIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA PARA TRAPEADOR
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESCOBAS PLASTICAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DETERGENTE ESPUMIL 1000 GRS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESINFECTANTE OLIMPO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SQUEEGEE LIMPIADOR DE VIDRIOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 291.99% | 100.00% | -191.99% | - | - | - | 0.34 | 65.75% | - | - | -191.99% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 118.26% | 100.00% | -18.26% | - | - | - | 0.85 | 15.44% | - | - | -18.26% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 102.79% | 100.00% | -2.79% | - | - | - | 0.97 | 2.71% | - | - | -2.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE DE 3''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.86% | 100.00% | 0.14% | - | - | - | 1.00 | -0.14% | - | - | 0.14% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.92% | 100.00% | 4.08% | - | - | - | 1.04 | -4.25% | - | - | 4.08% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 1.38% | 100.00% | 98.62% | - | - | - | 72.28 | -7127.88% | - | - | 98.62% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 94.17% | 100.00% | 5.83% | - | - | - | 1.06 | -6.19% | - | - | 5.83% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.33% | 100.00% | -6.33% | - | - | - | 0.94 | 5.95% | - | - | -6.33% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.33% | 100.00% | -6.33% | - | - | - | 0.94 | 5.95% | - | - | -6.33% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 106.33% | 100.00% | -6.33% | - | - | - | 0.94 | 5.95% | - | - | -6.33% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 87.71% | 100.00% | 12.29% | - | - | - | 1.14 | -14.01% | - | - | 12.29% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.74% | 100.00% | 17.26% | - | - | - | 1.21 | -20.87% | - | - | 17.26% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 40.15% | 100.00% | 59.85% | - | - | - | 2.49 | -149.07% | - | - | 59.85% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 404.67 | -40367.00% | - | - | 99.75% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.08% | 100.00% | -3.08% | - | - | - | 0.97 | 2.99% | - | - | -3.08% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 84.56% | 100.00% | 15.44% | - | - | - | 1.18 | -18.26% | - | - | 15.44% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 78.34% | 100.00% | 21.66% | - | - | - | 1.28 | -27.64% | - | - | 21.66% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 65.52% | 100.00% | 34.48% | - | - | - | 1.53 | -52.62% | - | - | 34.48% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 29.53% | 100.00% | 70.47% | - | - | - | 3.39 | -238.68% | - | - | 70.47% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA COLONIAL STYLE LATEX MATE BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BB SELLADOR MULTIFUNCIONAL BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 46.11% | 100.00% | 53.89% | - | - | - | 2.17 | -116.88% | - | - | 53.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 130.90% | 100.00% | -30.90% | - | - | - | 0.76 | 23.61% | - | - | -30.90% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 126.79% | 100.00% | -26.79% | - | - | - | 0.79 | 21.13% | - | - | -26.79% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 193.01% | 100.00% | -93.01% | - | - | - | 0.52 | 48.19% | - | - | -93.01% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.89% | 100.00% | 61.11% | - | - | - | 2.57 | -157.14% | - | - | 61.11% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.09% | 100.00% | -10.09% | - | - | - | 0.91 | 9.17% | - | - | -10.09% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 286.43% | 100.00% | -186.43% | - | - | - | 0.35 | 65.09% | - | - | -186.43% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 136.03% | 100.00% | -36.03% | - | - | - | 0.74 | 26.49% | - | - | -36.03% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 70.18% | 100.00% | 29.82% | - | - | - | 1.42 | -42.50% | - | - | 29.82% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CHORRO DE ESFERA 1/2 P/MANGUERA GENEBRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BAJADA DE AGUA DE 3 ALUMINIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.04% | 100.00% | 98.96% | - | - | - | 96.19 | -9518.81% | - | - | 98.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 1.04% | 100.00% | 98.96% | - | - | - | 96.19 | -9518.81% | - | - | 98.96% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 12373.64 | -1237264.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 14.35% | 100.00% | 85.65% | - | - | - | 6.97 | -596.65% | - | - | 85.65% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CANAL 2-1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 54.88% | 100.00% | 45.12% | - | - | - | 1.82 | -82.21% | - | - | 45.12% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 100.13% | 100.00% | -0.13% | - | - | - | 1.00 | 0.13% | - | - | -0.13% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 103.14% | 100.00% | -3.14% | - | - | - | 0.97 | 3.04% | - | - | -3.14% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 100.00% | 100.00% | -0.00% | - | - | - | 1.00 | 0.00% | - | - | -0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1076.43 | -107543.00% | - | - | 99.91% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.91% | 100.00% | 96.09% | - | - | - | 25.59 | -2459.44% | - | - | 96.09% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5.70% | 100.00% | 94.30% | - | - | - | 17.55 | -1654.91% | - | - | 94.30% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 955.55 | -95455.00% | - | - | 99.90% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 3.85% | 100.00% | 96.15% | - | - | - | 25.95 | -2495.14% | - | - | 96.15% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 100.00% | 100.00% | - | - | - | 31851.65 | -3185065.00% | - | - | 100.00% | - | 0.00% |
|
CASA # 45
|
- | - | - | - | - | - | 1.30% | 1.25% | 69.09% | 89.85% | 20.76% | - | - | - | 1.30 | -30.04% | - | - | 23.10% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 77.24% | 77.70% | 0.46% | - | - | - | 1.01 | -0.59% | - | - | 0.59% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 150.69% | 100.00% | -50.69% | - | - | - | 0.66 | 33.64% | - | - | -50.69% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.03% | 100.00% | -44.03% | - | - | - | 0.69 | 30.57% | - | - | -44.03% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 119.53% | 100.00% | -19.53% | - | - | - | 0.84 | 16.34% | - | - | -19.53% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 188.38% | 100.00% | -88.38% | - | - | - | 0.53 | 46.92% | - | - | -88.38% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.70% | 100.00% | -72.70% | - | - | - | 0.58 | 42.10% | - | - | -72.70% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 172.70% | 100.00% | -72.70% | - | - | - | 0.58 | 42.10% | - | - | -72.70% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.95% | 100.00% | 17.05% | - | - | - | 1.21 | -20.56% | - | - | 17.05% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 82.95% | 100.00% | 17.05% | - | - | - | 1.21 | -20.56% | - | - | 17.05% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 59.31% | 100.00% | 40.69% | - | - | - | 1.69 | -68.61% | - | - | 40.69% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 113.64% | 100.00% | -13.64% | - | - | - | 0.88 | 12.00% | - | - | -13.64% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 109.62% | 100.00% | -9.62% | - | - | - | 0.91 | 8.77% | - | - | -9.62% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 89.81% | 100.00% | 10.19% | - | - | - | 1.11 | -11.34% | - | - | 10.19% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 87.81% | 100.00% | 12.19% | - | - | - | 1.14 | -13.88% | - | - | 12.19% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA BLANCO EXTRA FINO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA P/AGUA #150 H-98 O C-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 514.88% | 0.00% | -514.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPATULA METALICA DE 2" MANGO PLASTICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALCOHOL EN GEL ANTIBACTERIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 508.55% | 0.00% | -508.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 508.55% | 0.00% | -508.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 38.13% | 0.00% | -38.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 109.88% | 0.00% | -109.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 105.77% | 0.00% | -105.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 0.00% | -99.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 0.00% | -42.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 75.19% | 0.00% | -75.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
RODILLO CON FELPA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FELPA SIN RODILLO DE FIBRA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MINI FELPAS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.82% | 0.00% | -73.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 73.82% | 0.00% | -73.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 71.87% | 0.00% | -71.87% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 87.44% | 100.00% | 12.56% | - | - | - | 1.14 | -14.37% | - | - | 12.56% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 112.27% | 100.00% | -12.27% | - | - | - | 0.89 | 10.93% | - | - | -12.27% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 183.75% | 100.00% | -83.75% | - | - | - | 0.54 | 45.58% | - | - | -83.75% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 289315.56% | 100.00% | -289215.56% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 11676.25% | 100.00% | -11576.25% | - | - | - | 0.01 | 99.14% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2102.10% | 100.00% | -2002.10% | - | - | - | 0.05 | 95.24% | - | - | -2002.10% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
EPOXICO ICITY 400ML
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1049.14% | 100.00% | -949.14% | - | - | - | 0.10 | 90.47% | - | - | -949.14% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 1802.13% | 100.00% | -1702.13% | - | - | - | 0.06 | 94.45% | - | - | -1702.13% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 323.60% | 100.00% | -223.60% | - | - | - | 0.31 | 69.10% | - | - | -223.60% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 137.87% | 100.00% | -37.87% | - | - | - | 0.73 | 27.47% | - | - | -37.87% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 32.24% | 100.00% | 67.76% | - | - | - | 3.10 | -210.19% | - | - | 67.76% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 32.33% | 100.00% | 67.67% | - | - | - | 3.09 | -209.33% | - | - | 67.67% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 32.33% | 100.00% | 67.67% | - | - | - | 3.09 | -209.33% | - | - | 67.67% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 92.75% | 100.00% | 7.25% | - | - | - | 1.08 | -7.82% | - | - | 7.25% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 161.67% | 100.00% | -61.67% | - | - | - | 0.62 | 38.15% | - | - | -61.67% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 220.42% | 100.00% | -120.42% | - | - | - | 0.45 | 54.63% | - | - | -120.42% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 202.43% | 100.00% | -102.43% | - | - | - | 0.49 | 50.60% | - | - | -102.43% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 123.44% | 100.00% | -23.44% | - | - | - | 0.81 | 18.99% | - | - | -23.44% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 90.52% | 100.00% | 9.48% | - | - | - | 1.10 | -10.47% | - | - | 9.48% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.77% | 100.00% | 6.23% | - | - | - | 1.07 | -6.64% | - | - | 6.23% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.26% | 100.00% | -27.26% | - | - | - | 0.79 | 21.42% | - | - | -27.26% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 22.02% | 100.00% | 77.98% | - | - | - | 4.54 | -354.12% | - | - | 77.98% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 22.02% | 100.00% | 77.98% | - | - | - | 4.54 | -354.12% | - | - | 77.98% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.79% | 100.00% | -10.79% | - | - | - | 0.90 | 9.74% | - | - | -10.79% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 81.53% | 100.00% | 18.47% | - | - | - | 1.23 | -22.66% | - | - | 18.47% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 143.85% | 100.00% | -43.85% | - | - | - | 0.70 | 30.48% | - | - | -43.85% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 13625.45% | 100.00% | -13525.45% | - | - | - | 0.01 | 99.27% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4377.01% | 100.00% | -4277.01% | - | - | - | 0.02 | 97.72% | - | - | -4277.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 62720.00% | 100.00% | -62620.00% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 653.09% | 100.00% | -553.09% | - | - | - | 0.15 | 84.69% | - | - | -553.09% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 166.79% | 100.00% | -66.79% | - | - | - | 0.60 | 40.04% | - | - | -66.79% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 73.89% | 100.00% | 26.11% | - | - | - | 1.35 | -35.33% | - | - | 26.11% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 795.26% | 100.00% | -695.26% | - | - | - | 0.13 | 87.43% | - | - | -695.26% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.82% | 100.00% | -166.82% | - | - | - | 0.37 | 62.52% | - | - | -166.82% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.95% | 100.00% | -43.95% | - | - | - | 0.69 | 30.53% | - | - | -43.95% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 883.60% | 100.00% | -783.60% | - | - | - | 0.11 | 88.68% | - | - | -783.60% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('BLOCK LEVANTADOS EN MUROS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BLOCK DE 19X19X39 - 100KGS/CM2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.25% | 100.00% | 91.75% | - | - | - | 12.12 | -1112.01% | - | - | 91.75% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.25% | 100.00% | 91.75% | - | - | - | 12.12 | -1112.01% | - | - | 91.75% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y COMPLEMENTOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BOMBA PARA FUMIGAR (MATABI)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 65.54% | 100.00% | 34.46% | - | - | - | 1.53 | -52.57% | - | - | 34.46% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 115.88% | 100.00% | -15.88% | - | - | - | 0.86 | 13.71% | - | - | -15.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6794.37% | 100.00% | -6694.37% | - | - | - | 0.01 | 98.53% | - | - | -6694.37% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 100.00% | -2172.46% | - | - | - | 0.04 | 95.60% | - | - | -2172.46% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1794.43% | 100.00% | -1694.43% | - | - | - | 0.06 | 94.43% | - | - | -1694.43% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1794.43% | 100.00% | -1694.43% | - | - | - | 0.06 | 94.43% | - | - | -1694.43% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 198.05% | 100.00% | -98.05% | - | - | - | 0.50 | 49.51% | - | - | -98.05% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 131.91% | 100.00% | -31.91% | - | - | - | 0.76 | 24.19% | - | - | -31.91% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 2279.58% | 100.00% | -2179.58% | - | - | - | 0.04 | 95.61% | - | - | -2179.58% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 136.90% | 100.00% | -36.90% | - | - | - | 0.73 | 26.96% | - | - | -36.90% | - | 0.00% |
|
LIJA P/AGUA #220 H-98 O A-99 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIJA NO. 100 P/AGUA BASE DE LONA 3M
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
TUBO RECTANGULAR DE ALUMINIO DE 1 3/4" X 3" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO CIRCULAR CORTE DE MADERA 7 1/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.32% | 100.00% | 85.68% | - | - | - | 6.98 | -598.31% | - | - | 85.68% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 6.97% | 100.00% | 93.03% | - | - | - | 14.35 | -1335.00% | - | - | 93.03% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 26.76% | 100.00% | 73.24% | - | - | - | 3.74 | -273.63% | - | - | 73.24% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 436.89% | 100.00% | -336.89% | - | - | - | 0.23 | 77.11% | - | - | -336.89% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPERMEABILIZANTE FASTYL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PASTA TABLAROCA 28KG USG CUBETA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA MALLA ADHESIVA DE 4" X 300'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 35.37% | 100.00% | 64.63% | - | - | - | 2.83 | -182.76% | - | - | 64.63% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 35.37% | 100.00% | 64.63% | - | - | - | 2.83 | -182.76% | - | - | 64.63% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 3.85% | 86.12% | 82.27% | - | - | - | 22.38 | -2138.08% | - | - | 95.53% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 5.53% | 88.00% | 82.47% | - | - | - | 15.91 | -1491.40% | - | - | 93.72% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.71% | 88.00% | 78.29% | - | - | - | 9.06 | -806.29% | - | - | 88.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO PVC GRIS DE 2" X 3 MTS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VUELTA PVC GRIS DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 5.40% | 88.00% | 82.60% | - | - | - | 16.28 | -1528.33% | - | - | 93.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.95% | 84.00% | 82.05% | - | - | - | 43.00 | -4200.17% | - | - | 97.67% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 30.56% | 84.00% | 53.44% | - | - | - | 2.75 | -174.86% | - | - | 63.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 1.10% | 84.00% | 82.90% | - | - | - | 76.70 | -7570.04% | - | - | 98.70% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 47
|
- | - | - | - | - | - | 1.30% | 1.25% | 38.86% | 50.85% | 11.99% | - | - | - | 1.31 | -30.84% | - | - | 23.57% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 75.25% | 74.46% | -0.79% | - | - | - | 0.99 | 1.04% | - | - | -1.06% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 106.07% | 100.00% | -6.07% | - | - | - | 0.94 | 5.72% | - | - | -6.07% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 206.40% | 100.00% | -106.40% | - | - | - | 0.48 | 51.55% | - | - | -106.40% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 212.82% | 100.00% | -112.82% | - | - | - | 0.47 | 53.01% | - | - | -112.82% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 144.59% | 100.00% | -44.59% | - | - | - | 0.69 | 30.84% | - | - | -44.59% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.74% | 100.00% | 12.26% | - | - | - | 1.14 | -13.97% | - | - | 12.26% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.04% | 100.00% | -27.04% | - | - | - | 0.79 | 21.29% | - | - | -27.04% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 102.32% | 100.00% | -2.32% | - | - | - | 0.98 | 2.27% | - | - | -2.32% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 168.38% | 100.00% | -68.38% | - | - | - | 0.59 | 40.61% | - | - | -68.38% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6347.05% | 100.00% | -6247.05% | - | - | - | 0.02 | 98.42% | - | - | -6247.05% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 277.85% | 100.00% | -177.85% | - | - | - | 0.36 | 64.01% | - | - | -177.85% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 186.94% | 100.00% | -86.94% | - | - | - | 0.53 | 46.51% | - | - | -86.94% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 164.76% | 100.00% | -64.76% | - | - | - | 0.61 | 39.30% | - | - | -64.76% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 87.41% | 100.00% | 12.59% | - | - | - | 1.14 | -14.41% | - | - | 12.59% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 35.44% | 100.00% | 64.56% | - | - | - | 2.82 | -182.20% | - | - | 64.56% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 433.30% | 100.00% | -333.30% | - | - | - | 0.23 | 76.92% | - | - | -333.30% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 2721.01% | 100.00% | -2621.01% | - | - | - | 0.04 | 96.32% | - | - | -2621.01% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 28.38% | 100.00% | 71.62% | - | - | - | 3.52 | -252.30% | - | - | 71.62% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 28.38% | 100.00% | 71.62% | - | - | - | 3.52 | -252.30% | - | - | 71.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 69.33% | 100.00% | 30.67% | - | - | - | 1.44 | -44.23% | - | - | 30.67% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 130.30% | 100.00% | -30.30% | - | - | - | 0.77 | 23.25% | - | - | -30.30% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4377.01% | 100.00% | -4277.01% | - | - | - | 0.02 | 97.72% | - | - | -4277.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 62720.00% | 100.00% | -62620.00% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 473.84% | 100.00% | -373.84% | - | - | - | 0.21 | 78.90% | - | - | -373.84% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
YOMBOLON 3-32
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 179.73% | 100.00% | -79.73% | - | - | - | 0.56 | 44.36% | - | - | -79.73% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 102.74% | 100.00% | -2.74% | - | - | - | 0.97 | 2.67% | - | - | -2.74% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 401.48% | 100.00% | -301.48% | - | - | - | 0.25 | 75.09% | - | - | -301.48% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.56% | 100.00% | 61.44% | - | - | - | 2.59 | -159.32% | - | - | 61.44% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 173.72% | 100.00% | -73.72% | - | - | - | 0.58 | 42.44% | - | - | -73.72% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 315.52% | 100.00% | -215.52% | - | - | - | 0.32 | 68.31% | - | - | -215.52% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 963.70% | 100.00% | -863.70% | - | - | - | 0.10 | 89.62% | - | - | -863.70% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 110.02% | 100.00% | -10.02% | - | - | - | 0.91 | 9.11% | - | - | -10.02% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 192.21% | 100.00% | -92.21% | - | - | - | 0.52 | 47.97% | - | - | -92.21% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 39.16% | 0.00% | -39.16% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 44.52% | 0.00% | -44.52% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 48.04% | 0.00% | -48.04% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 0.00% | -71.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 138.01% | 0.00% | -138.01% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 111.24% | 0.00% | -111.24% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 1348.78% | 0.00% | -1348.78% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 24.88% | 0.00% | -24.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 67.74% | 0.00% | -67.74% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.38% | 0.00% | -12.38% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 12.38% | 0.00% | -12.38% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 36.12% | 0.00% | -36.12% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 36.12% | 0.00% | -36.12% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.52% | 86.12% | 84.60% | - | - | - | 56.53 | -5552.84% | - | - | 98.23% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.71% | 88.00% | 85.29% | - | - | - | 32.52 | -3152.24% | - | - | 96.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 84.00% | 83.81% | - | - | - | 438.47 | -43747.33% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 7.67% | 0.00% | -7.67% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.14% | 0.00% | -0.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 31.00% | 0.00% | -31.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 31.00% | 0.00% | -31.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 31.00% | 0.00% | -31.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 50.94% | 0.00% | -50.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 50.94% | 0.00% | -50.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 50.94% | 0.00% | -50.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 50.94% | 0.00% | -50.94% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 50
|
- | - | - | - | - | - | 1.30% | 1.25% | 34.48% | 50.85% | 16.37% | - | - | - | 1.47 | -47.47% | - | - | 32.19% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 70.79% | 74.46% | 3.67% | - | - | - | 1.05 | -5.18% | - | - | 4.92% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 122.19% | 100.00% | -22.19% | - | - | - | 0.82 | 18.16% | - | - | -22.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 203.38% | 100.00% | -103.38% | - | - | - | 0.49 | 50.83% | - | - | -103.38% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 433.25% | 100.00% | -333.25% | - | - | - | 0.23 | 76.92% | - | - | -333.25% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 27112.05% | 100.00% | -27012.05% | - | - | - | 0.00 | 99.63% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 271.86% | 100.00% | -171.86% | - | - | - | 0.37 | 63.22% | - | - | -171.86% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 91.24% | 100.00% | 8.76% | - | - | - | 1.10 | -9.60% | - | - | 8.76% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.28% | 100.00% | -0.28% | - | - | - | 1.00 | 0.28% | - | - | -0.28% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.47% | 100.00% | 18.53% | - | - | - | 1.23 | -22.74% | - | - | 18.53% | - | 0.00% |
|
CLAVO DE LAMINA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 40.26% | 100.00% | 59.74% | - | - | - | 2.48 | -148.38% | - | - | 59.74% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 40.26% | 100.00% | 59.74% | - | - | - | 2.48 | -148.38% | - | - | 59.74% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 88.09% | 100.00% | 11.91% | - | - | - | 1.14 | -13.53% | - | - | 11.91% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 157.08% | 100.00% | -57.08% | - | - | - | 0.64 | 36.34% | - | - | -57.08% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 39946.67% | 100.00% | -39846.67% | - | - | - | 0.00 | 99.75% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 187.45% | 100.00% | -87.45% | - | - | - | 0.53 | 46.65% | - | - | -87.45% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 155.51% | 100.00% | -55.51% | - | - | - | 0.64 | 35.70% | - | - | -55.51% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 138.76% | 100.00% | -38.76% | - | - | - | 0.72 | 27.93% | - | - | -38.76% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 196.67% | 100.00% | -96.67% | - | - | - | 0.51 | 49.15% | - | - | -96.67% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.81% | 100.00% | -43.81% | - | - | - | 0.70 | 30.46% | - | - | -43.81% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 10.04% | 100.00% | 89.96% | - | - | - | 9.96 | -896.02% | - | - | 89.96% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 10.04% | 100.00% | 89.96% | - | - | - | 9.96 | -896.02% | - | - | 89.96% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 57.28% | 100.00% | 42.72% | - | - | - | 1.75 | -74.59% | - | - | 42.72% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 107.64% | 100.00% | -7.64% | - | - | - | 0.93 | 7.10% | - | - | -7.64% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 345718.18% | 100.00% | -345618.18% | - | - | - | 0.00 | 99.97% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1847.29% | 100.00% | -1747.29% | - | - | - | 0.05 | 94.59% | - | - | -1747.29% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 455.64% | 100.00% | -355.64% | - | - | - | 0.22 | 78.05% | - | - | -355.64% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 110.02% | 100.00% | -10.02% | - | - | - | 0.91 | 9.11% | - | - | -10.02% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 98.91% | 100.00% | 1.09% | - | - | - | 1.01 | -1.10% | - | - | 1.09% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 44.66% | 100.00% | 55.34% | - | - | - | 2.24 | -123.92% | - | - | 55.34% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 38.56% | 100.00% | 61.44% | - | - | - | 2.59 | -159.32% | - | - | 61.44% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 316.39% | 100.00% | -216.39% | - | - | - | 0.32 | 68.39% | - | - | -216.39% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 184.18% | 100.00% | -84.18% | - | - | - | 0.54 | 45.70% | - | - | -84.18% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 486.62% | 100.00% | -386.62% | - | - | - | 0.21 | 79.45% | - | - | -386.62% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 46.35% | 0.00% | -46.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 37.19% | 0.00% | -37.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 48.04% | 0.00% | -48.04% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 0.00% | -71.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 532.82% | 0.00% | -532.82% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 69.58% | 0.00% | -69.58% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 73.42% | 0.00% | -73.42% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 21.27% | 0.00% | -21.27% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.35% | 0.00% | -145.35% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 0.00% | -61.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.88% | 0.00% | -61.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 52.14% | 0.00% | -52.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 52.14% | 0.00% | -52.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.52% | 86.12% | 84.60% | - | - | - | 56.53 | -5552.84% | - | - | 98.23% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.71% | 88.00% | 85.29% | - | - | - | 32.52 | -3152.24% | - | - | 96.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 84.00% | 83.81% | - | - | - | 438.47 | -43747.33% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 1.13% | 0.00% | -1.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 43
|
- | - | - | - | - | - | 1.30% | 1.25% | 57.22% | 88.06% | 30.84% | - | - | - | 1.54 | -53.89% | - | - | 35.02% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 61.47% | 72.52% | 11.05% | - | - | - | 1.18 | -17.98% | - | - | 15.24% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 131.60% | 100.00% | -31.60% | - | - | - | 0.76 | 24.01% | - | - | -31.60% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 176.16% | 100.00% | -76.16% | - | - | - | 0.57 | 43.23% | - | - | -76.16% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 107.92% | 100.00% | -7.92% | - | - | - | 0.93 | 7.34% | - | - | -7.92% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 107.35% | 100.00% | -7.35% | - | - | - | 0.93 | 6.85% | - | - | -7.35% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 86.95% | 100.00% | 13.05% | - | - | - | 1.15 | -15.01% | - | - | 13.05% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.28% | 100.00% | 67.72% | - | - | - | 3.10 | -209.74% | - | - | 67.72% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 95.05% | 100.00% | 4.95% | - | - | - | 1.05 | -5.21% | - | - | 4.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 94.54% | 100.00% | 5.46% | - | - | - | 1.06 | -5.78% | - | - | 5.46% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 28911.52 | -2891052.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 94.17% | 100.00% | 5.83% | - | - | - | 1.06 | -6.19% | - | - | 5.83% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 94.17% | 100.00% | 5.83% | - | - | - | 1.06 | -6.19% | - | - | 5.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 94.17% | 100.00% | 5.83% | - | - | - | 1.06 | -6.19% | - | - | 5.83% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 94.17% | 100.00% | 5.83% | - | - | - | 1.06 | -6.19% | - | - | 5.83% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 41.42% | 100.00% | 58.58% | - | - | - | 2.41 | -141.41% | - | - | 58.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 17.12% | 100.00% | 82.88% | - | - | - | 5.84 | -484.00% | - | - | 82.88% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 17.12% | 100.00% | 82.88% | - | - | - | 5.84 | -484.00% | - | - | 82.88% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 17.12% | 100.00% | 82.88% | - | - | - | 5.84 | -484.00% | - | - | 82.88% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 17.12% | 100.00% | 82.88% | - | - | - | 5.84 | -484.00% | - | - | 82.88% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 117.53% | 0.00% | -117.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 117.53% | 0.00% | -117.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 117.53% | 0.00% | -117.53% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.49% | 0.00% | -145.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.49% | 0.00% | -145.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 145.49% | 0.00% | -145.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 0.00% | -46.62% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 73.84% | 100.00% | 26.16% | - | - | - | 1.35 | -35.43% | - | - | 26.16% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 94.43% | 100.00% | 5.57% | - | - | - | 1.06 | -5.90% | - | - | 5.57% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 156.93% | 100.00% | -56.93% | - | - | - | 0.64 | 36.28% | - | - | -56.93% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 153933.33% | 100.00% | -153833.33% | - | - | - | 0.00 | 99.94% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
MEZCLON PREPARADO LA ROCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5005.01% | 100.00% | -4905.01% | - | - | - | 0.02 | 98.00% | - | - | -4905.01% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 178.75% | 100.00% | -78.75% | - | - | - | 0.56 | 44.06% | - | - | -78.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 148.46% | 100.00% | -48.46% | - | - | - | 0.67 | 32.64% | - | - | -48.46% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 130.68% | 100.00% | -30.68% | - | - | - | 0.77 | 23.48% | - | - | -30.68% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.43% | 100.00% | 35.57% | - | - | - | 1.55 | -55.20% | - | - | 35.57% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 331.58% | 100.00% | -231.58% | - | - | - | 0.30 | 69.84% | - | - | -231.58% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 24.38% | 100.00% | 75.62% | - | - | - | 4.10 | -310.24% | - | - | 75.62% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 24.38% | 100.00% | 75.62% | - | - | - | 4.10 | -310.24% | - | - | 75.62% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 82.27% | 100.00% | 17.73% | - | - | - | 1.22 | -21.55% | - | - | 17.73% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 138.62% | 100.00% | -38.62% | - | - | - | 0.72 | 27.86% | - | - | -38.62% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 68127.27% | 100.00% | -68027.27% | - | - | - | 0.00 | 99.85% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 318.91% | 100.00% | -218.91% | - | - | - | 0.31 | 68.64% | - | - | -218.91% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 213.63% | 100.00% | -113.63% | - | - | - | 0.47 | 53.19% | - | - | -113.63% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 77.37% | 100.00% | 22.63% | - | - | - | 1.29 | -29.24% | - | - | 22.63% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1396.43% | 100.00% | -1296.43% | - | - | - | 0.07 | 92.84% | - | - | -1296.43% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.99% | 100.00% | -166.99% | - | - | - | 0.37 | 62.55% | - | - | -166.99% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 159.25% | 100.00% | -59.25% | - | - | - | 0.63 | 37.21% | - | - | -59.25% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 926.42% | 100.00% | -826.42% | - | - | - | 0.11 | 89.21% | - | - | -826.42% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 18.99% | 100.00% | 81.01% | - | - | - | 5.27 | -426.65% | - | - | 81.01% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 18.99% | 100.00% | 81.01% | - | - | - | 5.27 | -426.65% | - | - | 81.01% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 54.03% | 100.00% | 45.97% | - | - | - | 1.85 | -85.10% | - | - | 45.97% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 77.18% | 100.00% | 22.82% | - | - | - | 1.30 | -29.57% | - | - | 22.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6422.51% | 100.00% | -6322.51% | - | - | - | 0.02 | 98.44% | - | - | -6322.51% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 268.11% | 100.00% | -168.11% | - | - | - | 0.37 | 62.70% | - | - | -168.11% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 184.86% | 100.00% | -84.86% | - | - | - | 0.54 | 45.90% | - | - | -84.86% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3846.06% | 100.00% | -3746.06% | - | - | - | 0.03 | 97.40% | - | - | -3746.06% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 100.00% | 7.18% | - | - | - | 1.08 | -7.74% | - | - | 7.18% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 92.82% | 100.00% | 7.18% | - | - | - | 1.08 | -7.74% | - | - | 7.18% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 35.80% | 100.00% | 64.20% | - | - | - | 2.79 | -179.32% | - | - | 64.20% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 22.74% | 100.00% | 77.26% | - | - | - | 4.40 | -339.74% | - | - | 77.26% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 8.92% | 100.00% | 91.08% | - | - | - | 11.21 | -1020.71% | - | - | 91.08% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 10923.05% | 100.00% | -10823.05% | - | - | - | 0.01 | 99.08% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 20.40% | 100.00% | 79.60% | - | - | - | 4.90 | -390.24% | - | - | 79.60% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESPIGAS DE HULE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.27% | 100.00% | 59.73% | - | - | - | 2.48 | -148.32% | - | - | 59.73% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 40.27% | 100.00% | 59.73% | - | - | - | 2.48 | -148.32% | - | - | 59.73% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 42.61% | 100.00% | 57.39% | - | - | - | 2.35 | -134.67% | - | - | 57.39% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 78.76% | 100.00% | 21.24% | - | - | - | 1.27 | -26.97% | - | - | 21.24% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 138.39% | 100.00% | -38.39% | - | - | - | 0.72 | 27.74% | - | - | -38.39% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.00% | 100.00% | 29.00% | - | - | - | 1.41 | -40.84% | - | - | 29.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.83% | 100.00% | 6.17% | - | - | - | 1.07 | -6.58% | - | - | 6.17% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.02% | 100.00% | -27.02% | - | - | - | 0.79 | 21.27% | - | - | -27.02% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 38.02% | 100.00% | 61.98% | - | - | - | 2.63 | -163.01% | - | - | 61.98% | - | 0.00% |
|
SERVICIO DE BOMBEO COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIO DE COLOCACION COBRO MINIMO < 4M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 4.87% | 100.00% | 95.13% | - | - | - | 20.52 | -1952.35% | - | - | 95.13% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 4.20% | 86.12% | 81.92% | - | - | - | 20.49 | -1948.70% | - | - | 95.12% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 5.38% | 88.00% | 82.62% | - | - | - | 16.34 | -1534.21% | - | - | 93.88% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 5.40% | 88.00% | 82.60% | - | - | - | 16.28 | -1528.28% | - | - | 93.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4.73% | 88.00% | 83.27% | - | - | - | 18.60 | -1759.92% | - | - | 94.62% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 2.87% | 84.00% | 81.13% | - | - | - | 29.24 | -2823.78% | - | - | 96.58% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 78.95% | 84.00% | 5.05% | - | - | - | 1.06 | -6.39% | - | - | 6.01% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.59% | 84.00% | 83.41% | - | - | - | 142.24 | -14124.02% | - | - | 99.30% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 51
|
- | - | - | - | - | - | 1.30% | 1.25% | 32.87% | 50.85% | 17.98% | - | - | - | 1.55 | -54.71% | - | - | 35.36% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 67.42% | 74.46% | 7.04% | - | - | - | 1.10 | -10.45% | - | - | 9.46% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 92.48% | 100.00% | 7.52% | - | - | - | 1.08 | -8.13% | - | - | 7.52% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 179.80% | 100.00% | -79.80% | - | - | - | 0.56 | 44.38% | - | - | -79.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 270.17% | 100.00% | -170.17% | - | - | - | 0.37 | 62.99% | - | - | -170.17% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.50% | 100.00% | -29.50% | - | - | - | 0.77 | 22.78% | - | - | -29.50% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 90.62% | 100.00% | 9.38% | - | - | - | 1.10 | -10.35% | - | - | 9.38% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.28% | 100.00% | -0.28% | - | - | - | 1.00 | 0.28% | - | - | -0.28% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 82.86% | 100.00% | 17.14% | - | - | - | 1.21 | -20.69% | - | - | 17.14% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
HILO NYLON P/ALBAÑIL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 63.80% | 100.00% | 36.20% | - | - | - | 1.57 | -56.74% | - | - | 36.20% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 119.90% | 100.00% | -19.90% | - | - | - | 0.83 | 16.60% | - | - | -19.90% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1728.93% | 100.00% | -1628.93% | - | - | - | 0.06 | 94.22% | - | - | -1628.93% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 157.31% | 100.00% | -57.31% | - | - | - | 0.64 | 36.43% | - | - | -57.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 55.94% | 100.00% | 44.06% | - | - | - | 1.79 | -78.76% | - | - | 44.06% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5325.36 | -532436.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 165.16% | 100.00% | -65.16% | - | - | - | 0.61 | 39.45% | - | - | -65.16% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 219.49% | 100.00% | -119.49% | - | - | - | 0.46 | 54.44% | - | - | -119.49% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 140.82% | 100.00% | -40.82% | - | - | - | 0.71 | 28.99% | - | - | -40.82% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 23778.62 | -2377762.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 23778.62 | -2377762.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 53.61% | 100.00% | 46.39% | - | - | - | 1.87 | -86.55% | - | - | 46.39% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 100.74% | 100.00% | -0.74% | - | - | - | 0.99 | 0.74% | - | - | -0.74% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 229003.64% | 100.00% | -228903.64% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 821.02% | 100.00% | -721.02% | - | - | - | 0.12 | 87.82% | - | - | -721.02% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 131.47% | 100.00% | -31.47% | - | - | - | 0.76 | 23.94% | - | - | -31.47% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 97.91% | 100.00% | 2.09% | - | - | - | 1.02 | -2.13% | - | - | 2.09% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 44.66% | 100.00% | 55.34% | - | - | - | 2.24 | -123.92% | - | - | 55.34% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 41.20% | 100.00% | 58.80% | - | - | - | 2.43 | -142.73% | - | - | 58.80% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 316.39% | 100.00% | -216.39% | - | - | - | 0.32 | 68.39% | - | - | -216.39% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 180.69% | 100.00% | -80.69% | - | - | - | 0.55 | 44.66% | - | - | -80.69% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 446.87% | 100.00% | -346.87% | - | - | - | 0.22 | 77.62% | - | - | -346.87% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 78.56% | 0.00% | -78.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 38.69% | 0.00% | -38.69% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 50.72% | 0.00% | -50.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 89.19% | 0.00% | -89.19% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5051.66% | 0.00% | -5051.66% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 2272.46% | 0.00% | -2272.46% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 160.44% | 0.00% | -160.44% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 147.04% | 0.00% | -147.04% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 103.15% | 0.00% | -103.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 103.15% | 0.00% | -103.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.52% | 86.12% | 84.60% | - | - | - | 56.53 | -5552.84% | - | - | 98.23% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.71% | 88.00% | 85.29% | - | - | - | 32.52 | -3152.24% | - | - | 96.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 84.00% | 83.81% | - | - | - | 438.47 | -43747.33% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 1.13% | 0.00% | -1.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 44
|
- | - | - | - | - | - | 1.30% | 1.25% | 55.72% | 89.85% | 34.13% | - | - | - | 1.61 | -61.26% | - | - | 37.99% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 81.72% | 77.70% | -4.02% | - | - | - | 0.95 | 4.92% | - | - | -5.18% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 174.21% | 100.00% | -74.21% | - | - | - | 0.57 | 42.60% | - | - | -74.21% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 173.82% | 100.00% | -73.82% | - | - | - | 0.58 | 42.47% | - | - | -73.82% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 79.28% | 100.00% | 20.72% | - | - | - | 1.26 | -26.13% | - | - | 20.72% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 74.72% | 100.00% | 25.28% | - | - | - | 1.34 | -33.84% | - | - | 25.28% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 129.82% | 100.00% | -29.82% | - | - | - | 0.77 | 22.97% | - | - | -29.82% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 173.46% | 100.00% | -73.46% | - | - | - | 0.58 | 42.35% | - | - | -73.46% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 106.63% | 100.00% | -6.63% | - | - | - | 0.94 | 6.22% | - | - | -6.63% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 106.63% | 100.00% | -6.63% | - | - | - | 0.94 | 6.22% | - | - | -6.63% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 475.62 | -47462.00% | - | - | 99.79% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2165.00 | -216400.00% | - | - | 99.95% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 59.31% | 100.00% | 40.69% | - | - | - | 1.69 | -68.61% | - | - | 40.69% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 446.44 | -44544.00% | - | - | 99.78% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 7561.51 | -756051.00% | - | - | 99.99% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 32.30% | 100.00% | 67.70% | - | - | - | 3.10 | -209.63% | - | - | 67.70% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA ACERO MA GR 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANGOLA GRIS MA 20X66 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 96.66% | 100.00% | 3.34% | - | - | - | 1.03 | -3.45% | - | - | 3.34% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 46.62% | 100.00% | 53.38% | - | - | - | 2.15 | -114.50% | - | - | 53.38% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 2.20% | 100.00% | 97.80% | - | - | - | 45.46 | -4445.82% | - | - | 97.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3385.73 | -338473.00% | - | - | 99.97% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.34% | 0.00% | -129.34% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.34% | 0.00% | -129.34% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 129.34% | 0.00% | -129.34% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 364.89% | 0.00% | -364.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 364.89% | 0.00% | -364.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 364.89% | 0.00% | -364.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 38.13% | 0.00% | -38.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 109.88% | 0.00% | -109.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 105.77% | 0.00% | -105.77% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 99.89% | 0.00% | -99.89% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
GRIFO TIPO MEZCLADORA P/LAVATRASTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 80.72% | 0.00% | -80.72% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 148.15% | 0.00% | -148.15% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE TIPO PUSH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 96.70% | 0.00% | -96.70% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 42.88% | 0.00% | -42.88% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESAGUE LAVAMANOS TIPO REJILLA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAÑO BAJO HOME
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REJILLA DUCHA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.78% | 0.00% | -0.78% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCHA DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2116.34 | -211534.00% | - | - | 99.95% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25107.78 | -2510678.00% | - | - | 100.00% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 56.49% | 100.00% | 43.51% | - | - | - | 1.77 | -77.03% | - | - | 43.51% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 95.21% | 100.00% | 4.79% | - | - | - | 1.05 | -5.03% | - | - | 4.79% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 172.96% | 100.00% | -72.96% | - | - | - | 0.58 | 42.18% | - | - | -72.96% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 64046.07% | 100.00% | -63946.07% | - | - | - | 0.00 | 99.84% | - | - | 0.00% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
PIEDRIN DE 3/8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 812.70% | 100.00% | -712.70% | - | - | - | 0.12 | 87.70% | - | - | -712.70% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 50857.43% | 100.00% | -50757.43% | - | - | - | 0.00 | 99.80% | - | - | 0.00% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 225.48% | 100.00% | -125.48% | - | - | - | 0.44 | 55.65% | - | - | -125.48% | - | 0.00% |
|
SERVICIO DE COLOCACION DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.49% | 100.00% | -107.49% | - | - | - | 0.48 | 51.81% | - | - | -107.49% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 122.03% | 100.00% | -22.03% | - | - | - | 0.82 | 18.05% | - | - | -22.03% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.82% | 100.00% | 27.18% | - | - | - | 1.37 | -37.33% | - | - | 27.18% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 93.77% | 100.00% | 6.23% | - | - | - | 1.07 | -6.64% | - | - | 6.23% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.26% | 100.00% | -27.26% | - | - | - | 0.79 | 21.42% | - | - | -27.26% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.07% | 100.00% | 62.93% | - | - | - | 2.70 | -169.75% | - | - | 62.93% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.41% | 100.00% | 85.59% | - | - | - | 6.94 | -593.96% | - | - | 85.59% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 14.41% | 100.00% | 85.59% | - | - | - | 6.94 | -593.96% | - | - | 85.59% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 110.79% | 100.00% | -10.79% | - | - | - | 0.90 | 9.74% | - | - | -10.79% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 70.84% | 100.00% | 29.16% | - | - | - | 1.41 | -41.17% | - | - | 29.16% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 122.68% | 100.00% | -22.68% | - | - | - | 0.82 | 18.49% | - | - | -22.68% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 821.02% | 100.00% | -721.02% | - | - | - | 0.12 | 87.82% | - | - | -721.02% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 389.89% | 100.00% | -289.89% | - | - | - | 0.26 | 74.35% | - | - | -289.89% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 166.24% | 100.00% | -66.24% | - | - | - | 0.60 | 39.85% | - | - | -66.24% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 107.03% | 100.00% | -7.03% | - | - | - | 0.93 | 6.57% | - | - | -7.03% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 72.80% | 100.00% | 27.20% | - | - | - | 1.37 | -37.36% | - | - | 27.20% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 795.26% | 100.00% | -695.26% | - | - | - | 0.13 | 87.43% | - | - | -695.26% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.82% | 100.00% | -166.82% | - | - | - | 0.37 | 62.52% | - | - | -166.82% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.05% | 100.00% | -44.05% | - | - | - | 0.69 | 30.58% | - | - | -44.05% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 883.60% | 100.00% | -783.60% | - | - | - | 0.11 | 88.68% | - | - | -783.60% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 12.40% | 100.00% | 87.60% | - | - | - | 8.07 | -706.77% | - | - | 87.60% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 12.40% | 100.00% | 87.60% | - | - | - | 8.07 | -706.77% | - | - | 87.60% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 46.74% | 100.00% | 53.26% | - | - | - | 2.14 | -113.95% | - | - | 53.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 74.27% | 100.00% | 25.73% | - | - | - | 1.35 | -34.64% | - | - | 25.73% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 5544.59% | 100.00% | -5444.59% | - | - | - | 0.02 | 98.20% | - | - | -5444.59% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SILICONE SISTA 280ML BLANCO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 439.33% | 100.00% | -339.33% | - | - | - | 0.23 | 77.24% | - | - | -339.33% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 439.33% | 100.00% | -339.33% | - | - | - | 0.23 | 77.24% | - | - | -339.33% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 191.29% | 100.00% | -91.29% | - | - | - | 0.52 | 47.72% | - | - | -91.29% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 119.81% | 100.00% | -19.81% | - | - | - | 0.83 | 16.54% | - | - | -19.81% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 3217.96% | 100.00% | -3117.96% | - | - | - | 0.03 | 96.89% | - | - | -3117.96% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 61.74% | 100.00% | 38.26% | - | - | - | 1.62 | -61.98% | - | - | 38.26% | - | 0.00% |
|
DISCOS P/CORTE D/CONCRETO DIAMANTADO DE 9"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCOS P/CORTE D/METAL DE 4 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 5/8 X 8"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 35.80% | 100.00% | 64.20% | - | - | - | 2.79 | -179.32% | - | - | 64.20% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 15.09% | 100.00% | 84.91% | - | - | - | 6.63 | -562.69% | - | - | 84.91% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 39.24% | 100.00% | 60.76% | - | - | - | 2.55 | -154.82% | - | - | 60.76% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 425.36% | 100.00% | -325.36% | - | - | - | 0.24 | 76.49% | - | - | -325.36% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 343.72% | 100.00% | -243.72% | - | - | - | 0.29 | 70.91% | - | - | -243.72% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('PINTURAS, SOLVENTES E IMPERMEABILIZANTE',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
THINNER
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 29.41% | 100.00% | 70.59% | - | - | - | 3.40 | -240.04% | - | - | 70.59% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 29.41% | 100.00% | 70.59% | - | - | - | 3.40 | -240.04% | - | - | 70.59% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUMINISTRO PARA HERRAMIENTA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TENSOR GALVANIZADO E 1/2 PLG 680 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 31.69% | 100.00% | 68.31% | - | - | - | 3.16 | -215.60% | - | - | 68.31% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 48.85% | 100.00% | 51.15% | - | - | - | 2.05 | -104.70% | - | - | 51.15% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 178.75% | 100.00% | -78.75% | - | - | - | 0.56 | 44.06% | - | - | -78.75% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 140.22% | 100.00% | -40.22% | - | - | - | 0.71 | 28.68% | - | - | -40.22% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 119.77% | 100.00% | -19.77% | - | - | - | 0.83 | 16.51% | - | - | -19.77% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 64.46% | 100.00% | 35.54% | - | - | - | 1.55 | -55.15% | - | - | 35.54% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT COMERCIAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 292.11% | 100.00% | -192.11% | - | - | - | 0.34 | 65.77% | - | - | -192.11% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 220.72% | 100.00% | -120.72% | - | - | - | 0.45 | 54.69% | - | - | -120.72% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 337.18% | 100.00% | -237.18% | - | - | - | 0.30 | 70.34% | - | - | -237.18% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 0.00% | 100.00% | 100.00% | - | - | - | 16308.96 | -1630796.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 12.69% | 100.00% | 87.31% | - | - | - | 7.88 | -687.73% | - | - | 87.31% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 12.69% | 100.00% | 87.31% | - | - | - | 7.88 | -687.73% | - | - | 87.31% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 3.08% | 86.12% | 83.04% | - | - | - | 27.96 | -2696.27% | - | - | 96.42% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 5.25% | 88.00% | 82.75% | - | - | - | 16.77 | -1577.13% | - | - | 94.04% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 5.40% | 88.00% | 82.60% | - | - | - | 16.28 | -1528.28% | - | - | 93.86% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.64% | 84.00% | 83.36% | - | - | - | 131.57 | -13057.34% | - | - | 99.24% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.46% | 84.00% | 83.54% | - | - | - | 182.51 | -18150.60% | - | - | 99.45% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
CASA # 53
|
- | - | - | - | - | - | 1.30% | 1.25% | 36.55% | 63.05% | 26.50% | - | - | - | 1.73 | -72.51% | - | - | 42.03% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 67.22% | 100.00% | 32.78% | - | - | - | 1.49 | -48.76% | - | - | 32.78% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 108.18% | 100.00% | -8.18% | - | - | - | 0.92 | 7.56% | - | - | -8.18% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 186.70% | 100.00% | -86.70% | - | - | - | 0.54 | 46.44% | - | - | -86.70% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 285.07% | 100.00% | -185.07% | - | - | - | 0.35 | 64.92% | - | - | -185.07% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 101.20% | 100.00% | -1.20% | - | - | - | 0.99 | 1.19% | - | - | -1.20% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.74% | 100.00% | 12.26% | - | - | - | 1.14 | -13.97% | - | - | 12.26% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.04% | 100.00% | -27.04% | - | - | - | 0.79 | 21.29% | - | - | -27.04% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.18% | 100.00% | 28.82% | - | - | - | 1.40 | -40.50% | - | - | 28.82% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 27.87% | 100.00% | 72.13% | - | - | - | 3.59 | -258.87% | - | - | 72.13% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 27.87% | 100.00% | 72.13% | - | - | - | 3.59 | -258.87% | - | - | 72.13% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 75.10% | 100.00% | 24.90% | - | - | - | 1.33 | -33.16% | - | - | 24.90% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 125.68% | 100.00% | -25.68% | - | - | - | 0.80 | 20.43% | - | - | -25.68% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 488240.00% | 100.00% | -488140.00% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 187.32% | 100.00% | -87.32% | - | - | - | 0.53 | 46.61% | - | - | -87.32% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 33.13% | 100.00% | 66.87% | - | - | - | 3.02 | -201.81% | - | - | 66.87% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 27.75% | 100.00% | 72.25% | - | - | - | 3.60 | -260.30% | - | - | 72.25% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5325.36 | -532436.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.81% | 100.00% | -43.81% | - | - | - | 0.70 | 30.46% | - | - | -43.81% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 62.60% | 100.00% | 37.40% | - | - | - | 1.60 | -59.76% | - | - | 37.40% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.74% | 100.00% | 6.26% | - | - | - | 1.07 | -6.68% | - | - | 6.26% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 93.74% | 100.00% | 6.26% | - | - | - | 1.07 | -6.68% | - | - | 6.26% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 11.77% | 100.00% | 88.23% | - | - | - | 8.50 | -749.59% | - | - | 88.23% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 1713.55% | 100.00% | -1613.55% | - | - | - | 0.06 | 94.16% | - | - | -1613.55% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 154.69% | 100.00% | -54.69% | - | - | - | 0.65 | 35.36% | - | - | -54.69% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 154.69% | 100.00% | -54.69% | - | - | - | 0.65 | 35.36% | - | - | -54.69% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 39.27% | 100.00% | 60.73% | - | - | - | 2.55 | -154.63% | - | - | 60.73% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 248.91 | -24791.00% | - | - | 99.60% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 14.41 | -1341.00% | - | - | 93.06% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 5.27% | 100.00% | 94.73% | - | - | - | 18.97 | -1797.09% | - | - | 94.73% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 5.56% | 100.00% | 94.44% | - | - | - | 17.98 | -1697.97% | - | - | 94.44% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 71.88 | -7088.00% | - | - | 98.61% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 869.44 | -86844.00% | - | - | 99.88% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 50.28% | 100.00% | 49.72% | - | - | - | 1.99 | -98.89% | - | - | 49.72% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 87.57% | 100.00% | 12.43% | - | - | - | 1.14 | -14.20% | - | - | 12.43% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 280336.36% | 100.00% | -280236.36% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 126.26% | 100.00% | -26.26% | - | - | - | 0.79 | 20.80% | - | - | -26.26% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 108.36% | 100.00% | -8.36% | - | - | - | 0.92 | 7.71% | - | - | -8.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 57.18% | 100.00% | 42.82% | - | - | - | 1.75 | -74.88% | - | - | 42.82% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.38% | 100.00% | 74.62% | - | - | - | 3.94 | -293.96% | - | - | 74.62% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 176.25% | 100.00% | -76.25% | - | - | - | 0.57 | 43.26% | - | - | -76.25% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.07% | 100.00% | -69.07% | - | - | - | 0.59 | 40.85% | - | - | -69.07% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 446.87% | 100.00% | -346.87% | - | - | - | 0.22 | 77.62% | - | - | -346.87% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.21% | 100.00% | 91.79% | - | - | - | 12.17 | -1117.35% | - | - | 91.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.21% | 100.00% | 91.79% | - | - | - | 12.17 | -1117.35% | - | - | 91.79% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 2.86% | 86.12% | 83.26% | - | - | - | 30.11 | -2910.70% | - | - | 96.68% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 5.03% | 88.00% | 82.97% | - | - | - | 17.50 | -1650.16% | - | - | 94.29% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 5.18% | 88.00% | 82.82% | - | - | - | 16.99 | -1599.18% | - | - | 94.11% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.42% | 84.00% | 83.58% | - | - | - | 200.67 | -19967.03% | - | - | 99.50% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.37% | 84.00% | 69.63% | - | - | - | 5.84 | -484.48% | - | - | 82.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 11.39% | 0.00% | -11.39% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 5.93% | 0.00% | -5.93% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO ACERADO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 41.42% | 0.00% | -41.42% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('TABLAYESO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
FULMINANTE CAL.27 AMARILLO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROCK EXTERIOR 8' X 4' X 1/2" USG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DN27 1" C/ARANDELA SIN REMACHE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POSTE DE 2 1/2" X 12' (CAL 26) LMS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 53.49% | 0.00% | -53.49% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 81.91% | 0.00% | -81.91% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 81.91% | 0.00% | -81.91% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC PLUS ADHESIVO PARA CERAMICA GRIS DE 20KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGATEC SISATEC SISA NEGRO DE 10 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANDORRA ACERO GR 43X43
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO ANGOLA GRIS 20X66
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SAMBORO PISO CERAMICO ANDORRA PLOMO MA 43X43 A
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 2.12% | 0.00% | -2.12% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 49
|
- | - | - | - | - | - | 1.30% | 1.25% | 33.31% | 63.05% | 29.74% | - | - | - | 1.89 | -89.28% | - | - | 47.17% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 68.18% | 100.00% | 31.82% | - | - | - | 1.47 | -46.66% | - | - | 31.82% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 101.05% | 100.00% | -1.05% | - | - | - | 0.99 | 1.04% | - | - | -1.05% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 175.93% | 100.00% | -75.93% | - | - | - | 0.57 | 43.16% | - | - | -75.93% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 272.11% | 100.00% | -172.11% | - | - | - | 0.37 | 63.25% | - | - | -172.11% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 89.65% | 100.00% | 10.35% | - | - | - | 1.12 | -11.54% | - | - | 10.35% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 98.49% | 100.00% | 1.51% | - | - | - | 1.02 | -1.54% | - | - | 1.51% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 82.86% | 100.00% | 17.14% | - | - | - | 1.21 | -20.69% | - | - | 17.14% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.18% | 100.00% | 28.82% | - | - | - | 1.40 | -40.50% | - | - | 28.82% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 24.24% | 100.00% | 75.76% | - | - | - | 4.13 | -312.59% | - | - | 75.76% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 24.24% | 100.00% | 75.76% | - | - | - | 4.13 | -312.59% | - | - | 75.76% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 73.77% | 100.00% | 26.23% | - | - | - | 1.36 | -35.56% | - | - | 26.23% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.82% | 100.00% | 0.18% | - | - | - | 1.00 | -0.18% | - | - | 0.18% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 99.82% | 100.00% | 0.18% | - | - | - | 1.00 | -0.18% | - | - | 0.18% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 31.43% | 100.00% | 68.57% | - | - | - | 3.18 | -218.16% | - | - | 68.57% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 144.11% | 100.00% | -44.11% | - | - | - | 0.69 | 30.61% | - | - | -44.11% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 133.48% | 100.00% | -33.48% | - | - | - | 0.75 | 25.08% | - | - | -33.48% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 728.52% | 100.00% | -628.52% | - | - | - | 0.14 | 86.27% | - | - | -628.52% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 48.04% | 100.00% | 51.96% | - | - | - | 2.08 | -108.15% | - | - | 51.96% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.35% | 100.00% | 28.65% | - | - | - | 1.40 | -40.15% | - | - | 28.65% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 14.41 | -1341.00% | - | - | 93.06% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 47.65% | 100.00% | 52.35% | - | - | - | 2.10 | -109.88% | - | - | 52.35% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 61.74% | 100.00% | 38.26% | - | - | - | 1.62 | -61.98% | - | - | 38.26% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 116.02% | 100.00% | -16.02% | - | - | - | 0.86 | 13.81% | - | - | -16.02% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 203127.27% | 100.00% | -203027.27% | - | - | - | 0.00 | 99.95% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 124.95% | 100.00% | -24.95% | - | - | - | 0.80 | 19.97% | - | - | -24.95% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 75.95% | 100.00% | 24.05% | - | - | - | 1.32 | -31.67% | - | - | 24.05% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 35.93% | 100.00% | 64.07% | - | - | - | 2.78 | -178.35% | - | - | 64.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 316.39% | 100.00% | -216.39% | - | - | - | 0.32 | 68.39% | - | - | -216.39% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 199.29% | 100.00% | -99.29% | - | - | - | 0.50 | 49.82% | - | - | -99.29% | - | 0.00% |
|
CLAVO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 1003.45% | 100.00% | -903.45% | - | - | - | 0.10 | 90.03% | - | - | -903.45% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 121.61% | 100.00% | -21.61% | - | - | - | 0.82 | 17.77% | - | - | -21.61% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 60.92% | 100.00% | 39.08% | - | - | - | 1.64 | -64.16% | - | - | 39.08% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 57.37% | 100.00% | 42.63% | - | - | - | 1.74 | -74.32% | - | - | 42.63% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 107.81% | 100.00% | -7.81% | - | - | - | 0.93 | 7.24% | - | - | -7.81% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 46604.44% | 100.00% | -46504.44% | - | - | - | 0.00 | 99.79% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 4254.25% | 100.00% | -4154.25% | - | - | - | 0.02 | 97.65% | - | - | -4154.25% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 266.64% | 100.00% | -166.64% | - | - | - | 0.38 | 62.50% | - | - | -166.64% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 161.98% | 100.00% | -61.98% | - | - | - | 0.62 | 38.26% | - | - | -61.98% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 27.37% | 100.00% | 72.63% | - | - | - | 3.65 | -265.33% | - | - | 72.63% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5325.36 | -532436.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.55% | 100.00% | -6.55% | - | - | - | 0.94 | 6.15% | - | - | -6.55% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 631.67% | 100.00% | -531.67% | - | - | - | 0.16 | 84.17% | - | - | -531.67% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 23778.62 | -2377762.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 23778.62 | -2377762.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.67% | 86.12% | 84.45% | - | - | - | 51.48 | -5047.86% | - | - | 98.06% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.99% | 88.00% | 85.01% | - | - | - | 29.45 | -2845.18% | - | - | 96.60% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 9.69% | 88.00% | 78.31% | - | - | - | 9.09 | -808.55% | - | - | 88.99% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CINTA DE AISLAR SCOTCH
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 84.00% | 83.81% | - | - | - | 438.47 | -43747.33% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 1.28% | 0.00% | -1.28% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.14% | 0.00% | -14.14% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
WIPE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('LIMPIEZA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TOALLA DE MICROFIBRA 20U SURTIDO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 52
|
- | - | - | - | - | - | 1.30% | 1.25% | 30.52% | 63.05% | 32.53% | - | - | - | 2.07 | -106.60% | - | - | 51.60% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 62.40% | 100.00% | 37.60% | - | - | - | 1.60 | -60.25% | - | - | 37.60% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 76.05% | 100.00% | 23.95% | - | - | - | 1.31 | -31.49% | - | - | 23.95% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 147.98% | 100.00% | -47.98% | - | - | - | 0.68 | 32.43% | - | - | -47.98% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 207.89% | 100.00% | -107.89% | - | - | - | 0.48 | 51.90% | - | - | -107.89% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 92.36% | 100.00% | 7.64% | - | - | - | 1.08 | -8.27% | - | - | 7.64% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 100.28% | 100.00% | -0.28% | - | - | - | 1.00 | 0.28% | - | - | -0.28% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 81.47% | 100.00% | 18.53% | - | - | - | 1.23 | -22.74% | - | - | 18.53% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CLAVO DE 4"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 71.18% | 100.00% | 28.82% | - | - | - | 1.40 | -40.50% | - | - | 28.82% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PARALES DE 3 X 3 X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 74.16% | 100.00% | 25.84% | - | - | - | 1.35 | -34.84% | - | - | 25.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 123.92% | 100.00% | -23.92% | - | - | - | 0.81 | 19.30% | - | - | -23.92% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 248686.67% | 100.00% | -248586.67% | - | - | - | 0.00 | 99.96% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 190.89% | 100.00% | -90.89% | - | - | - | 0.52 | 47.61% | - | - | -90.89% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 33.13% | 100.00% | 66.87% | - | - | - | 3.02 | -201.81% | - | - | 66.87% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 27.75% | 100.00% | 72.25% | - | - | - | 3.60 | -260.30% | - | - | 72.25% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5325.36 | -532436.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 689.14 | -68814.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 143.81% | 100.00% | -43.81% | - | - | - | 0.70 | 30.46% | - | - | -43.81% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.94 | -10094.00% | - | - | 99.02% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.99 | -899.00% | - | - | 89.99% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 60.23% | 100.00% | 39.77% | - | - | - | 1.66 | -66.03% | - | - | 39.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 106.27% | 100.00% | -6.27% | - | - | - | 0.94 | 5.90% | - | - | -6.27% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 666323.64% | 100.00% | -666223.64% | - | - | - | 0.00 | 99.98% | - | - | 0.00% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPELLO GRUESO GRIS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 244.08% | 100.00% | -144.08% | - | - | - | 0.41 | 59.03% | - | - | -144.08% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 128.36% | 100.00% | -28.36% | - | - | - | 0.78 | 22.09% | - | - | -28.36% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 56.48% | 100.00% | 43.52% | - | - | - | 1.77 | -77.07% | - | - | 43.52% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6508.78 | -650778.00% | - | - | 99.98% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 22.75% | 100.00% | 77.25% | - | - | - | 4.40 | -339.60% | - | - | 77.25% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 176.25% | 100.00% | -76.25% | - | - | - | 0.57 | 43.26% | - | - | -76.25% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.36 | -14736.00% | - | - | 99.33% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 169.07% | 100.00% | -69.07% | - | - | - | 0.59 | 40.85% | - | - | -69.07% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 446.87% | 100.00% | -346.87% | - | - | - | 0.22 | 77.62% | - | - | -346.87% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.21% | 100.00% | 91.79% | - | - | - | 12.17 | -1117.35% | - | - | 91.79% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 8.21% | 100.00% | 91.79% | - | - | - | 12.17 | -1117.35% | - | - | 91.79% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 46.08% | 100.00% | 53.92% | - | - | - | 2.17 | -117.02% | - | - | 53.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 53.96% | 100.00% | 46.04% | - | - | - | 1.85 | -85.32% | - | - | 46.04% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 53.96% | 100.00% | 46.04% | - | - | - | 1.85 | -85.32% | - | - | 46.04% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 33.48% | 100.00% | 66.52% | - | - | - | 2.99 | -198.69% | - | - | 66.52% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 2246.38% | 100.00% | -2146.38% | - | - | - | 0.04 | 95.55% | - | - | -2146.38% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
ADHERENTE ACRILICO ACRYLAC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 184.79% | 100.00% | -84.79% | - | - | - | 0.54 | 45.88% | - | - | -84.79% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
MASKING TAPE 1" X 25 YDS (60)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CORONA PARA DESBASTE 5" PULGADAS PROFESIONAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 3/8 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 123.75% | 100.00% | -23.75% | - | - | - | 0.81 | 19.19% | - | - | -23.75% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 79.07% | 100.00% | 20.93% | - | - | - | 1.26 | -26.47% | - | - | 20.93% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 83.43% | 100.00% | 16.57% | - | - | - | 1.20 | -19.86% | - | - | 16.57% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 71.88 | -7088.00% | - | - | 98.61% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 46.51% | 100.00% | 53.49% | - | - | - | 2.15 | -115.02% | - | - | 53.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.86% | 100.00% | 41.14% | - | - | - | 1.70 | -69.88% | - | - | 41.14% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 14.41 | -1341.00% | - | - | 93.06% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.78% | 86.12% | 84.34% | - | - | - | 48.46 | -4746.00% | - | - | 97.94% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.71% | 88.00% | 85.29% | - | - | - | 32.52 | -3152.24% | - | - | 96.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.73% | 84.00% | 83.27% | - | - | - | 114.92 | -11391.62% | - | - | 99.13% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 25.10% | 84.00% | 58.90% | - | - | - | 3.35 | -234.71% | - | - | 70.12% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SIKAGROUT-212 GP - 22.7 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 1.13% | 0.00% | -1.13% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CASA # 48
|
- | - | - | - | - | - | 1.30% | 1.25% | 27.78% | 63.05% | 35.27% | - | - | - | 2.27 | -126.99% | - | - | 55.95% | - | 0.00% |
|
OBRA CIVIL
|
- | - | - | - | - | - | 0.62% | 0.60% | 56.49% | 100.00% | 43.51% | - | - | - | 1.77 | -77.03% | - | - | 43.51% | - | 0.00% |
|
OBRA CIVIL - PRELIMINARES Y CIMENTACION
|
- | - | - | - | - | - | 0.07% | 0.07% | 88.33% | 100.00% | 11.67% | - | - | - | 1.13 | -13.21% | - | - | 11.67% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 171.89% | 100.00% | -71.89% | - | - | - | 0.58 | 41.82% | - | - | -71.89% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.34 | 66.00% | - | - | -194.12% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 272.11% | 100.00% | -172.11% | - | - | - | 0.37 | 63.25% | - | - | -172.11% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 5128.79 | -512779.00% | - | - | 99.98% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.89 | 11.00% | - | - | -12.36% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.66 | 34.00% | - | - | -51.52% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.23 | 77.00% | - | - | -334.78% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 101.20% | 100.00% | -1.20% | - | - | - | 0.99 | 1.19% | - | - | -1.20% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 58.71% | 100.00% | 41.29% | - | - | - | 1.70 | -70.32% | - | - | 41.29% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 87.74% | 100.00% | 12.26% | - | - | - | 1.14 | -13.97% | - | - | 12.26% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 127.04% | 100.00% | -27.04% | - | - | - | 0.79 | 21.29% | - | - | -27.04% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 75.63% | 100.00% | 24.37% | - | - | - | 1.32 | -32.23% | - | - | 24.37% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 115.75 | -11475.00% | - | - | 99.14% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 727.22 | -72622.00% | - | - | 99.86% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TUBO RECTANGULAR DE METAL DE 1" X 2" X 6 MTS.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.82 | -15482.00% | - | - | 99.36% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 153.33 | -15233.00% | - | - | 99.35% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 2.49 | -149.00% | - | - | 59.84% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 384.16 | -38316.00% | - | - | 99.74% | - | 0.00% |
|
('INDIRECTOS DE OBRA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('FLETES Y EXTRACCIONES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
DESALOJO DE MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1036.22 | -103522.00% | - | - | 99.90% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9672.31 | -967131.00% | - | - | 99.99% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 832.67 | -83167.00% | - | - | 99.88% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8839.64 | -883864.00% | - | - | 99.99% | - | 0.00% |
|
OBRA CIVIL - NIVEL 2 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.18% | 0.17% | 76.77% | 100.00% | 23.23% | - | - | - | 1.30 | -30.25% | - | - | 23.23% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.09% | 0.09% | 128.83% | 100.00% | -28.83% | - | - | - | 0.78 | 22.38% | - | - | -28.83% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 46604.44% | 100.00% | -46504.44% | - | - | - | 0.00 | 99.79% | - | - | 0.00% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.45 | 55.00% | - | - | -122.22% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6347.05% | 100.00% | -6247.05% | - | - | - | 0.02 | 98.42% | - | - | -6247.05% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.29 | -829.00% | - | - | 89.24% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.70 | 30.00% | - | - | -42.86% | - | 0.00% |
|
CURADOR CURASEAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DESENCOFRANTE BASE DE ACEITE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 441.31% | 100.00% | -341.31% | - | - | - | 0.23 | 77.34% | - | - | -341.31% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 294.21 | -29321.00% | - | - | 99.66% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 2.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SILLETA PARA MALLA SM100 RECUBRIMIENTO 7.5
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUROPORT DE 1 CM. X 4 PIES X 8 PIES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.05 | 95.00% | - | - | -1900.00% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.05% | 0.05% | 171.15% | 100.00% | -71.15% | - | - | - | 0.58 | 41.57% | - | - | -71.15% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9335.34 | -933434.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 100.00% | 100.00% | - | - | - | 6973.62 | -697262.00% | - | - | 99.99% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 66.63% | 100.00% | 33.37% | - | - | - | 1.50 | -50.07% | - | - | 33.37% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 65.56% | 100.00% | 34.44% | - | - | - | 1.53 | -52.54% | - | - | 34.44% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 39.87 | -3887.00% | - | - | 97.49% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 32.21% | 100.00% | 67.79% | - | - | - | 3.10 | -210.42% | - | - | 67.79% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 545.26 | -54426.00% | - | - | 99.82% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.43 | -67443.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 121.38 | -12038.00% | - | - | 99.18% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 133.70 | -13270.00% | - | - | 99.25% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 106.55% | 100.00% | -6.55% | - | - | - | 0.94 | 6.15% | - | - | -6.55% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 631.67% | 100.00% | -531.67% | - | - | - | 0.16 | 84.17% | - | - | -531.67% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 22.61 | -2161.00% | - | - | 95.58% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 552.95 | -55195.00% | - | - | 99.82% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 148.06 | -14706.00% | - | - | 99.32% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 82.98 | -8198.00% | - | - | 98.79% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 321.91 | -32091.00% | - | - | 99.69% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1575.04 | -157404.00% | - | - | 99.94% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 928.14 | -92714.00% | - | - | 99.89% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 646.90 | -64590.00% | - | - | 99.85% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 18.34% | 100.00% | 81.66% | - | - | - | 5.45 | -445.12% | - | - | 81.66% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 2607.99 | -260699.00% | - | - | 99.96% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.07% | 0.07% | 0.00% | 100.00% | 100.00% | - | - | - | 21170.63 | -2116963.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1037.38 | -103638.00% | - | - | 99.90% | - | 0.00% |
|
OBRA CIVIL - NIVEL 1 | MUROS Y LOSAS
|
- | - | - | - | - | - | 0.21% | 0.21% | 54.86% | 100.00% | 45.14% | - | - | - | 1.82 | -82.27% | - | - | 45.14% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.11% | 0.11% | 103.11% | 100.00% | -3.11% | - | - | - | 0.97 | 3.01% | - | - | -3.11% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
CAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.55 | 45.00% | - | - | -81.82% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 115.88% | 100.00% | -15.88% | - | - | - | 0.86 | 13.70% | - | - | -15.88% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 4.5/4.5
|
- | - | - | - | - | - | 0.02% | 0.02% | 75.95% | 100.00% | 24.05% | - | - | - | 1.32 | -31.67% | - | - | 24.05% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 7/7
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 48.72 | -4772.00% | - | - | 97.95% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 22.75% | 100.00% | 77.25% | - | - | - | 4.40 | -339.60% | - | - | 77.25% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 666.43 | -66543.00% | - | - | 99.85% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/2 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 252.69% | 100.00% | -152.69% | - | - | - | 0.40 | 60.43% | - | - | -152.69% | - | 0.00% |
|
ACERO DE 3/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 209.89% | 100.00% | -109.89% | - | - | - | 0.48 | 52.36% | - | - | -109.89% | - | 0.00% |
|
ACERO DE 5/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 132.16% | 100.00% | -32.16% | - | - | - | 0.76 | 24.33% | - | - | -32.16% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.01% | 0.01% | 184.18% | 100.00% | -84.18% | - | - | - | 0.54 | 45.70% | - | - | -84.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 963.70% | 100.00% | -863.70% | - | - | - | 0.10 | 89.62% | - | - | -863.70% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.07% | 0.06% | 110.02% | 100.00% | -10.02% | - | - | - | 0.91 | 9.11% | - | - | -10.02% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3001 M3
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 100.00% | 100.00% | - | - | - | 11409.86 | -1140886.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO VIVIENDA INDUSTRIAL TNM 3/8 3000 PSI
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 8523.31 | -852231.00% | - | - | 99.99% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 66.57% | 100.00% | 33.43% | - | - | - | 1.50 | -50.21% | - | - | 33.43% | - | 0.00% |
|
DUROPORT DE 1' X 1' X 14
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 359.59 | -35859.00% | - | - | 99.72% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 15 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 8 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 10 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DISCO SEPARADORES PARA MUROS DE 12 CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.06 | 94.00% | - | - | -1566.67% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 12.18 | -1118.00% | - | - | 91.79% | - | 0.00% |
|
DESENCOFRANTE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.33 | -1033.00% | - | - | 91.17% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.85 | 15.00% | - | - | -17.65% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
GRANZA DE ARENA BLANCA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 27.63 | -2663.00% | - | - | 96.38% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 675.81 | -67481.00% | - | - | 99.85% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 180.96 | -17996.00% | - | - | 99.45% | - | 0.00% |
|
REGLA DE 3"X3"X10'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 101.41 | -10041.00% | - | - | 99.01% | - | 0.00% |
|
PLYWOOD FENOLICO DE 4' X 8' X 3/4''
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 393.44 | -39244.00% | - | - | 99.75% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1925.08 | -192408.00% | - | - | 99.95% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1134.43 | -113343.00% | - | - | 99.91% | - | 0.00% |
|
MATERIALES
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 790.65 | -78965.00% | - | - | 99.87% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
ALQUILER PUNTAL METALICO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1267.91 | -126691.00% | - | - | 99.92% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 100.00% | 100.00% | - | - | - | 29062.75 | -2906175.00% | - | - | 100.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3187.54 | -318654.00% | - | - | 99.97% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.09% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 25875.21 | -2587421.00% | - | - | 100.00% | - | 0.00% |
|
ACABADOS GRISES
|
- | - | - | - | - | - | 0.16% | 0.15% | 21.64% | 100.00% | 78.36% | - | - | - | 4.62 | -362.06% | - | - | 78.36% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 40.56% | 100.00% | 59.44% | - | - | - | 2.47 | -146.56% | - | - | 59.44% | - | 0.00% |
|
('AGLOMERADOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 213.55% | 100.00% | -113.55% | - | - | - | 0.47 | 53.17% | - | - | -113.55% | - | 0.00% |
|
CONCRETO 4001PSI MAXIPASTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 83.59 | -8259.00% | - | - | 98.80% | - | 0.00% |
|
MONOCAPA GRIS
|
- | - | - | - | - | - | 0.01% | 0.01% | 222.68% | 100.00% | -122.68% | - | - | - | 0.45 | 55.09% | - | - | -122.68% | - | 0.00% |
|
CEMENTO UGC
|
- | - | - | - | - | - | 0.00% | 0.00% | 103.62% | 100.00% | -3.62% | - | - | - | 0.97 | 3.49% | - | - | -3.62% | - | 0.00% |
|
('ACERO DE REFUERZO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 41.18% | 100.00% | 58.82% | - | - | - | 2.43 | -142.87% | - | - | 58.82% | - | 0.00% |
|
CLAVO ACERADO DE 2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ALAMBRE DE AMARRE
|
- | - | - | - | - | - | 0.00% | 0.00% | 14.27% | 100.00% | 85.73% | - | - | - | 7.01 | -600.76% | - | - | 85.73% | - | 0.00% |
|
ELECTROMALLA 6X6 DE 9/9
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G40 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 11.24 | -1024.00% | - | - | 91.10% | - | 0.00% |
|
ACERO DE 3/8 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 17.38 | -1638.00% | - | - | 94.25% | - | 0.00% |
|
CLAVO DE 3"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 3.47 | -247.00% | - | - | 71.18% | - | 0.00% |
|
ACERO DE 1/4 X 6 MT G60 LEG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 14.41 | -1341.00% | - | - | 93.06% | - | 0.00% |
|
ELECTROMALLA 6X6 6/6 LISA
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1730.09 | -172909.00% | - | - | 99.94% | - | 0.00% |
|
('FERRETERIA',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 15.53% | 100.00% | 84.47% | - | - | - | 6.44 | -544.03% | - | - | 84.47% | - | 0.00% |
|
DUROPORT DE 4' X 8' DE 2 PLGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
NYLON NEGRO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 862.86 | -86186.00% | - | - | 99.88% | - | 0.00% |
|
BROCAS PARA CONCRETO SDS 1/2 X 6"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.58 | -558.00% | - | - | 84.80% | - | 0.00% |
|
('COMBUSTIBLES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
COMBUSTIBLE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 9.83 | -883.00% | - | - | 89.83% | - | 0.00% |
|
('ADITIVOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
SIKADUR 31 HI-MOD GEL 5 KGS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 23.46 | -2246.00% | - | - | 95.74% | - | 0.00% |
|
('AGREGADOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 25.93 | -2493.00% | - | - | 96.14% | - | 0.00% |
|
PIEDRIN DE 1/2"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 19.18 | -1818.00% | - | - | 94.79% | - | 0.00% |
|
ARENA DE RIO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 6.75 | -575.00% | - | - | 85.19% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
ADHESIVO CAPA GRUESA 40 KG
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 498.41 | -49741.00% | - | - | 99.80% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 680.79 | -67979.00% | - | - | 99.85% | - | 0.00% |
|
('MADERA',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
TABLA 1" X 12" X 10'
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 1665.98 | -166498.00% | - | - | 99.94% | - | 0.00% |
|
('CONCRETO',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9281.66 | -928066.00% | - | - | 99.99% | - | 0.00% |
|
CONCRETO CONVENCIONAL 4003 M3
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 80.67 | -7967.00% | - | - | 98.76% | - | 0.00% |
|
CONCRETO CONVENCIONAL 3003 M3
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 100.00% | 100.00% | - | - | - | 9200.99 | -919999.00% | - | - | 99.99% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 10.29% | 100.00% | 89.71% | - | - | - | 9.72 | -872.15% | - | - | 89.71% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 10.29% | 100.00% | 89.71% | - | - | - | 9.72 | -872.15% | - | - | 89.71% | - | 0.00% |
|
SUBCONTRATO IMPERMEABILIZACION
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 100.00% | 100.00% | - | - | - | 3654.77 | -365377.00% | - | - | 99.97% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE BOMBEO DE CONCRETO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 1506.18 | -150518.00% | - | - | 99.93% | - | 0.00% |
|
SERVICIOS DE MANO DE OBRA
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 100.00% | 100.00% | - | - | - | 24620.20 | -2461920.00% | - | - | 100.00% | - | 0.00% |
|
('HERRAMIENTA Y EQUIPO',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
('ALQUILER EQUIPO DE CONSTRUCCION',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
ALQUILER ANDAMIOS METALICOS COMPLETOS C/(2MARCO, 2CRUCERTAS Y 4CONECTORES)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 100.00% | 100.00% | - | - | - | 155.98 | -15498.00% | - | - | 99.36% | - | 0.00% |
|
INSTALACIONES
|
- | - | - | - | - | - | 0.23% | 0.22% | 1.52% | 86.12% | 84.60% | - | - | - | 56.53 | -5552.84% | - | - | 98.23% | - | 0.00% |
|
INSTALACIONES ELECTRICAS
|
- | - | - | - | - | - | 0.12% | 0.12% | 2.71% | 88.00% | 85.29% | - | - | - | 32.52 | -3152.24% | - | - | 96.93% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 2.79% | 88.00% | 85.21% | - | - | - | 31.58 | -3057.52% | - | - | 96.83% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO INSTALACION ELECTRICA
|
- | - | - | - | - | - | 0.12% | 0.11% | 0.00% | 88.00% | 88.00% | - | - | - | 31575.18 | -3157418.32% | - | - | 100.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 88.00% | 88.00% | - | - | - | 947.26 | -94625.84% | - | - | 99.89% | - | 0.00% |
|
INSTALACIONES HIDROSANITARIAS
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.19% | 84.00% | 83.81% | - | - | - | 438.47 | -43747.33% | - | - | 99.77% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 6.58% | 84.00% | 77.42% | - | - | - | 12.77 | -1177.11% | - | - | 92.17% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
IMPREVISTOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 802.66 | -80166.20% | - | - | 99.88% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
POLIDUCTO NEGRO DE 1"
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
CAJA RECTANGULAR METALICA DE 2' X 4'
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 84.00% | 84.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
('SUB. CONTRATO MO. DE PLOMERIA',)
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
SUB CONTRATO SERVICIOS DE PLOMERIA
|
- | - | - | - | - | - | 0.11% | 0.10% | 0.00% | 84.00% | 84.00% | - | - | - | 26755.39 | -2675438.60% | - | - | 100.00% | - | 0.00% |
|
ACABADOS FINALES
|
- | - | - | - | - | - | 0.45% | 0.43% | 1.51% | 0.00% | -1.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ACABADOS CEMENTICIOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.10% | 0.09% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
JARDINIZACION
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LIMPIEZA FINAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.09% | 0.00% | -37.09% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.09% | 0.00% | -37.09% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 37.09% | 0.00% | -37.09% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO DE MANO DE OBRA DIRECTA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO DE TABLAYESO',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO MO DE TABLAYESO
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISOS Y AZULEJOS
|
- | - | - | - | - | - | 0.07% | 0.06% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PISOS Y AZULEJOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 1
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
AZULEJO TIPO 2
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ESTUQUE
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 2
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PISO CERAMICO TIPO 3
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PEGAMIX 20KG
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATO INSTALACION DE PISO',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATO COLOCACION DE PISO/AZULEJO
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ARTEFACTOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 1.56% | 0.00% | -1.56% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('MATERIALES',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 4.51% | 0.00% | -4.51% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('ELECTRICIDAD',)
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
EXTRACTOR DE OLORES 50CM
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('PLOMERIA',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.40% | 0.00% | -0.40% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVATRASTOS DE DOBLE FOSA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PILA DE 1 LAVADERO DERECH. O IZQ.
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS DE PEDESTAL
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
LAVAMANOS IMPORTADO
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
INODORO 1
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
DUCHA IMPORTADA
|
- | - | - | - | - | - | 0.01% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
REPOSADERA DE CONCRETO 0.22X0.22 CON TAPADERA REDONDA
|
- | - | - | - | - | - | 0.00% | 0.00% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.04% | 0.04% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PUERTAS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.06% | 0.06% | 6.55% | 0.00% | -6.55% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
VENTANAS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.08% | 0.08% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
ZOCALOS, PASAMANOS Y CELOSIA
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.02% | 0.02% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
PINTURA INTERIORES Y EXTERIORES
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.03% | 0.03% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
COMPLEMENTARIOS EN CULATAS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUBCONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
('SUB. CONTRATOS',)
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |
|
SUBCONTRATOS
|
- | - | - | - | - | - | 0.01% | 0.01% | 0.00% | 0.00% | 0.00% | - | - | - | 0.00 | 100.00% | - | - | 0.00% | - | 0.00% |